Lead Opinion
delivered the judgment of the court, with opinion.
Chief Justice Kilbride and Justices Thomas, Karmeier, and Theis concurred in the judgment and opinion.
Justice Freeman dissented, with opinion, joined by Justice Burke.
Justice Freeman dissented upon denial of rehearing, with opinion, joined by Justice Burke.
OPINION
The issue in this case is how to distribute foreclosure sale proceeds between a mortgagee and mechanics lien claimants when the mortgage predated the liens, the foreclosure sale proceeds are insufficient to satisfy all claims, and the mortgagee has paid for several improvements to the property through construction loan disbursements under section 16 of the Mechanics Lien Act. 770 ILCS 60/16 (West 2006). The circuit court of Will County subrogated the mortgagee and gave it priority with respect to those improvements for which it paid and gave the mechanics lien claimants priority with respect to the value of their individual improvements. The appellate court reversed, holding that the mortgagee was entitled to subrogation for payment of perfected mechanics liens, but that the value of those improvements paid for by the mortgagee where no lien was filed and perfected was to be first applied to the satisfaction of the mechanics liens.
BACKGROUND
LaSalle Bank loaned $8,018,151 to Cypress Creek 1, LR for the development of 13.79 acres of land in Boiling-brook, Illinois, into senior apartments. The loan was secured by a mortgage and security agreement, which were recorded on June 13, 2003. Construction began on the development and Cypress hired appellees, Eagle Concrete and Edon Construction, to perform work on the development. LaSalle funded a total of eight construction draws before June 2005, when it determined that there was no longer enough money in the trust to complete the project. In July 2005, LaSalle filed to foreclose on the mortgage. The following November, Eagle and Edon recorded mechanics liens for $63,478 and $285,825.80, respectively.
In April 2006, a judgment of foreclosure and sale was entered against Cypress. The trial court found that the balance due on the mortgage totaled $8,621,110. The order of judgment was subsequently amended to reflect payment of $5,577,540, leaving an amount due on the mortgage of $3,043,570. LaSalle bought the property at a sheriff’s sale in May 2006 for $1.3 million. Edon and Eagle filed to foreclose their mechanics liens and their actions were consolidated with the mortgage foreclosure proceeding.
In September 2007, a trial was held to determine the priority of lienholders and to distribute the proceeds of the sheriff’s sale. At trial, Edon, Eagle, and three other mechanics lien claimants argued for priority of their liens over the mortgage. The court heard testimony that, through the loan disbursements, LaSalle paid $99,917 in engineering costs, $2,842.50 for environmental reports, and $8,538 for utilities. LaSalle also paid $30,000 to Basic Development in satisfaction of their lien, which predated the mortgage by one month. In an order dated October 30, 2007, the court found that the value of the land before any improvements were made was $1,360,000, or 40% of the total value of the property, and that the value of enhancements, including those paid for by LaSalle, totaled $2,068,699, or 60% of the total value. Based on these findings, the court determined that 40% of the proceeds of the sheriffs sale should go to the mortgagee in satisfaction of the mortgage and the remaining 60% should be divided among those who had improved the land. The court conducted a proportionality analysis and allocated sale proceeds according to the following table:
Expense of sale: $1,542
Receiver’s fees and expenses: $746,244
Remaining proceeds ($552,214):
Value attributable to land: $215,100
Value attributable to all improvements: $331,328.40
The court applied the $215,100 attributable to the land toward the satisfaction of the mortgage and subrogated LaSalle Bank to the amounts it paid for construction costs, engineering costs, environmental reports, and utilities, as well as the amount it paid toward the satisfaction of Basic Development’s perfected hen. It then found the proportion of the total value of the improvements to which each party was entitled by dividing the value of each party’s improvements by the total value of the improvements, $2,068,699. The court concluded that Eagle’s hen for $63,478 accounted for approximately 3% of the value of the improvements and Edon’s hen for $285,827 accounted for approximately 15%. LaSalle was entitled to credit for 76% of the value of the improvements, and the three other lienholders, with liens amounting to a total of $131,629, were credited with a total of 5.8% of the improvements. The court therefore awarded $50,000 and $7,300 to Edon and Eagle, respectively. LaSalle was subrogated to $256,514 for the improvements it funded and the remaining lienholders were awarded a total of $20,300. In total, LaSalle was awarded $471,614, with $215,100 attributable to the value of the land before any improvements were made and $256,614 attributable to those improvements it funded. Edon and Eagle filed motions for modification of judgment, which were denied in January 2008.
