Lead Opinion
FACTS AND PROCEDURAL HISTORY
On August 13, 2010, The Lathan Company, Inc., entered into a public works contract with the State of Louisiana, Department of Education, Recovery School District ("the RSD") to renovate William Frantz School in New Orleans. Billes Partners, LLC ("Billes") served as architect on the project. Jacobs Project Management Company/CSRS Consortium ("Jacobs"), through a contract with the RSD, served as the construction manager on the project.
On May 14, 2012, Lathan filed a "Petition for Mandamus," naming the RSD and John White, in his official capacity as the Louisiana Superintendent of Education, as defendants, seeking an order requiring the RSD to make payment of all undisputed amounts owed for Lathan's work. In an amended petition filed on August 1, 2014, Lathan added Billes and Jacobs as defendants.
Lathan's lengthy amended petition, consisting of twenty-five pages and two hundred eighteen paragraphs, alleged, in pertinent part, that Jacobs owed a duty to Lathan to conduct constructability reviews and to oversee and administer the project according to the standard of care of similar professionals in the industry, which Jacobs did not do. In pertinent part, the amended petition alleged:
(1.) The original bid documents and design drawings contained flaws, including the failure to disclose certain mold conditions and an underground fuel tank, which resulted in Lathan performing additional work, and for which Lathan's contrаct was not adequately extended for the time required to address these undisclosed conditions;
(2.) As a result of the faulty design documents, Lathan submitted in excess of 400 requests for information ("RFIs") to Billes and despite numerous promises to timely respond by Billes and Jacobs, Lathan's RFIs were not timely responded to, resulting in project delays;
(3.) Billes and Jacobs did not perform inspections in the manner prescribed by industry standards; and
(4.) Billes and Jacobs failed to review, certify and/or approve the amounts due to Lathan, causing Lathan to incur additional costs, delaying the project, and preventing Lathan from having access to contract funds to pay subcontractors and suppliers.
Lathan summarized Jacobs's wrongful acts as: (1.) its unreasonable refusal to approve Lathan's payment applications and schedules; (2.) its extremely delayed responses to Lathan's questions and submittals; (3.) its refusal to give needed responses to reasonable questions; (4.) its refusal to properly recommend substantial completion; (5.) its refusal to properly manage the oversight of the project; and
In response, Jacobs filed a motion for summary judgment, seeking a dismissal of Lathan's claims against it. In its memorandum in support of its motion, Jacobs asserted that Lathan's general negligence claims must fail because Jacobs owed no duty to Lаthan, since Lathan was not a party to the contract between Jacobs and the RSD. Jacobs additionally urged that because it owed no duty to Lathan, Lathan's LUTPA claims must fail as a matter of law. Notwithstanding whether a duty was owed, Jacobs also argued that Lathan's allegations did not rise to the level of an unfair trade practice that is actionable under LUTPA. Alternatively, Jacobs argued that a majority of Lathan's claims against it were prescribed.
Lathan opposed the motion, contending that Jacobs owed it a duty given the high degree of control and power that Jacobs, as a learned professional, held and had exercised (or failed to exercise) over Lathan. Additionally, Lathan argued that its claims against Jacobs were timely because: (1) Billes and Jacobs are joint tortfeasors and thus, the 2012 suit against Billes interrupted prescription as to Jacobs; and (2) Jacobs was still performing work on the project and thus, Lathan's claims against Jacobs are governed by the continuing tort doctrine.
Following argument, the trial court granted Jacobs's motion for summary judgment, finding that Jacobs owed Lathan no duty. As such, the trial court concluded that in the absence of a duty, Lathan could not recover under its negligence theory or LUTPA claims.
On September 24, 2015, the trial court signed a judgment granting Jacobs's motion for summary judgment and dismissing Lathan's claims against Jacobs with prejudice. However, the written judgment was silent as to the prescription argument that was raised by Jacobs in support of the motion of summary judgment, and which the trial court stated, in its oral reasons for judgment, that it would deny. Lathan subsequently filed a motion for new trial, which was denied by the trial court.
