Landowners appeal from the judgment of the trial court granting Landvatter Ready Mix, Inc. (“supplier”), a mechanic’s lien on landowners’ real estate. Landowners argue that the trial court’s entry of the lien was erroneous in that supplier had executed a lien waiver expressly waiving “any and all lien” on the subject real estate. We affirm in that we find that the lien waiver did not extend to concrete delivered after the waiver’s execution.
The facts are undisputed. Landowners 1 were renovating their two townhouses in St. Louis. R. Green & Sons Construction, Inc., (“subcontractor”) hired supplier to provide concrete for the renovation. The landowners’ funds for the project were distributed by Commonwealth Land Title Insurance Company (“escrow agent”).
Supplier made its first concrete delivery to the property on February 23, 1994, billing subcontractor $1,194.10 for this material. On February 28, 1994, supplier preparеd, executed, and delivered to escrow agent a lien waiver. Supplier was paid the $1,194.10 due for that concrete delivery. On March 2 and 10, 1994, supplier made two additional deliveries to the property for which it billed subcontractor $4,399.25 by invoice dated March 12,1994. On March 16 and 17,1994, supplier delivered materials to the property and billed subcontractor $2,106.80 by invoice dated March 31, 1994. Supplier did not exеcute any subsequent lien waivers. Although landowners fully paid their general contractor, supplier never received payment for any of the concrete delivered in March totaling $6,506.05. On September 13, 1994, supplier filed a statement for a mechanic’s lien for that amount along with a petition to enforce the lien.
After a bench trial, the court entered a default personal judgment for $6,506.05 for supplier and against subcontractor, as well as a personal judgment for supplier and against landowners in the same amount. Although supplier requested the entry of a mechanic’s hen, no hen was granted by the trial court.
Landowners subsequently filed a motion to amend the judgment. They asked the court *301 to strike the judgment against them and enter judgment in favor of them and against the supplier on its mechanic’s lien, or, in thе alternative, to strike the personal judgment against landowners and enter a judgment limited to enforcement of a mechanic’s lien on the property. The trial court entered an amended judgment and order maintaining the personal judgment against subcontractor who was in default, vacating the personal judgment against the landowners, and entering a new judgment granting supplier a mechanic’s lien on lаndowners’ property in the amount of $6,506.05. Landowners appeal.
Our standard for review in construing the supplier’s written lien waiver is
de novo
after independently considering the evidence and reaching our own conclusions.
Anchor Centre Partners v. Mercantile Bank,
Landowners’ first point alleges that the trial court’s entry of the mechanic’s lien was erroneous because it failed to enforce supplier’s lien waiver according to its terms. We disagree.
The Ken waiver prepared and executed by suppler on February 28,1994, stated:
... We the undersigned for and in consideration of the sum of Eleven Hundred Ninety Four & 10/100, and other good and valuable considerations, the rеceipt of which is hereby acknowledged, we do hereby waive and release any and aK Ken, and claim or right to Ken on said above described building and premises under the Statutes of the State of Missouri relating to Mechanic’s Liens, on account of labor and materials, or both, furnished by the undersigned to or on account of the said R. Green & Sons for said building and premises.
Landowners contend that this waiver unambiguously waived aK right to a Ken on the job and, therefore, suppKer waived its rights to a Ken on the property for the March deKveries. We do not agree that the Ken waiver extended to future deKveries.
In
Zeller v. Janssen,
The primary rule in the interpretation of written documents is to ascertain the intent of the parties and to give effect to that intent.
CB Commercial Real Estate Group, Inc. v. Equity Partnerships Corp.,
It has long been the rule that a mechanic’s Ken claim may be waived, but the intention to do so must be clearly manifested.
Herbert & Brooner Const. Co. v. Golden,
499
*302
S.W.2d 541, 545 (Mo.App.1973);
Lee v. Hassett,
The language of the Ken waiver herein does not clearly manifest an intent to waive mechanic’s Ken rights accruing subsequent to the date of the waiver. The waiver merely releases “any and аK Ken ... on account of labor and materials, or both, furnished by the undersigned ... for said building and premises.” The Ken employs the past tense verb “furnished,” while it includes no prospective language at aK. Had suppKer intended to waive subsequent Ken rights, the waiver could easily have been modified to waive rights for materials “to be furnished” or for materials suppKed “hereafter.”
See Metropolitan Federal Bank v. A.J. Allen,
In the facts and circumstances of this case we find additional support that suppKer had no intention, when it executed the Ken waiver in February in connection with materials de-Kvered in February, to waive Ken rights as to future deKveries of materials for which biKr ing and payment had not yet occurred. Sup-pKer’s president testified that the waiver corresponded to the February invoice for the February 23, 1994 deKvery of concrete. He further testified that he understood a waiver was only final if he marked it “final.” Sup-pKer’s president did not testify that he intended to waive anything other than the right to claim a Ken for the amount actuaKy paid to suppKer. The waiver was executed in consideration of the payment of the exact amount biKed and due on past deKveries. There was no evidence of any conversation, inducement, or promise to show the parties contemplated waiver on future deKveries of materials or had any reason to waive Ken rights on future deKveries. Further, there was no evidence of payment or considеration apart from payment to support such a waiver.
Instructive on this issue is
Lee v. Hassett,
SimKarly, the language of the Ken waiver and the evidence in this case do not show any intent or purpose to waive a Ken for materials deKvered in the future. The Ken waiver must necessarily be read to be limited to materials already deKvered and to have no prospective appKcation. The omission of the words “up to this date” in this Ken waivеr, which was given in consideration of payment of the exact amount biKed on past deKveries of materials, does not clearly manifest an intent to waive future Ken claims which may arise with respect to future deKveries of materials.