Edon appealed the allocation of sale proceeds and Eagle joined the appeal. Edon and Eagle first argued that the mechanics hen claimants have full priority over a mortgagee under section 16 of the Mechanics Lien Act and that, therefore, the trial court should have satisfied their hens in total before disbursing any funds to LaSalle as mortgagee.
LaSalle filed a petition for rehearing on the subrogation ruling and the application of that ruling to the three lien claimants which had not appealed the trial court’s decision. The petition was granted and, on January 15, 2010, the appellate court filed its second opinion with majority, concurring, and dissenting opinions. The court retained its ruling on the subrogation issue, but ordered that the value attributable to the improvements paid with loan disbursements be allocated proportionally only between the two appellants, Edon and Eagle.
This court granted LaSalle’s petition for leave to appeal. Ill. S. Ct. R. 315 (eff. Feb. 26, 2010).
ANALYSIS
The issue before this court concerns the apportionment of foreclosure sale proceeds as between a mortgagee and mechanics lien claimants when the proceeds are insufficient to satisfy the mortgage and the mechanics liens. Apportionment is governed in this situation by section 16 of the Mechanics Lien Act (770 ILCS 60/16 (West 2006)). Questions of statutory construction are questions of law and reviewed de novo. People v. Perry,
In matters of statutory construction, we endeavor to “ascertain and give effect to legislative intent.” Id. at 323. We first must look to the plain language of the statute as the best indicator of legislative intent, considering the statute in its entirety. Id. Where the language is clear and unambiguous, we will apply it as written. Id. Only where the language is ambiguous do we resort to extrinsic aids to determine legislative intent. Id. at 323-24.
Plain Language
The Mechanics Lien Act affords some protection to contractors who contribute labor or materials to a construction project or who provide services such as an architect or engineer by giving them a lien on the subject property. 770 ILCS 60/1 (West 2006). The Act modifies the common law first-in-time, first-in-right rule (see 27A Ill. L. and Prac. Mortgages §50 (2003)) by affording hen-holders partial priority over pre-existing mortgages when the proceeds of a foreclosure sale are insufficient to satisfy all claims:
“No incumbrance upon land, created before or after the making of the contract under the provisions of this act, shall operate upon the building erected, or materials furnished until a lien in favor of the persons having done work or furnished material shall have been satisfied, and upon questions arising between incumbrancers and lien creditors, all previous incumbrances shall be preferred to the extent of the value of the land at the time of making of the contract, and the lien creditor shall be preferred to the value of the improvements erected on said premises, and the court shall ascertain by jury or otherwise, as the case may require, what proportion of the proceeds of any sale shall be paid to the several parties in interest. All incumbrances, whether by mortgage, judgment or otherwise, charged and shown to be fraudulent, in respect to creditors, may be set aside by the court, and the premises freed and discharged from such fraudulent incumbrance.” 770 ILCS 60/16 (West 2006).
Historically, this provision has been interpreted by the appellate court to give each mechanics lien claimant priority only to the extent of the increased value of the property due to that claimant’s improvements on the property. See, e.g., Commercial Mortgage & Finance Co. v. Woodcock Construction Co.,
With respect to priority determinations, section 16 directs that
“upon questions arising between incumbrancers and lien creditors, all previous incumbrances shall be preferred to the extent of the value of the land at the time of making of the contract, and the lien creditor shall be preferred to the value of the improvements erected on said premises ***.” 770 ILCS 60/16 (West 2006).
Eagle argues that, by creating two groups, lien creditors and incumbrancers, and subsequently giving the “lien creditor,” singular, priority with respect to the value of “improvements,” plural, that the statute unambiguously gives as few as one hen creditor preference to the value of all improvements erected on the premises after the date that the mortgage attached. We disagree.
First, “the time of making the contract” must be understood in the context of the entire statute. The language here does not refer to the date the mortgage is entered into, but rather the time when the lien creditors in question entered into their contracts with the property owner. This is evident from the beginning of the section, which refers to an encumbrance “created before or after the making of the contract under the provisions of this act,” clearly referring to the contracting for the provision of lienable services and materials. 770 ILCS 60/16 (West 2006).