Lathan then filed the instant appeal, assigning the following as error:
(1) The trial court improperly granted Jacobs's motion because Jacobs, being and acting as a licensed construction professional, and under the facts of this case, owed a duty to Lathan.
(2) The trial court improperly granted Jacobs's motion by making a credibility determination as to the record evidence.
(3) The trial court improperly granted Jacobs's motion by making an improper factual determination of disputed evidence on summary judgment concerning Jacobs's scope of duties properly reserved for the trier of fact-here, a jury.
(4) The trial court erred in failing to deny Jacobs's motion as premature considering the woefully inadequate state of discovery.
(5) The trial court erred in denying Lathan's motion because the underlying summary judgment ruling wascontrary to binding First Circuit authority.
(6) The trial court erred in denying Lathan's motion by finding that newly-discovered evidence on the issue of Jacobs's professional duties did not present an issue of fact warranting a new trial.
DISCUSSION
An appellate court reviews a trial court's decision to grant a motion for summary judgment de novo, using the same criteria that govern the district court's consideration of whether summary judgment is appropriate. Smith v. Our Lady of the Lake Hospital Inc., 93-2512 (La. 7/5/94),
The burden of proof is on the mover. See LSA-C.C.P. art. 966 C(2). However, if the mover will not bear the burden of proof at trial on the matter that is before the court on the motion, the mover's burden does not require that all essential elements of the adverse party's claim, action, or defense be negated. Instead, the mover must point out to the court that there is an absence of factual support for one or more elements essential to the adverse party's claim, action, or defense. Thereafter, the adverse party must produce factual evidence sufficient to establish that he will be able to satisfy his evidentiary burden of proof at trial. If the adverse party fails to meet this burden, there is no genuine issue of material fаct, and the mover is entitled to summary judgment as a matter of law. LSA-C.CP. art. 966 C(2); Temple v. Morgan, 15-1159 (La. App. 1st Cir. 6/3/16),
With regard to the negligence claim, Louisiana courts have adopted a duty-risk analysis in determining whether to impose liability under general negligence principles. Daniels v. USAgencies Cas. Ins. Co., 11-1357 (La. App. 1st Cir. 5/3/12),
Duty is a question of law and is a threshold issue in any negligence action. Simply put, the inquiry is whether a plaintiff has any law-statutory, jurisprudential, or arising from general principles of fault-to support the claim. In deciding whether to impose a duty in a particular case, the court must make a policy decision in light of the unique facts and circumstances presented. When no factual dispute exists and no credibility determinations are required, the legal question of the existence of a duty is appropriately addressed by summary judgment. Daniels,
Louisiana jurisprudence imposes a duty on professionals to perform in accordance with the generally accepted standards of their respective industry. See Calandro Development, Inc. v. R.M. Butler Contractors, Inc.,
Similarly, in Colbert v. B.F. Carvin Construction Co.,
"The determination whether in a specific case the defendant will be held liable to a third person not in privity is a matter of policy and involves the balancing of various factors, among which are the extent to which the transaction was intended to affect the plaintiff, the foreseeability of harm to him, the degree of certainty that the plaintiff suffered injury, the closeness of the connection between the defendant's conduct and the injury suffered, the moral blame attached to defendant's conduct, and the policy of preventing future harm." [Emphasis added.]
Colbert,
In Harris Builders, L.L.C. v. URS Corp.,
URS's construction plan preparations and instructions to Harris [general contractor] to redo certain work were acts that URS had to have known would directly affect Harris. It was foreseeable and fairly certain that Harris would suffer economic harm if URS managed the project poorly, and URS's development of project specifications directly affected the work Harris performed. In short, Harris asserts a high degree of economic control by URS that was the purpose recognized in Colbert as supporting a cause of action.
[Emphasis added.]
