22 Pa. Super. 564 | Pa. Super. Ct. | 1903
Opinion by
On August 11, 1897, tbe defendant owners entered into a written agreement with tbe defendant contractor, providing for the erection of a double dwelling house upon a lot owned by former. The agreement provided that the contractor “shall and will, within the space of three months from the date hereof, in a good and workmanlike manner and according to the best of his art and skill, and according to the plans and specifications furnished by an architect, which are to be taken and considered a part of this agreement, well and substantially erect, build and set up and finish the house mentioned in above mentioned plans and specifications.”
In pursuance of the agreement, the contractor, as authorized to do, entered upon the erection and construction of the said house. The cellar was excavated and the foundation walls erected; some of the lumber furnished by parties other then the plaintiffs was upon the ground and a part of it perhaps in place. The written agreement, under which this work was done, was marked “ Cancelled September 9,1897; all liens herein contained revoked by parties; new contract made this date.”
On the same day (September 9), a new agreement was entered into differing in many respects from the original one made on August 11, and containing especially this clause: “Seventh. No lien shall be filed against the building by the contractor or subcontractors nor by any of the material men or workmen.”
On the same day (September 9), according to the plaintiffs’ testimony, the contractor ordered from the plaintiffs certain material for the said buliding, part of which was delivered September 11, and the remainder later.
An apportioned lien was filed February 25, 1898, describing the double building as separate erections and claiming 1395.21 from each. The character, quality and amount of the materials are set forth, alleging that “ all of which materials were so furnished during the continuous erection and. construction of said new buildings which were finished within the six months last past and was commenced on the 18th day of August A. D. 1897, and completed continuously between that date and the 22d day of December, 1897.”
The act of assembly of June 26, 1895, P. L. 369, provides: “ That no contract for the erection of the whole or any part of any building hereafter made and no stipulation separately made as partof anysuch contract, whereby it is soughtto deprive or hinder a contractor, subcontractor, material man or other person from filing or maintaining a lien, commonly called a mechanic’s lien, for work done or material furnished to such building, or to any part thereof, shall operate to defeat the right of any subcontractor, material man or other person to file and maintain such a lien, unless such contractor or the stipulation shall specifically covenant against such lien by subcontractor or other person and unless said stipulation shall be put in writing and signed by the parties thereto prior to the time authority ,is given to the principal contractor to proceed with said Avork, and unless said contract or said stipulation shall be filed with the prothonotary of the county where the land lies for record within ten days after its execution.”
The plaintiffs contend that the stipulation against liens in the contract of September 9,1897, was wholly void as to them, under the provisions of the act of assembly, because it was not put in writing and signed by the parties thereto prior to the time authority was given to the principal contractor to proceed with the work of building the houses provided for in the contract.
The work having already proceeded to such an extent that it gave notice to all the world that the buildings were in process of erection and no stipulation against liens then appearing of record, they, the plaintiffs, were justified in furnishing the materials' upon the credit and faith of.-.the building, relying upon their right to file a mechanic’s lien .therefor.
The trial judge in the court below tried the case upon the
This view of the case was entirely erroneous. It was not a question of fraud or collusion. The motive which influenced the parties to the contract did not properly enter into the consideration of the ease. It was a question of the legal right of the defendant owners -and the defendant contractor to enter into a contract after the building had been commenced and partially completed to make a valid stipulation against liens. The contract of August 11 undoubtedly authorized and indeed required the plaintiff to proceed with the work of the erection of these buildings immediately. He did proceed to such an extent, as already stated, that the foundation walls were completed and perhaps some of the sills and joists laid. This was notice to all the world that the houses were being erected and an examination of the records at that time showing that no stipulation against liens had been made, anyone contemplating the furnishing of materials for the said houses had the right to rely upon the status as then existing, and indeed it may be seriously questioned whether, even if the plaintiffs had actual notice of the cancellation of the first agreement and of the making and recording of the second agreement, they would have been bound thereby. The provisions of the act of 1895, supra, are very specific. No contract shall operate to defeat the right of any subcontractor, material man or other person to file and maintain such a lien, unless the stipulation against liens shall be put in writing and signed by the parties thereto prior to the time authority is given to the principal contractor to proceed with the work. It is plain, therefore, that the rights of the plaintiff
We see nothing erroneous in allowing the defendant’s counsel to cross-examine the witness called by plaintiff as on cross-examination.
It is not necessary to follow the appellant through all of the thirty-two assignments of error with which his paper-book is encumbered. What we have said goes to the root of the case and sufficiently indicates the misconception of the court caused by leaving out of view the plain requirements of the act of assembly which led to all the subsequent mistakes. Judgment reversed and a new venire awarded.