In addition, statutes creating mechanic’s Kens are remedial in nature and
*303
should be given a liberal construction so as to effectuate their object and purрose and protect the claims of the mechanics and materi-almen. The mechanic’s hen law is to be construed as favorably to the materialman as its terms permit.
Refrigeration Supplies, Inc., v. J.L. Mason of Missouri, Inc.,
In their second point, landowners assert that the hen waiver was vahd аs to subsequent deliveries because they rehed to their detriment on the waiver in disbursing payment to contractor. For a hen waiver to be vahd, it must be supported by consideration or must induce the party receiving the waiver to detrimentally change its position in rehance upon the waiver.
P & K Heating and Air Conditioning, Inc. v. Tusten Townhomes,
We have found herein that the hen waiver, as a matter of law, did not waive future hen rights. Therefore, the validity of thе hen is not at issue and estoppel to deny an invalid hen does not arise. The parties’ intention not to waive future rights precludes any assertion of estoppel. Point denied.
In their final point, landowners allege that the trial court erred in granting suppher a mechanic’s hen because suppher’s petition failed to state a cause of action. Landowners aver that suppher failеd to plead and prove that landowners contracted with subcontractor for the concrete, and that such proof is an essential element of a mechanic’s hen claim.
In order to successfully enforce a mechanic’s hen, the plaintiff must plead and prove each element of the mechanic’s hen statute.
Herbert & Brooner Construction Co.,
Landowners concede that suppher successfully showed that it supphed materials under a contract with subcontractor that went to the renovation site. They assert, however, that suppher failed to meet its burden in that its petition nowhere asserted that subcontractor had a contract with landowners for the concrete dehvered by suppher. Landowners further maintain that suppher did not prove at trial that they or their general contractor had contracted with subcontractor for suppher’s concrete.
An appellate court will not find error on an issue which was never presented to the trial cоurt for decision.
Boatmen’s Bank of Southern Missouri v. Foster,
The aheged deficiency in suppher’s petition that landowner now complains of was not raised in the trial court. Landowners have waited to raise the issue here for the first time.
See CB Commercial Real Estate Group, Inc. v. Equity Partnerships Corp.,
Landowners assert, however, that suppher’s failure to state a cause of action may be raised at any juncture, including on appeal. Rule 55.27(g)(2) provides, in part, “[a] defense of failure to state a claim upon which rehef can be granted ... may be made ... on appeal.” This is so because a pleading which states no cause of action confers no subject matter jurisdiction on a court.
Phillips v. Bradshaw,
Suppher’s petition aheged that it supphed conсrete under a contract with subcontractor. Suppher’s petition further aheged that landowners held interests in the real estate. But the petition failed to assert that a contract existed between subcontractor and landowners or between subcontractor and Trout Development, as the general contractor.
*304 The trial court, however, properly entered the mechаnic’s lien because evidence relevant to the contractual relationship was introduced at trial without specific objection by landowners, and the introduction of that evidence constituted amendment of the parties’ pleadings by implied consent.
Failure to timely and specifically object to evidence on the ground that it is beyond the scope of the pleadings constitutеs consent for determination of issues thereby raised.
Kackley v. Burtrum,
Not only did landowners fail to specifically object to supplier’s evidence, but they introduced their own evidence of their contractual relationship with escrow agent.
See Justus v. Webb,
When issues not raised by the pleadings are tried by express or implied consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings. Rule 55.33(b). Issues raised by implied consent are treated as if raised by the pleadings even though the pleadings are not formally amended to conform to the evidence.
Kackley,
Landowners maintain that implied consent only arises if: (1) the opposing party fails to object to the evidence and (2) the evidence is admissible solely on the subject of the аmendment, and not on any other issue already in the case.
Mahan v. Missouri Pacific R. Co.,
We must consider all fact issues upon which no specific findings wеre made by the trial court to have been found in accordance with the result reached.
P & K Heating and Air Conditioning, Inc.,
In addition, landowners’ reliance on the proposition that pleadings can be amended by implied consent only when the evidence is solely relevant to an unpleaded issue is misplaced. First, that proposition originated in cases in small claims court and the associate division where formal pleadings are not required. Section 517.031 RSMo (1994); Rule 147;
Richardson v. Collier Bldg. Corp.,
*305
In
Richardson v. Collier Bldg. Corp.,
Appellant speaks of an alleged unfairness in this case by allowing amendment of the pleadings through implied consent. Actually, the unfairness would be in allowing appellant to take advantage of technical rules to exclude defenses to which it had full prior knowledge of the relevant facts.
Id.
The same policy applies with equal force here. Landowners were aware of the facts relevant to the contractual relationship between supplier and themselves and cannot claim surprise or prejudice. They, themselves, offered most of the evidence of those facts. Yet, lаndowners waited until appeal to object to the deficiency in supplier’s petition rather than move to dismiss prior to or during trial to allow supplier an opportunity to cure the defect.
The testimony of escrow agent’s representative and the introduction of the escrow agreement provided evidence sufficient to support the trial court’s implicit finding of the necessary сontractual relationship between subcontractor and landowners, and thereby with supplier. The introduction of this evidence cured any defect in supplier’s pleadings. The petition did state a cause of action. Point denied.
The judgment is affirmed.
Notes
. For purposes of this appeal, we refer to Karen Buckey and her co-defendant, Trout Development, Inc., collectively as landowners. The record is unclear as to Buckey’s exact interest in the property.
. Landowners’ counsel has obtained a copy of the lien waiver form used in Zeller; it did not appear in the opinion.
