LAKE BLUFF HOUSING PARTNERS, a Wisconsin limited partnership, Plaintiff-Respondent, v. CITY OF SOUTH MILWAUKEE, and Michael Vesperman, in his capacity as City Building Inspector, Defendants-Appellants.†
No. 94-1155
Court of Appeals
Decided October 4, 1994
Oral argument August 10, 1994.
525 N.W.2d 59
†Petition to review granted.
For the plaintiff-respondent the cause was submitted on the briefs of Weiss, Berzowski, Brady & Donahue, with Debra A. Slater of Milwaukee.
Before Sullivan, Fine and Schudson, JJ.
I. FACTUAL BACKGROUND
The essential facts relevаnt to resolution of this appeal are not in dispute. According to the record and the trial court findings, Lake Bluff is a Wisconsin limited partnership engaged in the business of developing rental property. In December 1992, Lake Bluff purchased a parcel of land running along the shore of Lake Michigan in the City of South Milwaukee. Lake Bluff acquired the property, intending to construct a multi-family development that would qualify for low income housing tax credits administered by the Wisconsin Housing and Economic Development Authority (WHEDA).
Since 1965, the land had been zoned C-2, a classification that allowed for construction of multi-family residential units. Before purchasing the land, Lake Bluff verified that it was zoned C-2, and that such zoning would allow for a multi family development. The controversy in this case surrounds the circumstances between the time Lake Bluff purchased the
WHEDA awarded Lake Bluff a $266,903 site-specific tax credit for the project at the property. After receiving the WHEDA award of the tax credit, Lake Bluff paid WHEDA a non-refundable fee of $16,314, to reserve the credit. Lake Bluff then obtained a survey of the property at a cost of $1,150, and contracted with its architect to prepare plans for the project at a cost of $29,513. The trial court found that in order to preserve the WHEDA tax credit, Lake Bluff‘s project had to be built, and certificates of occupancy had to issue by December 31, 1994. Further, the trial court found that, in order for this to occur, Lake Bluff had to begin construction immediately.
In February 1993, representatives of Lake Bluff met with the mayor, city administrator, building inspector, city engineer, and district alderperson of South Milwaukee to review initial plans for the project, and to confirm that the prоject could proceed to the construction stage. The City confirmed that the property was in a C-2 zone that permitted a multi-family project. At that same meeting, however, the City advised Lake Bluff that in order to obtain a building permit, it would have to provide a bluff assessment establishing that the project would not cause bluff erosion. The City also advised Lake Bluff that South Milwaukee‘s parking requirements had changed and that Lake Bluff would have to modify its plans to meet the new requirements. As a result, Lake Bluff modified its parking plans and also commissioned a bluff erosion study costing $4,950. Further, as a result of that study, Lake Bluff modified its plans so that one of the buildings would be relocated.
On July 6, 1993, the South Milwaukee Common Council adopted a resolution, pertaining only to the Lake Bluff property, imposing a moratorium on the issuance of a building permit. The Plan Commission then considered the rezoning request at its meeting of July 12. The Plan Commission minutes of that meeting state in part:
William Fox restated his request to rezone the land from C-2 Commercial to R-A Residential. A memo from the City Attorney was read... in which he advised that a moratorium on the issuance of building permits for the property may be lawfully be
[sic] imposed provided it is enacted by resolution1 and reasonably related to the consideration of the rezoning of that property. [Alderman] Tessmer questioned the legality of rezoning any property without the consent of the owner, in this case, Lake Bluff Housing Partners. [Attorney] Eli Frank, representing Lake Bluff Housing Partners, stated his clients purchased the property in good faith, fully aware of the requirements of the existing zoning. They have expanded [sic] considerable effort planning an apartment complex which complies with every aspect of the City‘s zoning regulations.
On August 5, 1993, the Wisconsin Department of Industry Labor and Human Relations issued its сonditional approval of Lake Bluff‘s plans, thus enabling Lake Bluff to seek a footing and foundation building permit and then to begin construction. That same day, Lake Bluff did submit its application for the permit, but the building inspector denied the permit because of the moratorium. Two days later, Lake Bluff began a series of attempts to learn whether its application was deficient in any way, or whether the denial was based solely on the moratorium. Among other efforts, on August 7, Lake Bluff wrote to Vesperman:
Pursuant to our application for a “Footing/Foundation” permit on Thursday, August 5, 1993,... it is the understanding of this office that the following additional information will be required:
the City Engineer... will review the drawings deposited with your office to “verify site/building grades” for conformance, - your office will review the drawings deposited with your office for “conformance to required set backs,”
- two (2) additional sets of drawings are required for application, one (1) additional “State Approved” copy, plus one (1) not necessarily stamped set,
- evidence of “DILHR Letter of Approval” dated August 5, 1993 for each building, copies of which have been sent directly to your office by DILHR via the U.S. Mail, and
- Footing/Foundation permit for the above captioned project “has been denied” per [the moratorium] dated July 6, 1993. Any questions concerning this matter should be referred to the City Attorneys office, attention Mr. Joseph Murphy.
