Layne-Minnesota Co. v. Regents of the University of MinnesotaLayne-Minnesota Co. v. Regents of the University of Minnesota
Appeal from an order denying plaintiff’s motion to compel arbitration under Minn. St. 572.09 of the Uniform Arbitration Act adopted by Minnesota in 1957. 1
“A caisson is a column of concrete and steel upon which the building rests. The contract called for a total of 56 caissons with varying diameters of 4, 5 or 6 feet. Each caisson extends from the ground surface to whatever depth was necessary to get an 8-inch penetration into bedrock which was approximately 25 feet below the surface. After excavation to bedrock was completed the holes were filled with concrete and reinforcing steel to form a set of reinforced concrete legs upon which the buildings would rest.”
2
Attached to the specifications, pursuant to which the plaintiff made its bid, were reports on preconstruction borings which had been conducted for defendant by the Minnesota Test Boring Company. These reports were provided for what value they might have to the contractor but were not guaranteed by defendant as accurate or indicative of all soils at the site. The contract included a modification clause and an arbitration clause hereafter quoted. During the course of the construction plaintiff encountered boulders, limestone slabs, and underground water in amounts and at locations not indicated by the plans and specifications. Plaintiff claims that a requested modification of the contract and a claim for additional compensation was made and denied. We are not informed whether this occurred before or after completion of the work.
3
Defendant does not deny that a request was made, but the particulars concerning the time, nature, and manner of the request, and of defendant’s denial, are not disclosed by the record. We assume that the request was denied and that plaintiff completed the work notwithstanding this controversy.
4
In any event, after a denial,
The pertinent provisions of the contract are as follows:
“Section 1-16 Changes, Extras, Etc.
“* * * Should the Contractor find at any time during the progress of the work that in his judgment existing conditions demand or malee desirable or beneficial a modification in the requirements covering any particulars or items, it shall be his duty and he is required to promptly report in writing each such matter to the Supervising Engineer for his decision and instruction.”
“Section 1-23 Disputes.
“If during progress of the work, any disputes, claims or questions arise between the owner and the contractor concerning the work, the architect/engineer shall be consulted and his decision shall be final. However, decision may -be submitted to arbitration.”
“Section 1-24 Arbitration.
“All disputes, claims or questions subject to arbitration under this contract shall be submitted to arbitration in accordance with the provisions, then obtaining of the Uniform Arbitration Act. Chapter 633, Laws of Minnesota, 1957, and this Agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.”
Essentially the question presented to the trial court and here is whether or not the parties intended by their contract to submit to arbitration a dispute arising over a claim for additional compensation occasioned by unanticipated difficulties in performing the work required by the contract.
As the question was submitted to the trial court and here, the arguments of the parties were primarily directed toward seeking a final judicial determination of whether the claim presents an issue referable to arbitration. We are urged, as was the trial court, to decide the question under the rules relating to the construction of contracts without reference to any specific provisions of the' Uniform Arbitration Act. This emphasis overlooks section 1-24 of the contract which makes the act an integral part of the contract, thereby requiring a consideration of those provisions of the act which were intended to apply and control a judicial determination of the very question presented.
One of the fundamental objectives of the act was to encourage and facilitate the arbitration of disputes by providing a speedy, informal, and relatively inexpensive procedure for resolving controversies arising out of commercial transactions, including the labor-
In this case the plaintiff vigorously contends that its claim for additional compensation is a controversy which arose during the progress of the work; that it concerns the work; and is one which the parties clearly agreed to arbitrate. Defendant, with equal vigor, contends that the claim is not a controversy concerning the work, and that it is clearly not one intended to be arbitrable. These conflicting contentions demonstrate most forcibly that the language of the contract does not clearly express the intention of the parties. Moreover, our determination would have to be based solely on the language of the contract since no other evidence relevant to the question presented was submitted to the trial court. We conclude that from the language alone a reasonable basis exists for arguing either contention. This the parties concede.
We believe that where upon application to compel arbitration the court is unable to ascertain the clear intent of the parties as to the scope of the arbitration clause in a contract, the sole issue is whether or not an agreement to arbitrate exists. Minn. St. 572.09 provides:
“(a) On application of a party showing an agreement described in section 572.08, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration, but if the opposing party denies the existence of the agreement to arbitrate, the court shall proceed summarily to the determination of the issue so raised and shall order arbitration if found for the moving party, otherwise, the application shall be denied.
“(b) On application, the court may stay an arbitration proceeding commenced or threatened on a showing that there is no agreement to arbitrate. Such an issue, when in substantial and bona fide dispute, shall be forthwith and summarily tried and the stay ordered if found for the moving party. If found for the opposing party, the court shall order the parties to proceed to arbitration.
* * * * *
‘'(e) An order for arbitration shall not be refused on the ground that the claim in issue lacks merit or bona fides or because any fault or grounds for the claim sought to be arbitrated have not been shown.”