Harris Builders,
Herein, Lathan asserts that while the defendants in Calandro, Colbert, and Harris Builders were classified as architects or engineers, the rationale and legal principles set forth therein support the proposition that a duty to third parties, even absent direct contractual privity, should not be confined to only those construction professionals holding the title of ''architect" or "engineer." Rather, Lathan avers that the focus is necessarily on the management responsibilities and supervisory authority that the particular construction professional holds or practices on the project that may warrant еxtending the duty owed by that construction professional to a third party not in privity. Accordingly, Lathan contends that given the scope of Jacobs's extensive management responsibilities and supervisory authority over the disputed construction project herein, Jacobs owed Lathan a duty to exercise this authority to a professional standard, which it allegedly failed to do; or, at the very least, that there are issues of fact that must be resolved by a trier of fact before a determination can be made as to whether or not Jacobs owed and breached a duty to Lathan.
Jacobs counters that the uncontested facts show that Jacobs did not serve as an architect, engineer, or design professional on the project, did not control Lathan, and did not owe Lathаn a duty. Jacobs maintains that Lathan's claims must fail because they are predicated on an erroneous assertion that Jacobs independently owed Lathan a duty to approve Lathan's pay applications and schedules, respond to submittals, recommend substantial completion, and manage the project. Jacobs asserts that it owed no such duty to Lathan, contractually or otherwise, and therefore, the trial court did not err in granting summary judgment and dismissing Lathan's claims against Jacobs.
In support of its motion for a summary judgment on the basis that it owed no duty, Jacobs submitted the affidavit of Nicholas Amort, a project manager for Jacobs who was involved in the management of the project at the William Frantz School, Mr. Amort attested that Jacobs did not draft specifications or prepare design documents for the project, but merely provided recommendations to the RSD based on its knowledge of how construction projects are supposed to proceed. Mr. Amort further attested that Jacobs did not sign any change order or any of the twenty-two
In opposition to the motion for summary judgment, Lathan submitted the contract between Jacobs and the School District. The contract provides that Jacobs's project management team shall include a Louisiana licensed architect or engineer, and a Louisiana licensed contractor or a certified project management professional . Moreover, the contract outlines more than eighty tasks that Jacobs Project Management Company was responsible for in connection with the project, including:
2.1 [Jacobs] will serve as an agent and representative of the Owner (RSD).
2.7 [Jacobs] shall be responsible for assisting the RSD in the procurement of, and providing design management of, professional design consultants[.]
2.9 [Jacobs] will be responsible for providing field inspection services as necessary to ensure compliance to schedule, budget, and quality contractual requirements.
3.3.2.9 [Jacobs shall] [v]alidate the professional design consultant's cost estimate and provide value engineering and constructability reviews for the Schematic Design, Design Development, and Construction Documents phases of the projects to ensure compliance with project budget and schedule.
3.3.2.10 [Jacobs shall] [p]rovide document quality assurance/quality control reviews for the Schematic Design, Design Development, and Construction Documents phases of the projects.
3.4.2.6 [Jacobs shall] [p]rovide project construction management services to include: conduct regular jobsite meetings, oversee quality assurance testing and inspection programs, monitor contractor and subcontractor work for deficiencies... expedite communication, processing and documentation of all contractor's submittals including RFI's, payments requests and change orders.
3.4.2.8 [Jacobs shall] [p]rocess аnd track payment requests for approval within a week of receipt.
3.5.2.2 [Jacobs shall] [p]rocess contractor's payments and verify accuracy of paid quantities.
3.5.3.1 [Jacobs shall] [r]eview contractor's punch lists and attend the professional design consultant's substantial completion inspections. Recommend to the RSD acceptance or rejection of professional design consultant's issuance of the certificate of substantial completion and conduct final acceptance inspections with the RSD.
3.5.3.5 [Jacobs shall] [m]onitor and document and report all Time and Materials change orders.
