Opinion
In thеse consolidated appeals, the plaintiff, John Lathrop, and the intervening plaintiff, Olin Corporation-New Haven Copper Company (Olin), 1 appeal from the summary judgment rendered by the trial court in favor of the defendant, Malcolm Pimie, Inc. 2 The dispositive issue on appeal is whether the court properly determined that no genuine issue of material fact existed as to whether the seven year statute of limitations set forth in General Statutes § 52-584a applies in the present case. The plaintiffs argue that a genuine issue of material fact exists as to whether the defendant provided services in connection with “an improvement to real property” within the meaning of § 52-584a (a). We agree with the plaintiffs that a genuine issue of material fact exists. 3 Accordingly, we reverse the judgment of the trial court granting summary judgment in favor of the defendant.
The following facts and procedural history are relevant to our review of the plaintiffs’ appeals. The present appeals stem from a negligence action arising from injuries that Lathrop, an Olin employee, allegedly sustained after he trippеd due to a sunken concrete cap that had been placed in the floor of a factory owned by Olin. Olin previously had contracted with the defendant, a professional engineering firm, to test for soil contamination. The defendant, in turn, contracted with a subcontractor, Glacier Drilling Company, LLC (Glacier), to drill boring holes through the factory floor in order to providе access to the soil. Glacier began drilling on December 27, 2004, and completed its services on January 17,2005. Under its contract with the defendant, Glacier also was responsible for filling the boring holes by using a process known as “backfilling.” The contract between Glacier and the defendant specified how the backfilling would be performed. It provides in relevant part: “All . . . borings will bе sealed with a grout mixture of 95 percent by weight Portland cement and 5 percent . . . bentonite . . . .” The top of the hole,
however, was to be covered by a concrete cap that would be of equal level with the factory floor. The plaintiffs allege that at least one hole was
Lathrop served the defendant with a complaint on Mаrch 26, 2008. On June 13,2008, Olin filed an intervening complaint against the defendant to recover the workers’ compensation benefits that it had paid to Lathrop. The defendant then filed a complaint against Glacier on August 26, 2008, seeking apportionment of liability pursuant to General Statutes § 52-102b. On September 24, 2008, Lathrop filed an amended complaint in order to assert a claim for money damages against Glacier. Thereafter, both Glacier and the defendant filed answers and special defenses denying the material allegations of Lathrop’s amended complaint.
On December 10, 2009, the defendant and Glacier filed a motion for summary judgment, arguing that no genuine issue of material fact existed and that they were entitled to judgment as a matter of law beсause Lathrop’s negligence action was barred by the three year hmitation period of General Statutes § 52-584. Lathrop filed an objection on June 16, 2010, arguing that his negligence action was not time barred because he had filed his complaint within the seven year limitation period set forth in § 52-584a. On June 22, 2010, the court heard oral argument on the motion. On July 16, 2010, the court issued its memorandum of decision granting the motion for summary judgment. These appeals followed.
On appeal, the plaintiffs claim that the court improperly concluded that the negligence action was barred under § 52-584, and that there exists a genuine issue of material fact as to whether the defendant had provided services in connection with “an improvement to real propеrty” within the meaning of § 52-584a. The defendant argues that the court properly determined that the three year statute of repose set forth in § 52-584 barred the plaintiffs’ negligence action, and that the court properly determined that the seven year statute of limitations set forth in § 52-584a does not apply. We agree with the plaintiffs.
“The standard of review of a trial court’s decision to grant summary judgment is well established. [W]e must decide whether the trial court erred in determining that there was no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. ... In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party. . . . The test is whether a party would be entitled to a directed verdict on the same facts. ... A material fact is a fact which will make a difference in the result of the case. . . . [I]ssue-finding, rather than issue-determination, is the key to the procedure. . . . [T]he trial court does not sit as the trier of fact when ruling on a motion for summary judgment. . . . [Its] function is not to decide issues of material fact, but rather to determine whether any such issues exist. . . .
“The party seeking summary judgment has the burden of showing the absence of any genuine issue [of] material facts which, under applicable principles of substantive law, entitle him to a judgment as a matter of law . . . and the party opposing such a motion must provide an evidentiary foundation to demonstrate the existence of a genuine issue of material fact. . . . Where the trial court is presented
“Practice Book § 17-49 provides that summary judgment shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party. . . . The party moving for summary judgment has the burden of showing the absence of any genuine issue of material fact and that the party is, therefore, еntitled to judgment as a matter of law. . . . Our review of the trial court’s decision to grant [the defendant’s] motion for summary judgment is plenary. . . . Issues of statutory construction . . . are also matters of law subject to our plenary review.” (Internal quotation marks omitted.)
Plato Associates, LLC
v.