Further, the use of “improvements” in the plural simply acknowledges that a single lienholder could have made multiple improvements that, combined, give rise to the hen creditor’s claim. The phrase “the hen creditor shall be preferred to the value of the improvements erected on said premises” must also be understood in context. Because prior incumbrancers have priority with respect to any improvements on the land which predate the hen claimant’s contract, “improvements” cannot mean all improvements. Additionally, because the statute acknowledges the possibihty of multiple hen claimants, it is only logical that each claimant would have priority with respect to his own improvements. “A statute is ambiguous if it is capable of being understood by reasonably well-informed persons in two or more different ways.” Krohe v. City of Bloomington,
The History of the Mechanics Lien Act and Prior Case Law
The current version of section 16 was enacted in 1903. 770 ILCS 60/16 (West 2006). The language at issue in this case tracks section 20 of the Liens Act of 1845 and section 17 of the Liens Act of 1874 with the exception of the clause “and the lien creditor shall be preferred to the value of the improvements erected on said premises.” See Albrecht v. Buelow,
This court has apphed the provision “upon questions arising between incumbrancers and hen creditors, all previous incumbrances shall be preferred to the extent of the value of the land at the time of making of the contract” on several occasions. With respect to section 20 of the Act of 1845, this court noted that “the statute gives the mechanics and material men hens, paramount to the trust deed, upon the improvements made by them upon the premises.” (Emphasis added.) Raymond v. Ewing,
In almost every subsequent instance, courts have found that the statute gives lienholders priority only with respect to the added value of the property attributable to those improvements forming the basis for the lien in question and gives the mortgagee priority with respect to the value of the land at the time the contract is entered into between the owner and the contractor. See, e.g., Commercial Mortgage & Finance Co. v. Woodcock Construction Co.,
Eagle cites, and we have found, only one case that has held otherwise. In Mitchell v. Robinovitz, the appellate court affirmed an order that gave the prior mortgagees priority only with respect to the value of the vacant land and four mechanics lien claimants priority with respect to the entire improvement. Mitchell v. Robinovitz,
The courts have thus applied this statute repeatedly and consistently since its adoption over one hundred years ago and the legislature has had ample time to contravene our understanding. This consistent judicial interpretation of the language in section 16 is considered a part of the statute until the legislature amends it contrary to that interpretation. See People v. Woodard,
Purpose of the Act and Practical Considerations
Our reading is also consistent with both the purpose of the Act and the practicalities of construction lending. The Mechanics Lien Act aims to “protect those who in good faith furnish material or labor for construction of buildings or public improvements.” Lawn Manor Savings & Loan Ass’n v. Hukvari,
Further, LaSalle argues that if, as under the appellate court’s decision, the only way a mortgagee could get “credit” for the value of improvements it has funded is to be subrogated to a valid, perfected mechanics lien, lenders would have every reason to require contractors to file mechanics liens and to then evaluate their validity before paying the contractor for work done on the property. This would significantly increase the paperwork and the cost of financing any construction project. If every contractor had to file a lien before getting paid, this would also defeat one of the purposes of the recording requirement in the Act. Eagle notes that the notice and filing provisions give third parties “notice of the existence, nature and character of lien claims,” and allow them to gauge the enforceabihty of such claims. Eagle argues that these filings are important to contractors to give them an opportunity to review the public record and determine whether a project is “in trouble” based on the liens filed against a property. However, if a mortgagee were only entitled to be preferred to the value of the land at the time the mortgage was contracted into and not to any of the improvements the mortgagee has funded unless it is subrogated to a perfected mechanics lien, there would be multiple mechanics hens on every project, whether or not the project was “in trouble” and this signaling function of the recorded hens would be lost.
For the foregoing reasons, we hold that section 16 of the Mechanics Lien Act gives mechanics lien claimants priority only with respect to the value of the property attributable to those improvements for which they furnished material or services. To the extent that the appellate court gave the henholders priority with respect to all improvements made subsequent to the mortgage, we find that this was in error.
