29 A.D. 298 | N.Y. App. Div. | 1898
The subject of inquiry in this case is, whether the plaintiff’s assignors were entitled to be paid under the contract set forth in the complaint, for 727 cubic yards of cut stone masonry, or only for 64 cubic yards thereof. On a construction of all the material parts of the contract relating to that subject, the court below held that the plaintiff could recover only for the 64 cubic yards.
Clause “ B ” annexed to the contract provided that, to prevent all disputes and litigations, it was further agreed by and between the parties to the contract that the engineer should in all cases determine the amount or the quantity of the several kinds of work which were to be paid for under the contract, and should determine all questions in relation to the work and construction thereof, and
The engineer’s determination under the existing circumstances that only sixty-four cubic yards of cut stone masonry were to be paid for is conclusive, under the terms of the contract. The plaintiff’s assignors received the stone from the city without expense, precisely as they would have taken the stone from the old arch, and used it in substitution for the old stone. If they had declined to use the stone, a different question would be presented, but they accepted that which the city supplied, without objection, and there is no legal reason, and certainly no equitable one, why they should recover against the city the large sum they demand on account of the substitution of the one stone for the other accepted by them and used by them in the work, apparently without protest.
The judgment appealed from, we think, was right, and should be affirmed, with costs.
Van Brunt, P. J., O’Brien, Ingraham and McLaughlin, JJ., concurred.
Judgment affirmed, with costs.