Should you be in disagreement with any of the contents of this letter, please notify this writer via facsimile... with a hard copy via U.S. mail, prior to the close of business on Monday, August 9, 1993.
The City did not respond. On August 20, Lake Bluff wrote to the City requesting a specific response that its application either: (1) would be approved, but for the moratorium; or (2) would be disapproved, even if there were not a moratorium, because of noncompliance.2
Please be advised that Mr. Vesperman has not yet reviewed the plans presented for the structural aspects of the property, has not verified the setbacks and zoning compliance and erosion control measures contemplated and the City Engineer has not had the opportunity to check the grading and zoning compliance. Furthermore, the Building Board of Review has not yet reviewed the plans.
Also, please be advised that inasmuch as the moratorium will not allow construction of this project until after November 4, 1993, neither the City Building Inspector nor the City Engineer intends to drop everything else that they are currently engaged in to process this application for a building permit. Your application for a permit will simply have to wait its turn for the attention like everything else thаt is coming across their desk. If there
is some reason that their review ought to be advanced and expedited, please advise me.
Although Lake Bluff did not reply directly to the city attorney‘s request to be advised “if there is some reason that... review ought to be advanced and expedited,” a Lake Bluff general partner wrote letters to the mayor of South Milwaukee on September 24 and October 7, requesting, in part, consideration “under whatever zoning category it may legally be determined to be now or in the future....” Despite Lake Bluff‘s efforts to secure a review of its plans, and despite the fact that, normally, the City processed such applications within one month of their receipt, the City did not review the plans and did not notify Lake Bluff of any deficiency in its application.
On October 7, the City held a public hearing on the rezoning request and, on November 2, 1993, the City enacted an ordinance, applicable only to the Lake Bluff property, rezoning it from C-2 to R-A.
On March 10, 1994, Lake Bluff resubmitted its application for a building permit, and also filed a complaint seeking a writ of mandamus to compel issuance of the permit. The complaint, in part, alleged:
Lake Bluff acquired vested rights in the C-2 zoning of the Property prior to South Milwaukee‘s enactment of the change in the zoning for the Property.
The change in the zoning of the Property is retroactive legislation and is unconstitutional, invalid and void.
Lake Bluff will be substantially damaged if it is unable to begin construction of the project at the Property by April 1, 1994 because it would then be unable to physically complete the project by December 31, 1994, which is a requirement of the approval
of the income tax credit program. There is no adequate specific legal remedy for the threatened injury, and the granting оf this Writ of Mandamus would not be inequitable.
In its answer filed March 16, 1994, the City, for the first time, asserted that Lake Bluff‘s August 5, 1993 plans failed to comply with C-2 zoning.3
The trial court, in its written findings of fact and conclusions of law and judgment, stated:
Only after Lake Bluff started this lawsuit, did South Milwaukee conduct the comprehensive review of Lake Bluff‘s application for building permit and only then did it identify any deficiencies in Lake Bluff‘s application. It did so at that time, in an additional effort to stop Lake Bluff‘s proposed development at the Property.
Since the start of this lawsuit, Lake Bluff has changed its plans to correct the deficiencies belatedly identified by South Milwaukee in Lake Bluff‘s permit application.
Lake Bluff would suffer significant and irreparable harm if it is not allowed to proceed with its planned construction at the Property immediately.
South Milwaukee had knowledge of Lake Bluff‘s proposed development at the Proрerty and of Lake Bluff‘s expenditure of significant sums of money toward accomplishing its development at the Property, before South Milwaukee imposed the moratorium for building at the Property or rezone the Property.
Accordingly, the trial court rendered the following conclusions of law:
Lake Bluff acquired protected vested rights and interests in the Property by virtue of the expenditures it made for the purchase price of the Property, the payment to WHEDA to reserve the low income housing tax credits, the cost of architectural plans and specifications, the survey costs and the costs for the bluff study, all in reliance upon the zoning in existence at the Property at the time that it purchased it.
