LAMELL LUMBER CORPORATION
v.
NEWSTRESS INTERNATIONAL, INC.
Supreme Court of Vermont.
*1217 Lisa B. Shelkrot and Clara F. Gimenez of Langrock Sperry & Wool, LLP, Burlington, for Plaintiff-Appellee.
Carrie J. Legus of Legus and Bisson, PLC, Montpelier, for Defendant-Appellant.
Present: REIBER, C.J., DOOLEY, JOHNSON and SKOGLUND, JJ., and DiMAURO, D.J., Specially Assigned.
¶ 1. SKOGLUND, J.
Plaintiff Lamell Lumber Corp., a lumber wholesaler and retailer based in Essex Junction, Vermont, entered into a contract with defendant Newstress International, Inc., a New Hampshire corporation, requiring defendant to fabricate a number of precast concrete panels and to "design, manufacture, truck, and erect these components" into a concrete kiln for plaintiff to use in the drying of lumber. After the kiln was completed, plaintiff detected an increasing number of cracks and holes in the concrete, which resulted in this lawsuit against defendant for breach of contract, breach of implied warranty, and negligence.[1]*1218 The jury returned a special verdict in favor of plaintiff, finding defendant to be liable on all three counts, and awarded damages of $100,000. On appeal, defendant contends the trial court erred in: (1) exercising subject matter jurisdiction despite the presence of an arbitration clause in the contract; (2) failing to dismiss the action as untimely under the four-year statute of limitations applicable to the sale of goods; (3) submitting the negligence claim to the jury; (4) instructing on damages; (5) excluding the testimony of defendant's expert witnesses; and (6) imposing sanctions against defendant. We affirm.
¶ 2. The basic facts may be briefly summarized. Additional material facts will be set forth in the discussion which follows. In November 1993, the parties entered into a contract calling for defendant to "design, manufacture, truck, and erect" a number of precast, prestressed concrete panels into a structure to be used by plaintiff as a kiln for drying lumber at its mill in Essex Junction. The kiln was completed in late 1993 or early 1994. Although the parties dispute the extent of defendant's participation in the design of the project, plaintiff adduced evidence at trial that defendant designed the concrete panels, the panel connections, the arrangement and location of the insulation materials inside the panels, and the building footings.
¶ 3. Plaintiff first noticed cracks in the kiln and reported them to defendant in the spring of 1998. Efforts over the next several years to repair the disintegrating concrete were unsuccessful, resulting in the filing of this lawsuit in April 2003. Following a series of pretrial motions, discussed more fully below, the case proceeded to trial in October and November 2005. Plaintiff's engineering expert, David Mitchell, testified that the building had not been properly designed to withstand the heat of the kiln, and that the deterioration of the concrete was caused by the improper arrangement of the insulation blocks inside the concrete panels and the improper connection of the panels to each other. As noted, the jury returned a special verdict in favor of plaintiff, awarding damages of $100,000. This appeal followed.
I.
¶ 4. Defendant first claims that the superior court lacked subject matter jurisdiction over this action. The basis of the claim is a clause in the parties' contract providing that all disputes arising out of the agreement shall be decided by arbitration. Although defendant raised the arbitration clause as an affirmative defense in its answer to the complaint, filed in June 2003, it proceeded to actively litigate the case over the next two years, responding to plaintiff's discovery requests and propounding requests of its own, attending depositions and other court proceedings, scheduling and canceling a mediation, and seeking several continuances of the jury draw. In early July 2005, however, about one month before trial was scheduled to commence, defendant filed a motion for summary judgment, arguing that the arbitration clause in the agreement deprived the court of subject matter jurisdiction and "estopped" plaintiff from pursuing its claims. Although plaintiff's counsel thereafter agreed to submit to arbitration, defendant rejected the offer on the ground that "any effort on the part of [plaintiff] to initiate arbitration at this time on its *1219 claims would be time-barred." Plaintiff thereupon filed an opposition to the motion, disputing defendant's claim that the court lacked subject matter jurisdiction and arguing that, by actively engaging in the litigation process for over two years, defendant had waived the arbitration agreement.[2]
¶ 5. The court issued a decision in October 2005, rejecting defendant's claim that it lacked subject matter jurisdiction and agreeing with plaintiff that defendant had waived the right to arbitration. Defendant contends the court erred, arguing that where, as here, a dispute is subject to an arbitration agreement, the Vermont Arbitration Act, 12 V.S.A. §§ 5651 to 5681 (VAA) confines the court's jurisdiction to certain statutorily defined proceedings and excludes civil actions based on the contract. As explained below, the claim is unpersuasive.