Accordingly, while Mr. Amort's affidavit may have demonstrated that Jacobs did not draft specifications or prepare design documents for the project, the evidence submitted by Lathan establishes that Jacobs was to provide: (1.) design management services, and (2.) document quality assurance/quality control reviews for schematic design, design development, and
Moreover, while Mr. Amort's affidavit may establish that Jacobs did not sign any change orders or CCD's and that Jacobs was not expected to respond to the RFIs, the evidence submitted by Lathan establishes that Jacobs was responsible for coordinating the management of invoices, contracts, and change orders. And, the evidence submitted by Lathan establishes that Jacobs's duties included the processing and documentation of all contractors' submittals including RFIs, payment requests, and change orders. Thus, if Jacobs improperly delayed the processing of invoices and RFIs, as alleged herein, it is foreseeable and to a degree certain that the project would be delayed, and thereby, adversely affect the work and profits of the general contractor, as Lathan alleges occurred herein.
Additionally, while Jacobs may have established that the certificate of completion can only be signed by the owner and architect, the evidence submitted by Lathan provides that Jacobs was obligated to attend the substantial completion inspection and that Jacobs was responsible for recommending "acceptance" to the owner. Should Jacobs delay the inspections or "negligently" refuse to recommend substantial completion, as Lathan alleges occurred herein, it is foreseeable that its actions could cause economic harm to Lathan, acting as the general contraсtor on the project.
Accordingly, after careful review of the record herein, we find that although Jacobs was not in direct contractual privity with Lathan, Jacobs must be deemed and held to know that its services were not only for the protection or interests of the owner but also third parties, including, specifically, Lathan, who was acting as the general contractor on the project. As outlined above, it was foreseeable and to a degree certain that Lathan would suffer economic harm if Jacobs failed to perform, or negligently performed, many of its professional duties. See Harris,
Thus, after carefully considering the record herein, and applying the balancing test enunciated in the jurisprudence noted above, we are unable to find any reason why the courts' rationale in such prior jurisprudence, extending the liability of architects and engineers, should not likewise apply to a project management professional, under the facts of this case. While the balancing test adopted by the Fifth Circuit in Colbert and the Middle District in Harris Builders is not binding, it is persuasive herein, and under this test, we agree with Lathan that a duty would be owed by Jacobs to plaintiff.
While Section 3.3.4 of Jacobs's contract provides that Jacobs is not responsible for any design acts or omissions of the design consultant on the project, and Section 3.6
Thus, we conclude that the trial court erred as a matter of law in granting summary judgment and dismissing Lathan's claims against Jacobs based on its erroneous finding that there was (or could be) no duty owed by the project manager to the general contractor. Accordingly, finding merit to Lathan's arguments herein, we conclude that the matter should be remanded to the trial court for further proceedings.
CONCLUSION
For the foregoing reasons, we reverse the trial court's September 24, 2015, summary judgment in favor of Jacobs/CSRS Consortium and its dismissal with prejudice of Lathan's claims against this defendant. The case is remanded to the trial сourt for further proceedings consistent with the views expressed herein. Costs of this appeal are assessed to defendant, Jacobs Project Management Co./CSRS Consortium.
REVERSED AND REMANDED.
Chutz, J. Dissents for Reasons assigned by McClendon, J.
Guidry, J. Concurs.
McClendon, J. dissents for reasons assigned.
Notes
Notably, the trial court also commented that, although not necessary to address, it would not have granted Jacobs's motion for summary judgment, as requested, on the issue of prescription.
We pretermit further discussion of the prescription argument that was raised as an alternative argument in the subject motion for summary judgment, as neither party has briefed this argument for purposes of the instant appeal. See LSA-C.C.P. art. 2133(B) ; Uniform Rules-Courts of Appeal, Rule 1-3.
Louisiana Code of Civil Procedure article 966 was amended and reenacted by Acts 2015, No. 422, § 1, with an effective date of January 1, 2016. The amended version of Article 966 does not apply to any motion for summary judgment pending adjudication or appeal on the effective date of the Act; therefore, we refer to the former version of the article in this case. See Acts 2015, No. 422, §§ 2 and 3.
CCDs are signed by the owner and architect only, and the contractor must proceed with the changes despite not signing off on the same. Whereas, change orders are signed by the architect, contractor, and owner.
