GARY LARUE v. GROUND ZERO CONSTRUCTION, INC. AND FORSGREN, INC.
No. CV-13-377
ARKANSAS COURT OF APPEALS, DIVISION IV
February 12, 2014
2014 Ark. App. 93
HONORABLE JOHN R. SCOTT JUDGE
APPEAL FROM THE BENTON COUNTY CIRCUIT COURT [NO. CIV 2011-1898-4]; APPEAL DISMISSED and CROSS-APPEAL DISMISSED
In this dispute over rock and other waste material from a road-construction project, Gary LaRue appeals from a judgment of the Benton County Circuit Court ordering him to pay appellee Ground Zero Construction, Inc., $89,600 for tortious interference of a contract between Ground Zero and appellee Forsgren, Inc. In turn, Ground Zero had been ordered to pay that same sum to Forsgren for breach of a contract between those parties. We must dismiss the appeal and cross-appeal without prejudice for lack of a final order.
Forsgren was the general contractor on an Oklahoma road project. On January 8, 2010, Forsgren entered into a contract with LaRue to use LaRue‘s nearby Oklahoma
Forsgren then sued Ground Zero. In its second amended complaint, Forsgren alleged that Ground Zero never made the remaining payment under the parties’ agreement and that it was owed $89,600. Forsgren also sought prejudgment interest and attorney‘s fees. Ground Zero filed an answer and counterclaim in which it alleged it purchased rock from Forsgren but was not able to obtain it and, therefore, Forsgren was unjustly enriched by $22,400.
Ground Zero also filed a third-party complaint against LaRue, claiming Forsgren‘s agreement with LaRue was void for lack of consideration because Forsgren did not own the waste material it promised to give LaRue, and that LaRue tortiously interfered with Ground Zero‘s agreement with Forsgren and was liable for punitive and compensatory damages. Ground Zero also sought injunctive relief in the form of an order permitting it entry onto
LaRue answered that he was owner of the rock because of his agreement with Forsgren and counterclaimed against Ground Zero for the fair-market value of the rock Ground Zero had removed from his property.
The case proceeded to a bench trial. The circuit court ruled from the bench and found that the agreement between Forsgren and LaRue was clear and meant that whatever waste material was left at the completion of Forsgren‘s project would remain on LaRue‘s property. The court noted that this interpretation was consistent with testimony by Forsgren‘s representative, as well as from LaRue. Turning to the contract between Forsgren and Ground Zero, Forsgren was awarded judgment against Ground Zero in the sum of $89,600. The court further found that Forsgren did not breach its contract with Ground Zero and, accordingly, dismissed Ground Zero‘s counterclaim.
As to Ground Zero‘s third-party claim against LaRue, the court found Ground Zero had a valid contract with Forsgren, that LaRue was aware of the contract, and that he disrupted the contract by erecting the fence to prevent Ground Zero from removing the rock and other material. Therefore, the court awarded Ground Zero judgment against LaRue in the sum of $89,600. A judgment consistent with the court‘s bench ruling was entered on January 16, 2013.2
Forsgren filed a motion seeking prejudgment interest, attorney‘s fees, and costs. The
On February 13, 2013, the court entered an amended judgment identical to the original judgment, but containing a Rule 54(b) certification. The certificate states that its purpose is to allow the appeal to proceed while the court addresses the posttrial motions for interest, fees, and costs.
An order entered on March 1, 2013, awarded Forsgren prejudgment interest of $7,929; $315 in costs; and $10,572 in attorney‘s fees against Ground Zero.
On March 5, 2013, the court awarded Ground Zero judgment for contribution, indemnity, and reimbursement against LaRue for the same prejudgment interest and attorney‘s fees it awarded Forsgren. LaRue filed notices of appeal from the court‘s judgment, amended judgment, and indemnification order. In each of his notices of appeal, LaRue abandoned any pending or unresolved claims. Ground Zero filed a cross-appeal from the amended judgment.
The question of whether an order is final and appealable is jurisdictional, and we are obligated to consider the issue on our own even if the parties do not raise it. See Advanced Envtl. Recycling Techs., Inc. v. Advanced Control Solutions, Inc., 372 Ark. 286, 275 S.W.3d 162 (2008). Pursuant to
The finality problem arises because of the lack of clarity in the circuit court‘s order. In disposing of Ground Zero‘s counterclaim against Forsgren, the circuit court stated as follows:
5. The Plaintiff, Forsgren, Inc., should be awarded judgment against the corporate Defendant, Ground Zero Construction, Inc., in the amount of [$89,600.00]. As the Plaintiff did not breach the contract with the Defendant, the Defendant‘s counterclaim against the Plaintiff is dismissed.
In the context of the counterclaim, which asserted causes of action for breach of contract, fraud, and unjust enrichment, we believe that this language only disposed of the cause of action for breach of contract. Although strict formality in language is not necessary, a judgment must specify clearly the relief granted or other determination of the action. McWhorter v. McWhorter, 2009 Ark. 458, 344 S.W.3d 64; Thomas v. McElroy, 243 Ark. 465, 420 S.W.2d 530 (1967). Likewise, the judgment did not specifically dispose of Ground Zero‘s claims in its third-party complaint against LaRue for misrepresentation and injunctive
Rule 54(b) is intended to permit review before the entire case is concluded, but only in those exceptional situations where a compelling discernible hardship will be alleviated by an appeal at an intermediate stage. Rutledge v. Christ is the Answer Fellowship, Inc., 82 Ark. App. 221, 105 S.W.3d 816 (2003). The Rule 54(b) certification in this case, however, was defective because it failed to state any factual reason to support the conclusion that there was no just cause to delay entry of a final judgment. The certification merely noted that Forsgren had filed a motion requesting prejudgment interest, costs, and attorney‘s fees and that Ground Zero had filed a response and a motion for judgment over against LaRue for indemnity for any and all such amount that the court may assess against Ground Zero. The court then found that resolution of these issues should not delay any appeal and whatever the court‘s decision concerning those postjudgment issues, it would not affect or cause the court
We also note that this problem could have been avoided had Ground Zero‘s notice of cross-appeal been in compliance with
state that the appealing party abandons any pending but unresolved claim. This abandonment shall operate as a dismissal with prejudice effective on the date that the otherwise final order or judgment appealed from was entered.
Appeal and cross-appeal dismissed without prejudice.
HARRISON and GLOVER, JJ., agree.
Hirsch Law Firm, P.A., by: E. Kent Hirsch, for appellant.
Robertson, Beasley & Ford, PLLC, by: Mark E. Ford; and Lisle Rutledge P.A., by: Donnie Rutledge, for appellees.
Notes
I hereby grant permission to Forsgren, Inc. the use of my property located at State Line Rd. (50) I understand that waste materials, dirt from the above named project will be permanently disposed of on the site.