Section 572.19, subd. 1, provides:
“Upon application of a party, the court shall vacate an award where:
#
“( 3) The arbitrators exceeded their powers;
* * * * *
"(5) There was no arbitration agreement and the issue was not adversely determined in proceedings under section 572.09 and the party did not participate in the arbitration hearing without raising the objection; * * *.”
So far as we can find, the construction and application of these provisions to the question presented is a matter of first impression. There are no legislative records which disclose the specific legislative intent underlying these provisions at the time the act was adopted in this state. However, the records of the National Conference of Commissioners on Uniform Laws, and particularly the writings of the chairman of the subcommittee that undertook the drafting of the act, disclose that the problem of judicial interference with, the question of arbitrability was intended to be governed by § 2 of the Uniform Act, now Minn. St. 572.09.
13
Apart from these writings, the language of
This case illustrates the difficulties of determining the true intent of the parties. We do not have before us any of the facts that most certainly would be presented in submitting the issue of arbitrability to the arbitrators. One of the claims made by plaintiff in its request for arbitration is that defendant withheld information concerning the condition of the soil, thus forcing plaintiff to rely solely on the pre-bidding exploration report of the Minnesota Test Boring Company. The particulars prompting this claim, and the evidence, if any, which may support plaintiff’s contention that this is part of the dispute arising “during progress of the work” and “concerning the work,” are not before us. 14
The fact that the act directs the court to “summarily” determine the issue of arbitrability was not intended to foreclose the taking of testimony relevant to that issue where the intent of the parties can be determined from the language of the contract. When that is not possible or even probable, practical considerations alone would, in most cases, indicate that the issue of arbitrability be referable to arbitration.
Minn. St. 572.09(e) reinforces our conclusion. The act intended that arbitrators decide both questions of law and fact.
15
Arbitration is not to be refused because a party seeks to establish that the “claim in issue lacks merit or bona fides or because any fault or grounds for the claim * * * have not been shown.” On the preliminary application to compel arbitration a court is barred from examining into the merits of that defense. No such limitation is im
Defendant argues finally that the contract requires arbitration only if both parties consent. Although the contract uses the word “may” in section 1-23, in section 1-24 it requires that disputes “shall be submitted to arbitration in accordance with the provisions” of the act. Unmistakably, the parties intended that any arbitration would be statutory and not governed by common-law principles. Minn. St. 572.08 expressly declares that an agreement to arbitrate shall be “irrevocable, save upon such grounds as exist at law or in quity for the revocation of any contract.” 16 When the parties incorporated the act into their contract, the agreement to arbitrate became irrevocable by force of this section unless the contract expressly provides for revocation. Under principles relating to contracts, a provision reserving the right of revocation is enforceable, 17 and by the language of § 572.08 such a provision in an agreement would be enforceable as an exception to irrevocability. However, we are not persuaded that the terms of the contract before us include any such provision.
Reversed with instructions to enter an order directing the parties to proceed with arbitration.
Notes
This act was drafted and approved by the National Conference on Uniform Laws and thereafter approved by the American Bar Association in 1955. In 1957, under the sponsorship of the Minnesota State Bar Association, Minnesota was the first state to adopt the act. Wyoming, Massachusetts, Illinois, and Arizona have subsequently adopted it. 9 Uniform Laws Annotated, pocket part, p. 36.
The record does not disclose these facts concerning the nature of the work but this statement, taken from plaintiff’s brief, is not challenged by defendant.
Apart from the moving papers, the record contains only the written request for arbitration and those parts of the contract which the parties deemed pertinent.
Plaintiff’s written request for arbitration includes this statement: “That
Although in the minority, Minnesota as early as 1943 adopted the policy of favoring arbitration and held that an agreement to arbitrate a future dispute could be specifically enforced and repudiated the common-law doctrine of revocability. Park Const. Co. v. Independent School Dist.
Minn. St. 572.09(a).
Minn. St. 572.09(b).
Minn. St. 572.19.
Minn. St. 572.20.
Minn. St. 572.18 and 572.21.
Minn. St. 572.19, subd. 1(5).
The draftsmen of the Uniform Act had this problem in mind because it had arisen under the New York arbitration law which, with its prototypes in other states, served as a base for the committee’s effort to draft a modern, simplified act. Pirsig, Some Comments on Arbitration Legislation and the Uniform Act, 10 Vand. L. Rev. 685, 692 to 699.
Pirsig,
The Minnesota Uniform Arbitration Act and the Lincoln Mills Case,
42 Minn. L. Rev. 333, 346, 348; Pirsig,
Some Comments on, Arbitration Legislation and the Uniform Act,
10 Vand. L. Rev. 685, 692.
If plaintiff by this claim charges fraud in the inducement of the contract, it might be observed that it is difficult to understand how such a dispute could arise “during progress of the work.”
Pirsig, Some Comments on Arbitration Legislation and the Uniform Act, 10 Vand. L. Rev. 685, 695.
Footnote 5, supra.
Raymond v. McKenzie,