55 Colo. 138 | Colo. | 1913
delivered the opinion of the court.
This case was disposed of by the district court by sustaining a general demurrer to the complaint, and the only question involved is as to whether or not the complaint states facts sufficient to constitute a cause of action against the defendants. It is alleged in the complaint
It is then alleged that the construction of plaintiff’s ditch was commenced on the first of April, 1873, and completed in the spring of 1874, and thereupon it began the immediate use of the appropriated water. That for a period of twenty years after the completion of its ditch, and for more than ten years after the date'of said decree, plaintiff and its stockholders enjoyed during the entire irrigation season of each year, its said appropriation from the Cache la Poudre river, through its ditch and without interruption, and there was during said period and at all times a plentiful supply of water in the river to supply plaintiff’s appropriation, to the- end of each irrigation season; that beginning with the year 1892 plaintiff and its stockholders have been deprived of water for irrigation during the latter part of each season by the alleged wrongful conduct of the defendant.
It is then said that the defendant, The Pleasant Valley and Lake Canal Company “is the owner of a ditch with headgate on the south side of the Cache la Poudre river about one below the canon of the river, and above the headgate of plaintiff’s ditch. That the defendant company’s ditch extends in a south and easterly direction for a distance of three and one-half miles, through what is known as Pleasant Valley, where said ditch reaches what is known as Bingham Hill. That the said defendant company was a party to the said general adjudication decree of April 11th, 1882, and there was decreed to said
It is further alleged that the defendant John L. Armstrong as water commissioner, wrongfully permitted the Pleasant Valley and Lake Canal Company to take from the Cache la Poudre river, through its canal, about 40 cubic feet of water per second, to be used under the said extension, all of which water belongs to the plaintiff. That all of this has been against the protest of plaintiff, and contrary to its repeated and constant demand upon the water commissioner, that it be allowed to have furnished to its ditch the water which it claims under its appropriation. But that the defendant water commissioner has, at the request of the defendant company, closed the head-gates of the plaintiff, and deprived it of its appropriation of water which it so alleges it was entitled.
The prayer was for injunctive relief.
It will be thus seen that the complaint alleges in sub
The complaint also alleges that the defendant did not begin to apply this water to use under its extension until
It is the contention of the defendant that by the decree its rights to the use of the water under the extension stands adjudicated and therefore may not be considered in this proceeding. On the other hand, plaintiff contends that it is beyond the power of the court, by that decree, and at that time, to grant the defendant the priorities for which it so contends.
It appears from the complaint also, that the defendant has remained in the constant and uninterrupted use of the water in dispute from a time beginning with 1882 up to the filing of the complaint in 1909, or for a period of twenty-seven years. But the complaint alleges that this has been over the repeated and insistent protest of the defendant.
Briefly, the defendant from its three priorities of 1861, 1864 and 1872, neither used nor applied more than twenty cubic feet of water of the total amount claimed and decreed until it turned water into its extension in 1882, and but for the decree would be entitled to no more than the twenty cubic feet of water so used and applied as against the plaintiff as a junior appropriator.
The question of abandonment by the plaintiff since the rendition of the decree, is not alleged in the complaint.
Counsel for plaintiff in error cites Mercer Ditch Co. v. Armstrong, 21 Colo., 357, 40 Pac. 989, as supporting its contention in this case, but that case was likewise cited and relied on in Ditch Co. v. Ditch Co., 22 Colo. 115, 43 Pac. 140, where the court said; “Counsel for appellants,
. It is not alleged and it is scarcely possible, that the defendant’s extension of ten miles in length, and occupying three years in construction, and its claim to the use and application of water thereunder, was not duly considered and determined by the court at the time of the rendition of the decree.
So far as the complaint alleges, no objection was made, and we must therefore assume that the plaintiff acquiesced in the decree, which granted to the defendant the very things of which plaintiff now complains.
Under the adjudication statutes, the priorities between ditch companies and other owners of irrigation ditches, and also all other questions of law and right growing out of, or involved or carried thereunder, are adjudicated. Combs v. Farmers’ Highline Ditch Co., 38 Colo., 420, 88 Pac. 396.
It has been repeatedly held by this court that a proceeding to adjudicate priorities to the use of water for irrigation purposes cannot be attacked in a collateral proceeding after the statutory time for reformation or review in the court of original jurisdiction has expired, and the time for appeal has elapsed. Also that a decree in such case, cannot in the absence of fraud, be re-opened by a party thereto after the lapse of the statutory period provided.
The complaint in this case recites an adjudication of the very matter of which it complains and which must therefore be held to be res acljudicata.
The judgment is affirmed.
In Division.
Chibe Justice Musser and Justice G-abbert concurring.