Lаpenna Contracting, Ltd., Appellant, v David L. Mullen et al., Respondents, et al., Defendants.
528992
Appellate Division, Third Department
October 29, 2020
2020 NY Slip Op 06183
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.
Decided and Entered: October 29, 2020
Calendar Date: September 15, 2020
Before: Egan Jr., J.P., Mulvey, Aarons, Pritzker and Colangelo, JJ.
H. Scott Ziemelis, Middletown, for appellant.
Christopher J. Smith, Middletown, for respondents.
Colangelo, J.
Appeal from an order of the Supreme Court (Fisher, J.), entered February 4, 2019 in Ulster County, upon a decision of the court in favor of defendants David L. Mullen and Lynn M. Veluta-Mullen.
In July 2016, plaintiff and defendаnts David L. Mullen and Lynn M. Veluta-Mullen (hereinafter collectively referred to as defendants) entered into a construction contract to erect an addition to defendants’ home. To finance the project, defendants appliеd for a construction loan from defendant PrimeLending and, after entering into a contract with plaintiff required by the lender, closed on the loan.1 Pursuant to the contract, the project completion date was April 8, 2017. Defendants requested and were given two draws from the loan totaling $36,350 through December 2, 2016 and paid plaintiff an additional $9,515.48 out of pocket. Defendants terminated plaintiff‘s services in March 2017 and hired one of plaintiff‘s subcontractors to complete thе project. In May 2017, plaintiff commenced this action to recover $33,870, asserting, among other things, causes of action for breach of contract, quantum
Following a bench trial, Supreme Court dismissed рlaintiff‘s breach of contact claim, finding that plaintiff‘s contract violated
Initially, plaintiff argues that Supreme Court erred in dismissing its cause of action for breach of contract and awarding defendants damages on their counterclaim. “When reviewing a nonjury verdict, [this Court] independently review[s] the probative weight of the evidence, together with the reasonable inferences that may be drawn therefrom, and grant[s] the judgment warranted by the record while according due deference to the trial court‘s factual findings and credibility determinations” (Galarneau v D‘Andrea, 184 AD3d 1064, 1065 [2020] [internal quotation marks and citations omitted]; see Grimaldi v Sangri, 177 AD3d 1208, 1209-1210 [2019]; Protect the Adirondacks! Inc. v New York State Dept. of Envtl. Conservation, 175 AD3d 24, 27 [2019]).
The record reflects, and plaintiff does not dispute, that he failed to comply with
Turning to Supreme Court‘s award to defendants on their counterclaim for breach of contract, we find that the record evidence supports the court‘s finding that plaintiff breached the contract. “To recover for a breach of contract, a party must establish the existence of а contract, the party‘s own performance under the contract, the other party‘s breach of its contractual obligations, and damages resulting from the breach” (Adirondack Classic Design, Inc. v Farrell, 182 AD3d 809, 811 [2020]; see Carroll v Rondout Yacht Basin, Inc., 162 AD3d 1150, 1151 [2018], appeal and lv dismissed 32 NY3d 1035 [2018]; WFE Ventures, Inc. v Mills, 139 AD3d 1157, 1160 [2016]). The credible testimony at trial established that the work performed by plaintiff was deficient, beginning with plaintiff breaking both the water line and septic pipe during excavation. According to the testimony of the engineer, industry custom and standards required plaintiff, after the water line was broken, to locate and mаrk the septic pipe before excavating. In addition, plaintiff failed to follow the architectural plans furnished to it and instead created a new plan that did not reflect defendants’ original plan or their wishes. As a result, a set of stairs was incorrectly installed overlapping the parking bay in the garage. A photograph of the garage was introduced on defendants’ case, which corroborated this testimony. The record further established, among other things, that the contract provided for the installation of a concrete retaining wall extension to the foundation. Instead, plaintiff built a stonewall from materials on defendants’ property.
Moreover, the record demonstrates that, when plаintiff was fired in March 2017, approximately seven months after work
Plaintiff next contends that the damages awarded to defendants on their breach of contract counterclaim was excessive. We disagree. “[T]he proper measure of damages for breach of a construction contract is the cost to either repair the defective construction or complete the contemplated construction” (Haber v Gutmann, 64 AD3d 1106, 1108 [2009], lv denied 13 NY3d 711 [2009]; see Feldin v Doty, 45 AD3d 1225, 1226 [2007]). Supreme Court found that defendants werе entitled to a credit in the amount of $13,235 for charges that were double billed. Such credit lowered the amount that defendants owed plaintiff under the contract to $32,630.48, leaving a contract balance of $52,119.52 had plaintiff completed the project. Defendants paid plaintiff‘s subcontractor $81,910.43, which the court found was reasonably necessary to complete the project, and plaintiff was therefore liable to defendants for the difference of $29,790.91. The cоurt erred, however, in awarding defendants $43,025.91 on their breach of contract counterclaim since $13,235 was already accounted for when the court lowered the amount that defendants owed plaintiff under the contract from $52,119.52 to $32,630.48. Accordingly, we modify the amount of damages that Supreme Court awarded to defendants on their counterclaim for breach of contract to $29,790.91.
Next, we find no merit to plaintiff‘s contentions that Supreme Court erred in finding that it exaggerated the mеchanic‘s lien
Here, the record reflects that all alleged “additional work” was included in the contract for which plaintiff was already paid over $45,865.48 at the time that it filed the lien. As Supreme Court correctly found, an award of the claimed lien amount of $33,780 would result in a payment to plaintiff of $79,735.48, or 94% of the contract price, when expert testimony established that plaintiff performed only $36,350 worth of reasonable site work. Given these estimations and the court‘s findings of plaintiff‘s аnd LaPenna‘s inability to be trustworthy, the court‘s determination that plaintiff willfully exaggerated the lien beyond inaccuracy “in an attempt to coerce . . . [d]efendants to acquiesce to plaintiff‘s unreasonable and fictitious demands” is a sufficient basis to find willful exaggeration, rendering the lien null and void and rendering plaintiff liable in damages to defendants (see
Egan Jr., J.P., Mulvey, Aarons and Pritzker, JJ., concur.
ORDERED that the order is modified, on the law, without costs, by reversing so much thereof as awarded defendants David L. Mullen and Lynn M. Veluta-Mullen $43,025.91 on their counterclaim for breach of contract; said defendants are awarded $29,790.91 on said counterclaim; and, as so modified, affirmed.