¶ 6. "Subject matter jurisdiction" refers to the power of a court to hear and determine a general class or category of cases. See In re B.C.,
¶ 7. Notwithstanding its presumptively broad jurisdiction, defendant asserts that the superior court here lacked subject matter jurisdiction over plaintiff's contract and negligence claims as a result of the arbitration clause in the contract. Defendant relies on the VAA section authorizing the superior court to issue nine specific orders in relation to an agreement to arbitrate, including orders to compel arbitration, appoint arbitrators, confirm or vacate an arbitration award, and enter judgment on an award. 12 V.S.A. § 5671. Defendant claims that § 5671 effectively limits or "demarcates the parameters of the superior court's jurisdiction" and by implication divests the court of other authority. However, the superior court is presumed to retain jurisdiction over all civil actions unless the Legislature has clearly indicated to the contrary. Contrary to defendant's assertion, we find nothing in the language of § 5671 or the VAA as a whole that suggests a legislative intent implied *1220 or otherwise to "oust" the superior court of general jurisdiction over a civil suit arising from a contract containing an arbitration agreement.
¶ 8. Apart from the absence of any clear evidence of legislative intent, defendant's argument also lacks support in case law or other authority. Indeed, jurisdictional claims similar to defendant's have been uniformly rejected in other states. See, e.g., Multi-Service Contractors, Inc. v. Town of Vernon,
¶ 9. In further support of its claim that the arbitration agreement was jurisdictional and therefore could not be voluntarily waived defendant cites a section of the VAA providing that a written arbitration agreement "creates a duty to arbitrate, and is valid, enforceable and irrevocable." 12 V.S.A. § 5652(a). As that section implies, Vermont law and public policy strongly favor arbitration as an alternative to litigation for the "efficient resolution of disputes." Springfield Teachers Ass'n v. Springfield Sch. Dirs.,
¶ 10. Although we have not previously addressed this precise issue, numerous decisions from other jurisdictions have endorsed this view. See, e.g., Shahan v. Brinegar,
¶ 11. Accordingly, we discern nothing in the VAA or other authority to support the claim that the arbitration agreement could not be waived as a matter of law, or to invalidate the trial court's finding that defendant's active participation in the litigation process and failure to assert the arbitration agreement in a timely fashion resulted in a waiver. The waiver issue is generally held to be a question of fact to be resolved under the circumstances of each case, considering such factors as the timing of the request for arbitration, the extent to which the party seeking arbitration has participated in the judicial process, and whether the party opposing arbitration has suffered prejudice through the incursion of litigation time, costs, and expenses. See Home Gas,
II.
¶ 12. Defendant next contends the court applied the wrong statute of limitations in ruling that plaintiff's complaint was timely filed within six years of discovery of the injury under 12 V.S.A. § 511. Defendant argues that the court should have applied the four-year statute of limitations applicable to the sale of goods under Article 2 of the Uniform Commercial Code (UCC), codified at 9A V.S.A. § 2-725(1).[5] Defendant argues that plaintiff's claim was barred by the UCC's four-year statute of limitations. As noted, although the contract here provided for the sale of goods consisting of prestressed concrete slabs, it also called for defendant to "design, manufacture, truck and erect the components," and the trial court concluded that these service aspects of the contract controlled for purposes of determining the correct statute of limitations. See Congdon v. Taggart Bros.,
¶ 13. It is well settled that where, as here, a transaction contains elements of both sales and service, application of the UCC, including the four-year statute of limitations under § 2-725(1), turns on whether the transaction "predominantly," or essentially, relates to goods or services. Lucien Bourque, Inc. v. Cronkite,
¶ 14. In determining the essential or predominant aspect of an agreement, courts typically look to several factors. Foremost among these are the language of the agreement itself and the circumstances of its making and performance. See Insul-Mark,
¶ 15. The terms of the contract and the circumstances of its performance thus demonstrate that the purchase and sale of the component materials themselves, while necessary to the project, were incidental to the overall objective of designing, engineering, and erecting the kiln according to the plans provided by defendant. Ample authority supports the conclusion that, in such circumstances, the contract was not subject to the UCC. See, e.g., Lincoln Pulp & Paper Co. v. Dravo Corp.,
III.
¶ 16. Defendant's remaining claims do not require extended discussion. *1224 First, defendant contends that the court erred in submitting the negligence claim to the jury, asserting on appeal as it did at trial that the evidence failed to demonstrate a tort duty separate from the contractual obligation. Plaintiff adduced substantial evidence to support a theory of liability premised upon defendant's negligent design and construction of the kiln, and we have elsewhere recognized the tort of professional negligence for breach of a duty to exercise reasonable care and responsibility in the design and construction of a project arising out of a contractual commitment. See Howard v. Usiak,
¶ 17. Defendant next contends that the court erroneously instructed the jury that it could award damages for the "reasonable cost of either repairing or replacing" the entire kiln, including the cost of tearing down the building, in view of a contract provision limiting damages to the cost of correcting or replacing any defective or nonconforming material. The provision in question, however, by its terms deals exclusively with the remedies available for "defective materials." Plaintiff adduced evidence at trial that the disintegration of the concrete was, in fact, caused by the improper design or arrangement of the insulation inside the concrete panels and the connections of the panels to each other, not by defects in the materials per se. Thus, the contract provision did not by its terms limit the damages available as defendant contends. Nor, by its terms, did it exclude any potential tort remedies flowing from the negligent design and construction. See Colgan,
¶ 18. Defendant next contends that the court abused its discretion in excluding the testimony of three proposed expert witnesses. Under our discovery rules a party may compel its opponent to identify the experts that it intends to call at trial, the subject matter on which the expert is expected to testify, and the grounds for the expert's opinion. V.R.C.P. 26(b)(4)(A)(i). We have held that the trial court has the inherent authority and discretion to enforce the discovery requirements of Rule 26, and that its imposition of discovery sanctions will not be overturned absent an abuse of that discretion. Greene v. Bell,
¶ 19. The record here reveals that defendant failed to respond to plaintiff's request to identify expert witnesses, resulting in a court order providing for "[n]o expert disclosure by Defendant after July 11, 2005." Four days after the court's deadline, defendant filed a brief notice indicating an intention to call Chad Phillips, an engineer, as an expert witness "to rebut the conclusions contained in the Richard Servidio report." Plaintiff thereupon moved to preclude the expert based on the untimely disclosure. Defendant filed no response to the motion and failed to supplement the disclosure by August 15, 2005, as permitted by the trial court at a hearing on August 1, 2005. Accordingly, the court issued an order, dated August 23, 2005, that defendant would be precluded from calling expert witnesses.