In Kappa, HNTB was hired as a "program manager" by the city to oversee a construction project. Under the facts therein, the court found that HNTB did not owe a legal duty to the general contractor, Kappa Development, noting in the opinion that:
Kappa explained in its summary judgment filings, and at oral argument, that its claim against HNTB is for HNTB's alleged failure to timely recommend that the City aсcept and pay a certain change order. Kappa does not allege that HNTB negligently supervised the manner in which Kappa performed its work or that HNTB negligently performed any other alleged construction management responsibilities.
The trial court's dismissal of plaintiff's LUTPA claims was based on its finding that Jacobs did not owe a duty to Lathan. Insofar as we have reversed this finding of the trial court, we further remand this matter to the trial court for a determination by the trier of fact as to whether plaintiff's LUTPA claims should be dismissed pursuant to Jacobs's alternative argument that Lathan's allegations do not rise to the level of an unfair trade practice that is actionable under LUTPA.
Dissenting Opinion
The majority errs in concluding that Jacobs owed a duty to Lathan, with whom it had no contractual privity. The majority cites Calandro ,
The majority recognizes that Lathan did not rely upon plans and specifications prepared by Jacobs. Rather, the contract between Jacobs and the RSD specifically provided that the objective was for Jacobs to "assist the RSD in managing implementation of a multi-sitе capital plan." (Emphasis added.) Jacobs' duties, as reflected in the portions of the contract set forth in the majority opinion, involved services such as inspecting, validating cost estimates, providing document quality assurance/quality control review, processing and documenting contractor's submittals, verifying accuracy of paid quantities, reviewing punch list items, and monitoring and documenting all time and material change orders. Further, the contract provided as follows:
3.3.4 Notwithstanding anything in this section, the PM/CM [Jacobs] shall not be responsible for any design work or the acts or omissions of the professional design consultant or for the failure of the professional design consultant to carry out any of its work in accordance with the terms of its contract with the RSD.
* * *
3.6 Notwithstanding anything above, the PM/CM shall not hаve control over or charge of or be responsible for a contractor's means, methods, techniques, sequences, procedures, or safety programs, construction defects or the failure to detect any construction defects. The PM/CM shall not be responsible for any construction work or have control over the acts or omissions of a contractor or its subcontractors or suppliers, or for the failure of any of them to carry out any work in accordance with the terms of the contractor's agreement with the RSD.
Clearly, the RSD hired Jacobs to oversee the project and Jacobs' duty was to RSD, with whom it had contractual privity.
In extending the duty beyond the owner, the majority concludes that "[s]hould Jacobs delay the inspections or 'negligently' refuse to recommend substantial completion,... then it is foreseeable that its actions could cause economic harm to Lathan." However, merely because Jacobs could potentially cause economic harm to Lathan is insufficient to create a duty giving rise to tort liability. The majority cites no Louisiana state case where such a duty has been extended to a project manager, who is retained to protect the interests of the owner and whose obligations to the general contractor on the project are limited. See Stelko Electric, Inc. v. Taylor Community Schools Building Corp .,
The majority also references a trial court decision in Kappa Development & General Contracting Company v. City of Biloxi , Cause No. A2404-14-cv.00176 (Harris Country Circuit Court, Second Judicial District, State of Mississippi 7/21/16). However, in that case the court also refused to extend liability to a program manager. Therein, Kappa, the general contractor, entered into a contract with the City of Biloxi to repair damage to the City's infrastructure caused by Hurricane Katrina. HNTB Corporation entered into an agreement for professional services with the City to serve as program manager on the City's behalf. As program manager, HNTB's role was tо "assist the City in bringing to completion ... projects to repair the City's infrastructure caused by Hurricane Katrina and to support the design, construction, and evaluation thereof." After Kappa encountered unexpected sub-surface conditions, it sued, among others, HNTB, alleging:
HNTB had a duty ... to exercise the appropriate knowledge and skill of a professional engineering corporation in the management and administration of the contract during the project with Kappa. HNTB breached its duty and was negligent by failing to properly administer the contract thereby causing Kappa to experience unreasonable delay and incur extra cost and expense to construct the project.
