LANE-TAHOE, INC., A NEVADA CORPORATION v. KINDRED CONSTRUCTION COMPANY, INC., A NEVADA CORPORATION, AND DAVIS WADE KINDRED; LANE-TAHOE, INC., A NEVADA CORPORATION v. McKENZIE CONSTRUCTION, INC., A NEVADA CORPORATION
Nos. 7602, 7670
Supreme Court of Nevada
June 11, 1975
91 Nev. 385 | 536 P.2d 491
Breen, Young, Whitehead & Hoy, and Milos Terzich, of Reno, for Respondent Kindred Construction Company, Inc.
Woodburn, Wedge, Blakey, Folsom & Hug and Robert Cox, of Reno, for Respondent McKenzie Construction, Inc.
OPINION
By the Court, THOMPSON, J.:
These consolidated appeals are from orders of the district court, entered in lien foreclosure proceedings, denying motions to compel the arbitration of disputes arising under construction contracts.
The appellant in each instance, Lane-Tahoe, Inc., as owner, entered into written contracts with respondents, McKenzie Construction, Inc., and Kindred Construction Co., respectively for land site preparation and for the construction of condominiums. Each contract contains provisions for the arbitration of claims and disputes arising thereunder. McKenzie and Kindred seek court foreclosure of lien claims timely filed. Lane-Tahoe sought unsuccessfully to stay court action and to compel arbitration in lieu thereof. These appeals followed. We first must resolve a motion to dismiss tendered by Kindred.
1. Kindred filed a statement of facts constituting its claim of lien [
The motion to compel arbitration was offered pursuant to
A Rule 54(b) determination is not necessary if a statute or rule expressly authorizes an appeal. In DeLuca ImportingCo. v. Buckingham Corp., 90 Nev. 158, 520 P.2d 1365 (1974), we ruled that an appeal may be taken from an order denying a motion for an injunction,
Kindred‘s motion to dismiss is denied. We turn to consider the merits of the consolidated appeals.
2. The contractual provisions for arbitration are, in each instance, identical and, in relevant part, are quoted below.2 Moreover, each contract states that it “shall be governed by the law of the place where the Project is located.” The project is located in Washoe County, Nevada. Consequently, the arbitration provisions of the contracts are to be read in conjunction with the Uniform Arbitration Act of this state.
The underlying purpose of the Act is to preclude court intervention into the merits of disputes when arbitration has been provided for contractually. This is evident from a mere reading of the Act. A contract to submit controversies to arbitration, with certain exceptions, is valid, enforceable, and irrevocable.
Although Lane-Tahoe did not file a written demand for arbitration, neither did McKenzie nor Kindred. All had agreed, however, to settle their disputes in that manner. In view of that agreement, one of the contracting parties was obliged to initiate the arbitration process. Absent express language in the contract placing the initial burden on either party, that responsibility properly rests with the party seeking relief. Mamlin v. Susan Thomas, Incorporated, 490 S.W.2d 634, 639 (Civ.App. Tex. 1973); Nordenstrom v. Swedberg, 143 N.W.2d 848, 857 (N.D. 1966); Klein Coat Corp. v. Peretz, 153 N.Y.S.2d 92, 97 (Sp.Ct. 1956). He should not be free to litigate in the courts simply because his opponent did not demand arbitration. This is not to say that the opponent could not have initiated arbitration. We hold only that the burden to initiate arbitration is upon the party seeking relief and does not shift to the opponent absent a clear waiver of arbitration by the opponent. The parties seeking relief in these cases, that is, payment for the claimed balances due for their work, are the contractors McKenzie and Kindred.
This view is compatible with
The record contains nothing to suggest a waiver of arbitration by Lane-Tahoe. Waiver requires conduct which speaks the intention clearly. United Assn. Journeymen v. Stine, 76 Nev. 189, 199, 351 P.2d 965 (1960). The contracting parties did not discuss waiving arbitration. The passing of time after the disputes arose, without more, does not point to a waiver of the arbitration provisions by Lane-Tahoe, when the duty to initiate the arbitration process rested upon the claimants McKenzie and Kindred. There is nothing to show that Lane-Tahoe did not intend to rely upon arbitration should the claimants press their claims. When the lien foreclosure actions were commenced, Lane-Tahoe moved to stay them, and for arbitration. Had Lane-Tahoe answered to the merits instead of moving for arbitration, a waiver could be found. Galion Iron Works & Mfg. Co. v. J. D. Adams Mfg. Co., 128 F.2d 411, 413 (7th Cir. 1942). This, it did not do. Rather, it moved for the relief explicitly authorized by
3. The contracts provide that the demand for arbitration shall be made within a reasonable time and in no event “after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.” With regard to the McKenzie controversy, it is urged that the quoted language bars arbitration since Lane-Tahoe did not file its motion to compel arbitration until more than six months after
The mechanics’ lien law does not impair the right to sue for the debt claimed to be due.
4. The district court intimated that arbitration is not suited to a case where a lienor-contractor enjoys the statutory remedy provided by the mechanics’ lien law.
We find no authority holding that arbitration is inappropriate when the parties to a construction contract have agreed to that method of settlement. Neither the mechanics’ lien law nor the arbitration act discloses a legislative intention to preclude the voluntary arbitration of disputes arising out of a construction contract. The contractors before us have not attempted to demonstrate how or why they would be prejudiced by having the rights settled by the arbitration process to which they have agreed.5
We conclude that a valid arbitration agreement should be enforced as between the parties hereto.
Reversed, with direction to stay the lien foreclosure proceedings of McKenzie and Kindred, and to enter an order in each instance granting arbitration.
ZENOFF and MOWBRAY, JJ., concur.
GUNDERSON, C. J., and BATJER, J., dissenting:
With all respect, we believe the majority‘s resolution of the above cases is incorrect.
We believe that, as the district court perceived, staying lienproceedings while one claimant arbitrates potentially warps the lien law and permits one claimant to deprive others of their statutory remedies, merely by invoking a contract to which the others are not parties.
Even if no stay of proceedings be granted, the arbitration if compelled will often be futile; for the results will not be binding on the other claimants, who by statute have the right to have the court declare the existence, amount, and priority of all liens. See:
Notes
“Notice of the demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made . . . within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.”
(a) . . .
(b) An action upon a contract, obligation or liability founded upon an instrument in writing. . . .”