Priority as to the Value of Paid-For Improvements
We turn now to one remaining question: if the mortgagee is preferred to the value of the land at the time the owner contracts with the lien claimants, and the hen claimants are preferred only to the value of those improvements that form the basis of their hens, what becomes of any value attributable to those improvements that have been made by contractors after the contracts in question were entered into but who were paid for their work and therefore never filed hens? In Clark v. Moore,
“[W]here, as in this case, there is a large proportion of the enhanced value of the property produced by the owner paying for labor and material furnished by others than the parties to the suit, *** the enhanced value produced by the payment of money by the owner, whilst the work was progressing, should be applied to the satisfaction of the mortgages on the property; and if any portion of the fund thus created shall remain, to be applied to the satisfaction of the liens for labor and materials. It has always been recognized the true rule to hold all improvements placed by the mortgagor on the premises as being embraced in and subject to the mortgage. We can not suppose that they were intended, when made, to be for the benefit of other lien holders.” Id. at 282-83.
Rejecting interpretations that would give lienholders priority to or would give mortgagees and henholders pro rata shares in the value attributable to these improvements, the Clark court further reasoned that the lien-holders “have their lien on the enhanced value they have given to the property, but have advanced neither money nor materials for which the owner has paid; and the subsequent mortgages may have been given to secure the very money paid by the owner for the labor and materials.” Id. at 283. Though the Mechanics’ Liens Act of 1895 provided that when the owner paid for such improvements, “the enhanced value thereby given shall be treated as a fund in which the mortgagee and lien-holder shall participate pro rata,” in 1903 the legislature substantially reenacted the earlier language that Clark interpreted. See Albrecht,
The logic of the Clark decision applies equally to this case, and we see no reason to depart from it. In this case, the trial court found that LaSalle paid $1,587,765 in lien-able expenses
Eagle argues that because “in 1845, *** a contractor who provided labor or material became a perfected lien claimant as soon as it provided services or material,” Clark “in essence held that a mortgagee or owner should get the benefit of payments made to perfected mechanics lien claimants who, at that time, was anyone who had provided labor or materials.” Even if we presume this to be the case, the Clark court nowhere relied on principles of subrogation or the idea that the contractors paid by the owner in that case were perfected lien creditors. Instead, the court appeared to recognize that improvements paid for by the owner to property subject to a mortgage would presumably be paid for out of the proceeds of the mortgage, and therefore it is the mortgagee, not the lienholders, that should take priority with respect to the added value attributable to those improvements. Clark,
Subrogation
In distributing the proceeds of the foreclosure sale, the trial court conducted a proportionality assessment. Two methods have been used by courts to determine the value of a mechanics lien — the market value approach and the contract approach. The trial court determined that, because the improvements are not complete, it is difficult if not impossible to determine their market value, and thus employed the contract approach, valuing each mechanics lien at the contract price agreed upon by the owner and the mechanics hen claimant. None of the parties have argued that this was in error.
The trial court determined that the land, prior to the start of construction, was worth $1,360,000. It then determined that the value of all improvements made on the land (including those paid for through draws on the construction loan), valued at their contract price, amounted to $2,068,699. The trial court held that LaSalle was entitled to be subrogated to the extent it paid construction costs, engineering costs, environmental reports, utilities, and the lien of Basic Development, which predated the mortgage.
Our analysis above makes subrogation unnecessary in a case like this, with the exception of the payment of Basic Development’s lien. Because the trial court used the contract method of determining the value of the mechanics hen claimants’ improvements to the property, it was correct to apply the same method to value all other henable improvements — those paid for by the eight draws made on LaSalle’s loan to Cypress. The value of these improvements, paid for with mortgage proceeds, should thus go toward the satisfaction of the mortgage without a question of subrogation arising.
The end result, however, is the same. By subrogating LaSalle to the value of the improvements, the trial court conducted the same type of analysis as would be required if it had valued those improvements that formed the basis for the mechanics liens and then valued the rest of the land and given LaSalle credit in a proportionality determination for the latter.