HNTB subsequently filed a motion for summary judgment, urging that it owed no duty to Kappa. In granting thе motion, the court noted that while Kappa may have a claim against the City for breach of contract, no separate claim existed against HNTB. The court reasoned that HNTB "was neither an architect nor the engineer on the subject project" and "did not perform professional services on which third-third parties reasonably rely." As such, the court "decline [d] to create such a duty in tort without clear precedent for doing so."
Similarly, in Ratcliff Architects v. Vanir Constr. Management ,
Considering the foregoing, I cannot conclude that the contract between Jacobs and the RSD created any duty in favor of Lathan nor did Jacobs render any professional services that would give rise to tort liability in this case.
Even so, Lathan submits that Jacobs had the "power of economic life and death over the contractor," which should give rise to liability in its favor. In Colbert , the court noted that one of the rationales for imposing liability on architects in favor of contractors with whom they are not in privity is the degree of control exercised by the supervising architect over the contractor, specifically, "[t]he power of the architect to stop the work alone [that] is tantamount to a power of economic life or death over the contractor." Colbert v. B.F. Carvin Construction Co. ,
Even if this court were to adopt the test enunciated in Colbert and extend it to a project manager, Lathan failed to show that it would be able to meet its burden of proof at trial that Jacobs had such expansive authority. Specifically, Nicholas Amort, a project manager for Jacobs who was involved in the management of the project at the William Frantz School, attested that Jacobs did not sign any change order or any of the twenty-two CCD's issued on the project. Mr. Amort also attested that Jacobs was not expected to respond to any RFI's (Requests for Information), as they were created by Lathan and responded to by Billes, the project's architect. Moreover, Mr. Amort attested that any work change proposal requests were issued by Billes to Lathan, that Jacobs did not sign these forms, nor was Jacobs obligated or expected to respond.
Ms. Hankins indicated that Jacobs could not sign any change orders and that she would not have signed a change order without Jacobs' recommendation, but in most instances there would have been a collaborative process leading to that recommendation. Ms. Hankins confirmed that the RSD did not sign "just because Billes or Jacobs approves or recommends something" and that the RSD exercised its own discretion in deciding whether to sign a change order. Moreover, Ms. Hankins indicated that Jacobs did not have authority tо stop work on the project. Accordingly, given the RSD retained ultimate control, I cannot conclude that Jacobs had the power of economic life or death over the contractor.
In light of the foregoing, I find no error in the trial court's grant of summary judgment in favor of Jacobs, nor any error in the trial court's denial of Lathan's motion for new trial. Further, despite Lathan's purported need to undertake additional discovery, Lathan did not seek to avail itself of the benefit of LSA-C.C.P. arts. 966(B) and 967(C) by formally requesting additional time or moving for continuance of the summary judgment hearing in order to undertake discovery. See Bardwell v. Faust ,
Considering the foregoing, I respectfully dissent and would affirm the ruling of the trial court.
Calandro Dev., Inc. v. R.M. Butler Contractors, Inc. ,
Colbert v. B.F. Carvin Construction Co. ,
Harris Builders, L.L.C. v. URS Corp. ,
In Stelko,
The Construction Manager, except to the extent [it can schedule and coordinate], and Architect will not have control over or charge of and will not be responsible for construction means, methods, techniques, sequences or procedure, or for safety precautions and programs in connection with the Work, since these are solely the Contractor's responsibility ... and neither [the Construction Manager or Architect] will be responsible for the Contractor's failure to carry out the Work in accordance with the Contract Documents. Neither the Construction Manager nor the Architect will have control over or charge of or be responsible for acts or omissions of the Contractor, Subcontractors, or their agеnts or employees, or of any other person performing portions of the Work.
In In re Hughes-Bechtol,
I note that Ms. Hankins' deposition was submitted in connection with the motion for new trial and is in the record.
Additionally, even if a LUTPA claim is viable absent a duty, Lathan has not shown that Jacobs' conduct is immoral, unethical, oppressive, unscrupulous, or substantially injurious such that Lathan can prevail on a LUTPA claim at trial.
