70 Ind. App. 537 | Ind. Ct. App. | 1919
On June 9, 1908, the Lake Michigan Water Company, appellant herein, desiring to improve its water supply system at Michigan City, Indiana, entered into a contract with the M. H. McGovern Company, hereinafter called the contractor, to make such improvement. The United States Fidelity and Guaranty Company, appellee, became surety on said contractor’s bond for the faithful performance of the contract. This action is by appellant on said bond. The contractor and said guaranty company were each made defendants, but process was never served upon the former. The complaint was in two paragraphs, to each of which appellee successfully demurred for want of sufficient facts. Appellant refused to plead further, and judgment was rendered that appellant take nothing, and that appellee recover costs. The appeal is from this judgment, and the only errors assigned are based on the rulings of the court on the demurrers to the two paragraphs of complaint. Appellant in its oral argument expressly waived the error, if any, as to the court’s ruling on the demurrer to the second paragraph of complaint, and rested its case on the alleged error of the court in sustaining appellee’s demurrer to the first paragraph.
The first paragraph of complaint, hereinafter de
It is contended by appellee, and such was the holding of the trial court, that the complaint is demurrable for the reason that the facts pleaded show that appellant was bound at its peril so to inspect the work as it progressed that all improper material or defective work would be discovered and rejected before making final payment sixty days after the work
It is very clear that the parties by their contract intended to place the engineer of the water company in charge of the work, and to make it his duty to supervise the construction, to the end that the improvement when completed should be in every particular in accordance with the plans and specifications. Appellee as surety on the bond had no voice in the acceptance or rejection of materials, but had a right to assume that the engineer would do his duty. The bond did not provide that the surety should be responsible for the conduct of the engineer in the exercise of the authority vested in him by virtue of