We note that LaSalle paid $30,202 to Basic Development for a hen that predated the mortgage. The parties do not dispute that LaSalle was properly subrogated to this claim. See Detroit Steel Products Co. v. Hudes,
CONCLUSION
For the reasons discussed above, we hold that, in a proportionality determination under section 16 of the Mechanics Lien Act, the value of the property attributable to improvements paid for with proceeds of a mortgage and construction loan should be attributed toward the satisfaction of the mortgage. We therefore find that the appellate court erred when it reversed the trial court’s distribution of proceeds. Accordingly, we reverse the judgment of the appellate court on this point and remand to the trial court for further proceedings consistent with this opinion. Because Edon and Eagle have not appealed the appellate court’s award of LaSalle’s attorney fees (
Appellate court judgment affirmed in part and reversed in part; cause remanded.
Notes
Eagle argues in its brief to this court that Croskey “leaves no doubt about the fact that the mortgagee is preferred to the value of the land and improvements at the time of the attachment of the mortgage and that the mechanics lien claimants are preferred as to the improvements supplied thereafter.” This is a misstatement of the holding in Croskey. While the opinion does say that “land,” as used in the statute, must mean “the land with such improvements as there are upon it at the time of the execution of the mortgage,” the court directed that the security of the mortgagee is protected by being “preferred to the extent of the value of the land at the time the contract is made with the mechanic or material man,” and that the lien claimants are only entitled to “a paramount lien on the improvements towards which they furnished materials.” Croskey,
In its brief to this court, Eagle questions the lienability of some of the expenses LaSalle was subrogated to by the trial court. Neither Eagle nor Edon contested the lienability of these expenses at trial nor in the appellate court. This issue is, therefore, forfeited. E&E Hauling, Inc. v. Pollution Control Board,
Dissenting Opinion
dissenting:
I believe today’s opinion incorrectly construes section 16 of the Mechanics Lien Act. I therefore respectfully dissent.
Background
None of the relevant facts are disputed in this appeal. In 2003, LaSalle National Bank Association lent Cypress Creek 1, Ll^ a development group, $8,018,151 for construction of a housing development. The note was secured by a mortgage and security agreement, recorded in June 2003. This represents the only loan made by LaSalle to Cypress.
Subsequently, Cypress entered into agreements with various contractors to build the development. Importantly, after the loan from LaSalle was in default, LaSalle continued to advance Cypress $1,557,563 from the loan proceeds. Cypress used this money to pay contractors for construction work performed at the development site. Eagle Concrete, however, was not paid for the concrete work it performed and thus recorded a mechanics lien for $62,478 in November 2005. Edon Construction Company was also not paid for its carpentry work on the project, and it recorded a mechanics lien for $285,826.80 in November 2005.
In July 2005, LaSalle filed suit to foreclose on the mortgage. Eagle filed a complaint to foreclose on its mechanics lien on March 30, 2006.
Analysis
The question here is one of lien priority since the proceeds from the sale were insufficient to satisfy all of the parties who have liens against this property. Although the court recognizes that this question is to be decided under section 16 of the Mechanics Lien Act, the court’s analysis does not apply the statute’s plain language. Section 16 provides:
“No incumbrance upon land, created before or after the making of the contract under the provisions of this act, shall operate upon the building erected, or materials furnished until a lien in favor of the persons having done work or furnished material shall have been satisfied, and upon questions arising between incumbrancers and lien creditors, all previous incumbrances shall be preferred to the extent of the value of the land at the time of making of the contract, and the lien creditor shall be preferred to the value of the improvements erected on said premises, and the court shall ascertain by jury or otherwise, as the case may require, what proportion of the proceeds of any sale shall be paid to the several parties in interest. All incumbrances, whether by mortgage, judgment or otherwise, charged and shown to be fraudulent, in respect to creditors, may be set aside by the court, and the premises freed and discharged from such fraudulent incumbrance.” 770 ILCS 60/16 (West 2006).
Under this language, priority is determined by first looking at whether the lien claimants’ contracts were executed before or after the mortgage was recorded. 770 ILCS 60/16 (West 2006). Both Edon and Eagle entered into contracts with Cypress after LaSalle had recorded its mortgage.
In such situations, section 16 directs that Eagle’s and Edon’s liens are preferred to the extent of the value of their improvements to the land (usually the price of their original contracts less any payments made),
The court interprets the plain language of section 16 so as to treat the $1,587,765 that Cypress paid to contractors from its loan with LaSalle, after the loan was already in default, as the equivalent of a mechanics lien claim. In other words, LaSalle’s role as the lender in this project put it on equal footing with the other unpaid claimants, such as Edon and Eagle. The effect of this is to improperly increase LaSalle’s pro rata percentage to more than it is entitled to under the Act. I disagree with this approach for several reasons.