Environmental Compliance Services, Inc.,
The defendant’s motion for summary judgment was granted because the court found that the three year statute of repose contаined in § 52-584 applied, thus barring the plaintiffs’ negligence action. The plaintiffs argued that the seven year statute of limitations in § 52-584a should have been applied, and therefore the action should be allowed to proceed. We believe it helpful to begin our discussion with an examination of the two statutes in question.
Section 52-584 provides in relevant part: “(a) No action tо recover damages for injury to the person . . . caused by negligence . . . shall be brought but within two years from the date when the injury is first sustained or discovered or in the exercise of reasonable care should have been discovered, and except that no such action may be brought more than three years from the date of the act or omission complained of . . . .” (Emphasis addеd.) Section 52-584a (a) provides in relevant part: “No action . . . whether in contract, in tort, or otherwise, (1) to recover damages (A) for any deficiency in the design, planning, contract administration, supervision, observation of construction or construction of, or land surveying in connection with, an improvement to real property . . . (C) for injury to the person . . . arising out of any such deficiency, or (2) for contribution or indemnity which is brought as a result of any such claim for damages shall be brought against any architect, professional engineer or land surveyor performing or furnishing the design, planning, supervision, observation of construction or construction of, or land surveying in connection with, such improvement more than seven years after substantial completion of such improvement.” (Emphasis added.)
It is undisputed that in the present case thе limitation period began to run on the same day under both statutes, January 17,2005, the day that Glacier had finished drilling and backfilling the boring holes. The complaint was not served until March 26, 2008. Therefore, if the three year statute of repose contained in § 52-584 applies, then the action is barred, but if the seven year statute of limitation in § 52-584a applies, then the action can go forward. Our Supreme Court has stated that the seven year statute of limitations contained in § 52-584a applies for certain actions against architects and engineers arising out of a deficiency in the design,
Our Supreme Court defined the term “improvement to real property” as it relates tо § 52-584a in
Verna
v.
Commissioner of Revenue Services,
The defendant argues that it provided environmental testing services only, and, as such, its activities do not constitute an improvement to real property. It is undisputed that Olin hired the defendant to test its factory for environmental pollutants. To this end, the defendant was required to perform an investigation in order to determine whiсh pollutants were present at the factory, design a remediation plan and “supervise the remediation and/or removal of pollutants.” The defendant also was required to perform a variety of specific tasks, including the following: to look into the nature of operations, to assess sources of pollution, to develop an investigation plan to detеrmine the nature and extent of contamination, to collect groundwater samples, to oversee soil borings, well borings and the proper backfilling of soil borings, to evaluate test data, to determine the need for remediation and develop a remediation
After the defendant removed a sample from a boring, Glacier “backfilled” the hole. As specified in the contract between the defendant and Glacier, the borings were to be backfilled with a grout mixture of 95 percent by weight Portland cement and 5 percent bentonite. After the holes were backfilled, they were to be topped with a concrete cap. At oral argument before this court, the defendant’s attorney argued that the defendant’s work could in no way constitute an improvement to real property; in other words, its actions, as a matter of law, do not constitute an improvement to real proрerty. To support its argument, the defendant directs us to our Supreme Court’s decision in
Grigerik
v.
Sharpe,
supra,
In
Grigerik,
a septic system could not be completed due to the negligence of a professional engineer. Our Supreme Court concluded that where the improvement to real property contemplated by the architect’s or engineer’s services is not completed because of the defect complained of, § 52-584a, and not § 52-584, applies to the plaintiffs cause of action.
Grigerik
v.
Sharpe,
supra,
The plaintiffs, however, rely on оur Supreme Court’s recent decision in
Plato Associates, LLC
v.
Environmental Compliance Services, Inc.,
supra,
We conclude that there exists a genuine issue of material fact as to whether
The judgment is reversed and the case is rеmanded for further proceedings according to law.
In this opinion the other judges concurred.
Notes
We will refer to Lathrop and Olin individually by name and collectively as the plaintiffs.
The plaintiffs concede that the trial court properly granted summary judgment in favor of Glacier Drilling Company, LLC (Glacier), because it is not a professional engineering firm. Accordingly, the plaintiffs do not challenge the court’s decision insоfar as it concerns Glacier. We will refer in this opinion to Malcolm Pimie, Inc., as the defendant.
Because our conclusion that a genuine issue of material fact exists with respect to the plaintiffs’ claim that the defendant provided services in connection with an improvement to real property is dispositive, we do not address the plaintiffs’ additional claim that the court improperly required them to plead and prove that the alleged improvements to the property could not have been completed as a result of the defendant’s negligence.
The court did not have the benefit of our Supreme Court’s decision in
Plato Associates, LLC
v.
Environmental Compliance Services, Inc.,
supra,
We note that the definition of improvement in the current edition of Black’s Law Dictionary remains the same. See Black’s Law Dictionary (9th Ed. 2009) p. 826.
