Thе declaration in this action of contract contains three counts but we are concerned only with the first, which is on an account аnnexed. Recovery was sought on quantum meruit for substantial performanсe of a building contract. 1 The judge found for the plaintiff in the sum of $1,885. A report to the Appellate Division was dismissed and the defendants appеaled.
*349 At the trial there was evidence tending to establish the following: Thе plaintiff, a builder, entered into a written contract with the defendants to build a house. The plaintiff commenced to build the house in July, 1957, and continuеd to work on it until late in November, 1957, at which time he had received $4,627.50 in pаyment from the defendants. At the time the plaintiff stopped work, four items of work and materials called for by the contract had not been completed or furnished. In addition, there were thirteen deviations from thе contract specifications on work that had been comрleted. These could be corrected only by “expending very substantial sums of money.”
The only questions presented arise from the denial of the defendants’ fourth, fifth and sixth requests for rulings.
The fourth request reads: “In order for the building contractor to recover for substantial performance he must prove that the deviations were immaterial or justified or excusеd.” This request was apparently based in part on a statement in
Hub Constr. Co.
v.
Dudley Wood Works Co.
There was no error in the denial of the fifth requеst, which reads: “In the absence of special exculpating circumstances, *350 an intentional departure from the precise requirements of the contract is not consistent with good faith in the endeavor fully to perform it, and unless such departure is so trifling as to fall within the rule de minimis it bars all recovery.” Since, as stated above, the judge found that there was no “intentional deviation” the request was immaterial.
The sixth request asked the judge to find for the defendant if he found that the plaintiff had “abandоned the job before completion according to the specifications and contract.” This request was rightly refused, for it was couсhed in language broad enough to bar recovery for any failure tо complete, however trivial, and, as pointed out above, thаt is not the law.
Order dismissing report affirmed.
Notes
The defendants argue that the plaintiff declared on the contract and is precluded from recovering on quantum meruit. But this point was not raised at the trial and is not open here. Moreover, there is nothing in the point in any event. “By declaring on an account annexed the plaintiff has by legal intendment stated all the allegations cоntained in all the common counts.”
Martha, Inc. of New York
v.
Remis,
