58 Wash. 589 | Wash. | 1910
Action upon bond, to recover for breach of building contract. Judgment for plaintiffs, and the surety company appeals.
The respondents alleged a breach of the contract in three particulars: Failure to supply proper material, furnish competent workmen, or to prosecute the work with diligence. The answer contained nothing other than denials. The
The next day the architects gave respondents a certificate, to the effect that the contractor had failed to comply with the contract in the particulars complained of by respondents, and gave it as their judgment that, because of these defaults, the owner was justified in terminating the contract and taking possession of the building. This certificate was in accordance with a stipulation in the contract. The respondents served a copy of this certificate upon the contractor, with a further notice that in three days they would take possession. Copies of the certificate and notice were also served upon the appellant on February 18, and on February 16 respondents mailed a verified statement of the particulars in which he claimed default to the home office of the appellant. On February 22 a further written statement was mailed,
It has never been held that, every time a contractor put in a defective board which was changed, on his attention being called to it, or sometimes sawed a timber off too short, or cut his joist too long, or erred in other minor details which on notice were all corrected, these constituted such breaches of the contract as would relieve a surety not receiving notice. In building contracts substantial compliance is the requirement, and it may be assumed that, from time to time as the work progresses, there will be technical violations of the specifications which will require correction. Yet to hold that these were breaches of the contract, requiring notice, no loss having been sustained by the owner, would be a strict interpretation of the contract never followed by this court. The notice provision is inserted for the benefit of the surety. It is to give him notice of the doing or neglecting to do something by the contractor which will result in loss to the owner primarily, and thus subj ect the surety to a liability. And since the purpose of the provision is protection to the surety, when it appears that notice is given in ample
All that need be said concerning the next assignment is that the evidence amply justified the giving of the certificate by the architect, and under the contract its receipt by the respondents was a justification for them to proceed as they did. In this regard, due notice of the fact was given appellant, and it had ample opportunity to take charge and save respondents and itself from further loss.
As to the next assignment, the contract provided that, in case the owner should be compelled to take charge of the building and finish the contract, the cost should be audited and certified by the architects, and such audit and certificate should be conclusive upon the parties. Such stipulations are usual in contracts of this character, and the courts recognize the same binding force of the agreement made by the parties in this respect as in any other. Having stipulated
Finding no error, the judgment is affirmed.