135 P. 392 | Okla. | 1913
On the 20th day of December, 1909, in the district court of Grant county, Doop Frater, a partnership, brought suit against the Lamont Gas Oil Company, on account of an alleged indebtedness, due said partnership, arising out of a contract to drill two oil or gas wells for the defendant company. Plaintiff's petition alleged that there was due it the sum of $1,078.75 for drilling and $1,064 for reaming a well by it drilled under said contract, and an additional cash bonus of $300, or a total of $2,442.75. The drilling contract relied upon by plaintiff was in writing, and a copy thereof is attached to plaintiff's petition, and made a part thereof. The provisions of the contract bearing upon the controversy between the parties are as follows:
"That in consideration of one dollar and twenty-five cents ($1.25) per lineal foot, the parties of the second part agree to drill two wells for gas or oil for the party of the first part, to a depth of eight hundred and fifty (850) feet unless sooner stopped by party of the first part. In event that the said party of the first part should stop drilling before a depth of six hundred and fifty (650) feet is reached, as a result of striking gas or oil, then said party of the first part agrees to pay said party of the second part one dollar and twenty-five cents ($1.25) per lineal foot to the depth of six hundred and fifty (650) feet, termed in that event, the completion of the well. It is agreed that the said second party shall use all due diligence and care to enter all gas sand in as dry condition as possible.
"Should it be necessary, and possible, to drill said well deeper than eight hundred fifty (850) feet, said parties of the second part agree to drill the same deeper at the same price per lineal foot as herein before mentioned, to such depth as is deemed satisfactory to said party of the first part, or to water." *429
Defendant's answer denies any liability to plaintiff, on account of the latter's failure to comply with the terms of said written contract, and asked judgment in the sum of $1,000 damages, caused by plaintiff's breach of said contract. The trial resulted in a verdict in favor of plaintiff in the sum of $1,392.50.
Considering the assignments of error in the order presented in the brief of counsel for plaintiff in error, we shall first consider the paragraphs of the court's charge complained of. Construing the drilling contract, the court gave the jury the following charge:
"You are instructed, gentlemen of the jury, that under and by virtue of the contract entered into by and between the plaintiff and the defendant all money was due and payable under said contract for drilling and completing said well when said well was turned over to and accepted by the party of the first part — that is to say, the defendant in this case — less such sums as had been advanced, but in this regard you are instructed as a matter of *430 law that if you find from a preponderance of the evidence that the plaintiff dug or sunk said well to the depth of 850 feet, said well, under and by virtue of the terms of the contract was completed, and the amount due for the construction of said well, including the amount due for necessary reaming, was then and there payable, and an arbitrary refusal upon the part of the defendant to accept said well could not avail the defendant in this case."
It is not denied but that plaintiff had drilled said well to a depth of 863 feet. The court's charge told the jury that if said well had been drilled to a depth of 850 feet, then under and by virtue of the terms of the contract it was completed, and that both the amount due for drilling and necessary reaming was then and there payable. Obviously this was error, as the contract provided that, should it be necessary and possible to drill said well deeper than 850 feet, the plaintiff should do so, to such a depth as was deemed satisfactory to said party of the first part, or to water, and at the same price per lineal foot as thereinbefore provided. The court's charge does not take into consideration the latter part of the first provision of the contract, hereinbefore set out. Nor does it consider the further provision of said contract, providing that all money shall be due and payable on said drilling contract when each well is turned over to and accepted by said party of the first part, less such sums as have been advanced under authority of another provision. It is not contended that the well drilled was at any time accepted by defendant, but that on the other hand, acting through its officers, it at all times demanded of plaintiff that it drill said well to a greater depth, as it had agreed and undertaken to do. No oil or gas had been found when the depth of 863 feet was reached. It does not appear that further drilling was impossible, so that, if the prospecting for oil and gas was to be continued further, as was the purpose of the contract, it was necessary to drill the well deeper. It was doubtless this very thought that prompted the parties to expressly provide for the continuation of the drilling until either the owner of the well was satisfied, or water was reached, and for which further drilling additional consideration was provided. No payment, other than $75 and the cost of fuel, was to be paid until *431 the well being drilled was turned over to and accepted by the company. This included, not only the cost of drilling, but the incidental work of reaming as well.
In construing a contract the intention of the parties must be deducted from the entire agreement, and not from any part or parts thereof, because where a contract has several stipulations, it is plain that the parties agreed that their intention was not expressed by any single part or stipulation of it, but by every part and provision in it, considered together, and so construed as to be consistent with every other part. Kansas City Bridge Co. v. Lindsay Bridge Co.,
Concerning defendant's counterclaim, the court gave the following instruction:
"You are instructed, gentlemen of the jury, that if any amount was due from the defendant to the plaintiff for reaming said well, as defined by these instructions heretofore given, and upon the completion thereof — that is to say, when said well was dug to the depth of 850 feet — the defendant denied any liability for reaming and refused to pay therefor, the plaintiff was justified in refusing to continue the digging of said well, and the defendant would not be entitled to recover anything upon their cross-bill in the shape of damages, unless you find that the charges presented for reaming were fraudulent, wicked, wrongful, and were not made in good faith."
As we have seen, payment for drilling and completing said well, which would, of course, include any necessary reaming, was not due until the well was turned over to and accepted by the company, unless it should be made to appear that defendant not *432 only refused payment at the time, but unconditionally denied liability, even though plaintiff continued to perform and carry out its part of the contract. The principal vice of the instruction lies in the fact that it tells the jury that defendant would not be entitled to recover damages on its counterclaim, unless the charges presented by plaintiff for reaming were fraudulent, wicked, wrongful, and not made in goodfaith. Why it should first be determined that the charges presented for reaming were of the character indicated we are unable to conjecture, and counsel for plaintiff below, having filed no brief in this court, have not undertaken to defend the charge. If plaintiff had misconstrued the terms of the contract, and was asserting a claim for which defendant was not legally liable, or which under the contract was not then due, and, persisting in its position, refused to carry out and perform its part of the contract, in consequence of which defendant sustained injury, the plaintiff would be liable for such damages as would fairly compensate the defendant for the loss sustained, without regard to the existence of an evil motive on plaintiff's part.
At the trial the defendant sought to introduce evidence for the purpose of showing that at the time the contract was entered into the members of the plaintiff firm explained to the officers of defendant company the meaning of the clause with reference to reaming the well, providing that the party of the first part was to pay for all reaming necessary, at $25 per day, labor of 24 hours, for two men. This testimony was by the court excluded, and it is urged as ground for reversal. It does not appear, however, from the record before us what the evidence of the several witnesses would have been, if admitted. In order that this court may consider assignments of error relating to the exclusion of evidence, there must be a showing in the record as to what the excluded evidence would have been before the court can say that there is reversible error in the ruling. Hutchings v. Cobble,
Other errors assigned by plaintiff in error we deem it unnecessary to consider. The record contains over 300 pages of unindexed typewritten matter. The applicability and correctness of the defendant's requested instructions would involve a close and careful consideration of the entire record, and that without the aid of a brief on the part of the defendant in error. The court's charge, in the particulars heretofore indicated, constituted error necessitating a reversal of the case.
The judgment of the trial court should therefore be reversed, and the cause remanded for a new trial.
By the Court: It is so ordered. *434