First, this court has long recognized that mechanics liens are created purely by statute and are in derogation of the common law. Norman A. Koglin Associates v. Valenz Oro, Inc.,
Section 1 of the Act entitles any person who, in order to improve real estate, provides labor, services, materials or fixtures either under a contract with the owner or someone authorized by the owner to assert a lien under the Act if he or she is not paid. 770 ILCS 60/1 (West 2006). A contractor is defined as the party in privity with the owner of the real estate, the owner’s agent or anyone whom the owner has knowingly permitted to make improvements. Id. Subcontractors who provide labor, services, material, or fixtures for the improvement of real estate may also assert liens under the Act. Id.
Second, the court relies on Clark v. Moore,
“fail[s] to find a meaningful distinction between an owner paying the contractor from his bank account with presumably borrowed funds (given that all owners have a preexisting mortgage on the property when this statutory provision is in question) and authorizing the mortgagee to pay the contractor directly through a draw on the loan. In either case, the payments were presumably not made for the benefit of other lienholders.”242 Ill. 2d at 246 .
While the court might not see a meaningful distinction between owners and incumbrancers, the General Assembly does because the Act distinguishes between owners (770 ILCS 60/4, 27 (West 2006)), incumbrancers (mortgagees) (770 ILCS 60/16 (West 2006)), contractors (770 ILCS 60/1 (West 2006)), and subcontractors (770 ILCS 60/5, 21 (West 2006)). Indeed, the very section at issue in this case, section 16, distinguishes between incumbrancers and lien creditors — they are not treated alike.
More importantly, this court in Clark, in granting the owner priority, relied primarily on then-section 23 of the Mechanics Lien Law, which vested courts in mechanics hen cases with sweeping equitable powers. Clark,
A simple illustration of the proportionality analysis that is contemplated by the Act and that should be used in this case can be found in Bradley v. Simpson,
“As between the mortgages and the mechanic’s liens, under the statute the mortgages were entitled to satisfaction out of the land, and the other liens out of the building. As the building could not properly be separated from the lots, in order to realize the benefit of the liens the whole property, land and building together, had to be sold, that it might be converted into money and the proceeds divided. The proceeds of the sale represent and stand in the place of the land and the building, and the parties have the same proportionate interest in the proceeds that they had in the property before it was sold.” (Emphasis added.) Bradley,93 Ill. at 95 .
This analysis makes clear that all improvements are to be added to the value of the land before apportioning percentages to the sales proceeds when those proceeds cannot satisfy the mortgage and hen claimants. In Bradley, the mortgagee’s percentage from the sale was approximately 33.7% (3200/9492). The analysis in Bradley therefore demonstrates that the court today is incorrect when it states that “improvements” as used in the statute “cannot mean all improvements.” (Emphasis in original.)
Moreover, and contrary to the court’s interpretation (id. at 241 n.1), Bradley teaches that Eagle correctly argues that this court’s decision in Croskey v. Northwestern Manufacturing Co.,
Under the plain language of section 16, LaSalle, an “incumbrancer” (i.e., mortgagee) has priority with respect to only the value of the land before improvements. Everyone agrees in this case that the value of the land before any improvements were made was $1,360,000. According to the plain language of section 16, with respect to the priority as between “incumbrancers” (mortgagees) and “hen creditors” (mechanics hen-holders), all “previous incumbrances” (mortgagees) shall be preferred only to the extent of the value of the land (here, $1,360,000) “at the time of the making of the contract” and the hen creditors (each mechanic hen-holder) “shall be preferred to the value of the improvements erected on said premises [for Edon, $285,827; for Eagle $63,478].” 770 ILCS 60/16 (West 2006). Here, however, just as in Bradley, because
“the building could not properly be separated from the lots, in order to realize the benefit of the liens the whole property, land and building together, had to be sold, that it might be converted into money and the proceeds divided. The proceeds of the sale represent and stand in the place of the land and the building, and the parties have the same proportionate interest in the proceeds that they had in the property before it was sold.” Bradley,93 Ill. at 95 .