¶ 20. Defendant asserts that the belated disclosure of Mr. Phillips was justified by plaintiff's disclosure, shortly before the July 11 deadline, of a new expert witness, David Mitchell, propounding new theories of liability. The claim, however, is belied by defendant's own expert-witness disclosure indicating that Mr. Phillips would be called to rebut Richard Servidio, an expert whom plaintiff had disclosed much earlier. Nor does defendant explain or justify its failure to supplement the disclosure with additional information about Phillips' testimony or the names of other experts between the original July 11 deadline and the court's August 23 order. Accordingly, we find no basis to conclude that the court abused its discretion in barring defendant from calling Phillips as an expert witness.
¶ 21. Defendant also claims that the court erred in barring the expert testimony of a licensed engineer, Terry Waite. However, defendant offers no argument to support the claim, and we therefore find no error. In addition, defendant claims the court abused its discretion in precluding Nishan Nahikian, its owner and principal, from testifying as an expert. Mr. Nahikian was identified as a fact witness and ultimately provided extensive testimony at trial. The court refused to allow him to testify as an expert witness based on defendant's failure to identify him as such by the disclosure deadline.
¶ 22. We have recognized that an expert "whose knowledge or opinions are relevant because of his participation in the events giving rise to suit should be treated for discovery purposes as an ordinary witness." Hutchins v. Fletcher Allen Health Care, Inc.,
¶ 23. Finally, defendant disputes the court's award of sanctions against Newstress rather than against defense counsel based on their joint failure to appear at a jury draw scheduled for July 27, 2005. The court imposed a monetary sanction of $4,718.25 against Newstress, consisting of the attorney's fees and costs incurred by plaintiff in attending the jury draw. Defendant summarily "requests that the sanction apply to trial counsel instead" but makes virtually no argument or showing that the trial court either lacked the authority to impose the sanction or abused its discretion in doing so. We have observed that the trial court has inherent authority to impose sanctions when necessary, in its discretion, to protect the integrity of the judicial system or "instill respect in both litigants and litigators for the law and the legal process." Van Eps v. Johnston,
Affirmed.
NOTES
Notes
[1] The original complaint did not include a claim for negligence, but the court granted plaintiff's subsequent motion for leave to add the count. The original complaint also included a claim for consumer fraud, but the court granted summary judgment in favor of defendant on this count, and plaintiff has not appealed from the ruling.
[2] We note that defendant has retained new counsel on appeal.
[3] Although defendant contends that the VAA is more restrictive of the court's jurisdiction than either the Federal Arbitration Act or the Uniform Arbitration Act, and that decisions from other jurisdictions are therefore distinguishable, we find nothing in either the VAA or the federal or uniform acts to support the claim. Nevertheless, we need not, and do not, rely on federal law to conclude that the VAA did not divest the superior court of jurisdiction or preclude its finding that defendant waived the arbitration agreement. Defendant also relies on several out-of-state decisions, but careful examination shows that they do not support its position. Defendant cites Hughley v. Rocky Mountain Health Maintenance Organization, Inc.,
[4] Although defendant subsequently raised the issue in its reply brief, arguing that its motion for summary judgment to enforce the arbitration clause was in fact timely, arguments raised initially in a reply brief will generally not be considered on appeal. Montgomery v. Devoid,
[5] Defendant raised the issue for the first time in a motion for judgment on the pleadings, filed in late July 2005, within a month of the scheduled trial date.
[6] We addressed an analogous issue in DaimlerChrysler Services North America v. Ouimette,
[7] In further support of the claim, defendant invokes the "economic loss" doctrine, which generally prohibits recovery in tort for primarily economic losses. Gus' Catering Inc. v. Menusoft Sys.,
[8] Defendant has appended a hearing transcript to its reply brief in which the trial court indicates that it would consider permitting Mr. Nahikian to testify as an expert on certain subjects if plaintiff had questioned him about those subjects at his deposition, since there would then be no prejudicial surprise. Although defendant asserts that the court forgot this ruling at trial, defendant makes no claim or showing that the testimony it unsuccessfully sought to elicit from Mr. Nahikian at trial was, in fact, disclosed at the deposition.
