134 P. 989 | Cal. | 1913
This cause comes here on an order of transfer following a judgment of affirmance in the district court of appeal for the second appellate district. The facts are fully and correctly stated in the opinion of that court, and we were, at the time of ordering the transfer, and are now, of the view that there had been a correct disposition of all points presented except that relating to the plea of accord and satisfaction. We entertained some doubt on this point, but our further examination has convinced us that it, too, was rightly disposed of by the district court of appeal. *27
The great weight of authority in American courts undoubtedly supports the rule that where the amount due is in dispute, and a check for an amount less than that claimed is sent to the creditor with a statement that it is sent in full satisfaction of the claim, and the tender is accompanied by such acts or declarations as amount to a condition that if the check is accepted at all it is accepted in full satisfaction of the disputed claim, and the creditor so understands, its acceptance by the creditor constitutes an accord and satisfaction, even though the creditor states at the time that the amount tendered is not accepted in full satisfaction. (Wald's Pollock on Contracts, 3d ed., p. 839.) Whether there was a dispute concerning the amount due and whether the tender was on condition that acceptance would be in full satisfaction, are primarily questions of fact for the trial court. In the case at bar we think, notwithstanding an expression to the contrary by the district court of appeal, that it appears clearly enough that the amount due was in dispute at the time of the acceptance and retention of the check. But the evidence was such as to justify the finding (impliedly if not expressly made) that the tender was not subject to the condition that an acceptance of the check would be a satisfaction in full. This is an essential element of an accord and satisfaction by tender of a check. In the absence of such condition, the retention of the check, at least where the creditor promptly notifies the debtor that he still insists upon payment of the balance claimed, does not establish his assent to the acceptance of the sum tendered as a full settlement.(Hillestad v. Lee,
The judgment is, accordingly, affirmed.
The opinion of the district court of appeal, above referred to, is as follows:
"The action was one to recover a balance due upon a contract dated March 20, 1909, alleged to have been entered into between defendant, party of the first part, and plaintiff of the second part, through which the second party agreed to furnish all the materials and construct a pipe-line upon a certain designated location shown by a map attached. The pipe-line exceeded two miles in length, the head of which was in and traversed a portion of the government reservation, and near the foot thereof the same was shown to cross the right of way of the Sante Fe Railroad. The contract provided that the work should be commenced within ten days after the first party shall have procured a permit to construct such pipeline through the reservation, and should be completed within thirty days thereafter. Partial payments were provided for, upon an engineer's estimate, during the progress of the work, *29 and twenty-five per cent of the contract price was to be retained as a final payment until thirty-six days after completion. It is averred that on March 24th notice was given of the issuance of a permit to construct the line across the public lands, and work was commenced April second and prosecuted with due diligence; that shortly after the commencement of the work the defendant entered into negotiations with the railroad company for permission to construct its pipe-line across the right of way of the railroad, and notified plaintiff that certain restrictions relative to a cement culvert were imposed by the railroad company as a condition precedent to crossing such right of way, and that it would require sixty days' time to construct such culvert; that defendant notified plaintiff that while time was of the essence of the contract it need not hurry with the work, only to the extent of having the line completed to the right of way by the time that defendant had completed its cement culvert; that plaintiff had completed its work up to the line of the right of way by the time defendant had commenced work on its culvert; that the culvert was not completed until the first of July; that on the second of July plaintiff proceeded to and did complete the construction of the pipe-line and the same was inspected and accepted by defendant on July 8th. Defendant made all payments, other than the completion payment, provided for in the contract, but on August 14, 1909, a balance of $1786.46 was unpaid upon such completion payment; that of such sum defendant had only paid $816.26, and a balance of $970.20 remained unpaid, for which plaintiff asked judgment.
"Defendant by its answer alleged that it had performed all of the obligations imposed upon it, and that the contract was not completed within the time specified, nor until July 8, 1909; that by reason of plaintiff's delay it had suffered damage to the amount of $970.20. It is further alleged that in August, 1909, defendant paid to plaintiff the sum of $816.26, which sum was received by plaintiff in full settlement, payment and discharge of the claim and demand set forth in the complaint, at which date of payment a dispute existed as to the amount of money due from defendant to plaintiff.
"The trial court found the allegations of the amended complaint to be true, and the allegations of the answer with reference to the accord and satisfaction to be untrue, and rendered *30 judgment in plaintiff's favor for the amount claimed, from which judgment defendant appeals upon a bill of exceptions.
"Appellant's first contention is, that the action being upon an express contract, and it affirmatively appearing from the complaint that the work was not completed within the time specified, plaintiff cannot recover thereon, but is relegated to an action based upon a quantum meruit. Section
"The only serious question, to our mind, relates to the issue of accord and satisfaction. An accord is defined by section
"We see no error in the action of the trial court in its rulings upon the admissibility of evidence; none at least sufficiently prejudicial to warrant a reversal.
"The judgment should be affirmed, and it is so ordered."
Beatty, C.J., does not participate in the foregoing.