The improvements made to the property by the lien claimants in this case totaled $480,934.
In light of the above, I have difficulty in ascertaining the basis for the court’s holding that it is the plain language of section 16 which allows LaSalle to be treated as the equivalent of a contractor.
JUSTICE BURKE joins in this dissent.
Dissenting Opinion Upon Denial of Rehearing
Edon filed its complaint to foreclose its mechanics lien in August 2006. The various lien claimants actions were consolidated with the mortgage foreclosure proceeding.
Illinois courts use two different methods in determining the value of the improvements, the “market value” approach and the “contract price” approach. See Lyons Savings v. Gash Associates,
The Act defines subcontractors as parties who have contracts with the general contractor as opposed to the owner. 770 ILCS 60/21 (West 2006). This provision is not at issue in this case since it is undisputed that both Edon and Eagle contracted directly with Cypress.
With respect to its statutory construction, Clark is confusing. The opinion cites to the “12th section of the lien law,” stating that this section “declares that incumbrances on the property prior or subsequent to making the contract for erecting the building shall not operate upon the building or materials until the liens in favor of the workmen and the material-men shall be satisfied; and upon questions between previous incumbrancers and creditors, the previous incumbrance shall be preferred to the value of the land at the time of making the contract.” Clark,
This represents the sum of the hen claimants as found by the trial court: All American: $46,200; Eagle: $63,478; Gallagher: $46,506; Another Plumbing: $38,923; and Edon: $285,827.
Illinois courts recognize two forms of subrogation: equitable subrogation which is based in the common law and conventional subrogation which is based on an express provision contained in a contract. Aames Capital Corp. v. Interstate Bank of Oak Forest,
It bears mentioning that the doctrine of equitable subrogation confers priority, and priority is relief that must be pled. Norman A. Koglin Associates v. Valenz Oro, Inc.,
Dissenting Opinion
dissenting:
In my original dissent I warned that the court’s decision will cause confusion to Illinois mechanics hen law, an area of practice that is both “technical and complex.”
For example, Eagle notes that the court’s construction of the statutory phrase “at the time of the making of the contract” will have an adverse impact on subcontractor’s liens, which have, until now, related back to the date of the original contractor. Eagle also asks, in light of the court’s holding, “what happens to the value given to a project by a contractor which was neither paid nor for whom a lien was filed?” Eagle explains that this question is a direct result of the court’s interpretation of section 16. Eagle further asserts that in the wake of the court’s opinion, there will be “only two possible ways for a contractor to ensure payment of its work. It will either need to require the lender to prepay for the next segment of work or require the owner to post a payment bond.” Eagle asserts that it is “rare” in the construction industry for there to be such bonds.
Edon, for its part, points out that, in the wake of the court’s opinion, “trial courts will be confronted with the virtually impossible task of determining the exact components of a building which are subject to claims of lien creditors,” which is the result of the court’s novel interpretation of section 16.
The points raised by these contractors demonstrate that the court’s opinion, apart from contradicting existing case law, will unnecessarily disrupt existing commercial practices and cause a ripple effect on the marketplace For these reasons, the contractors’ contentions should be addressed. As Edon aptly observes:
“If the Court fails to reconsider its decision and the Majority Opinion stands, *** mechanic’s lien[s] will no longer provide protection to contractors. The inevitable result will be chaos in the construction industry. Contractors will [no] longer be able to rely upon the protection of the Act and will have to require payment in advance, which will increase the risk assumed by owners and developers, delay completion of troubled projects, and interfere with economic recovery.”
The court’s resolution of this case unfairly gives a financial advantage to the banking industry at the expense of the construction industry in the area of mechanics liens. This is not merely unfair, it contradicts the express intent of the General Assembly in enacting the Mechanics Liens Act. Historically, this court has consistently viewed the Act’s purpose to “protect” those who increase or improve, by the furnishing of labor and materials, the “value or condition of the property,” that is, contractors like Eagle and Edon. R.W. Dunteman Co. v. C/G Enterprises, Inc.,
Rehearing is appropriate where the reviewing court has overlooked or misapprehended a point. Ill. S. Ct. R. 367 (eff. Sept. 1, 2006). Rehearing is warranted under these circumstances, and I dissent from the court’s denial.
JUSTICE BURKE joins in this dissent.