Lake Bluff acquired its vested rights before South Milwaukee‘s enactment of the moratorium prohibiting the issuance of building permits at the Property.
South Milwaukee‘s actions in denying Lake Bluff‘s aрplication for a building permit were arbitrary, capricious and invalid.
Because it acquired vested rights in the existing C-2 zoning at the property, Lake Bluff is entitled to a Writ of Mandamus directing the Building Inspector to issue a permit allowing it to construct its project at the Property.
South Milwaukee is estopped from raising its belated objections to Lake Bluff‘s plans.
II. STANDARD OF REVIEW
“In reviewing a mandamus action, ‘the action of a trial judge in either granting or denying the writ will be affirmed’ unless the judge erroneously exercised discretion.” Keane v. St. Francis Hosp., 186 Wis. 2d 637, 645, 522 N.W.2d 517, 520 (Ct. App. 1994). We will affirm a discretionary determination of the trial court if it is:
demonstrably... made and based upon the facts appearing in the record and in reliance on the appropriate and applicable law.... [A] discretionary determination must be the product of a rational mental process by which the facts of record and law relied upon are stated and are considered together for the purpose of achieving a reasoned and reasonable determination.
Hartung v. Hartung, 102 Wis. 2d 58, 66, 306 N.W.2d 16, 20 (1981). In Neu v. Voege, 96 Wis. 489, 71 N.W. 880 (1897), the supreme court stated the criteria governing whether a trial court will issue a writ of mandamus:
To be sure, the granting or refusing of a writ of mandamus is somewhat discretionary, but when the application therefor is made by a person to enforce a clear legal right; the duty sought to be enforced is positive and plain; the applicant for the writ shows that he will be substantially damaged by nonperformance of such duty; and there is no other adequate specific legal remedy for the threatened
injury, and no laches on the part of such applicant, and no special reasons exist rendering a resort on his part to the remedy, under the circumstances, inequitable, to refuse to issue the writ constitutes an abuse of judicial discretion.
Id., 96 Wis. at 492-493, 71 N.W. at 881. In this case, the issue reduces to whether Lake Bluff had a clear legal right and whether the City had a positive and plain duty.
III. DISCUSSION
The City argues that the propriety of mandamus in this case must be measured precisely on March 10, 1994, when Lake Bluff resubmitted an application for a building permit. The City contends that, prior to March 10, Lake Bluff never submitted an application in compliance with the C-2 zoning requirements, and that, of course, on March 10, Lake Bluff‘s plans did not meet the requirements of R-A zoning.4 Therefore, the City maintains, Lake Bluff never was entitled to approval of its application. Thus, the City argues, in the absence of an application complying with zoning requirements, Lake Bluff had no clear legal right and the City certainly had no positive and plain duty to issue a permit.
Lake Bluff, on the other hand, аrgues that the propriety of mandamus must be measured more broadly, with consideration of all the surrounding circumstances. Lake Bluff suggests that, when we make that measurement, we should focus on the March 10 denial against the background of all that occurred both
The City argues that the trial court‘s conclusion that Lake Bluff “acquired vested rights in the existing C-2 zoning” is erroneous because a party can only have vested rights in property, not in zoning. The City points to several cases, including Buhler v. Racine County, 33 Wis. 2d 137, 146 N.W.2d 403 (1966), in which the supreme court stated, “Property holders have a great interest in zoning, but... they acquire no vested rights against rezoning because of their reliance upon the original zoning.” Id., 33 Wis. 2d at 148, 146 N.W.2d at 408. Thus, the City maintains, Lake Bluff‘s circumstances are no different from thоse of many parties who purchase property with plans to develop it, but later discover that their intended plans cannot go forward because of subsequent rezoning.5
Lake Bluff responds that “under certain circumstances, a property owner can acquire vested rights to proceed with construction despite a change in the zoning of property,” and that under the specific circumstances of this case it had acquired vested rights in the property entitling it to approval of the application. Lake Bluff maintains that, on August 5, 1993, it had the clear legal right to have its application considered, and to have it approved or disapproved under C-2 zoning. In effect, therefore, Lake Bluff contends that regardless of whether we measure from August 5, 1993, or from March 10, 1994, the City had a positive
Several cases have considered whether property owners have acquired vested rights in their property such that they can continue plans or construction despite zoning changes. In the Building Height Cases, 181 Wis. 519, 195 N.W. 544 (1923), the supreme court considered whether property owners in three separate cases had acquired vested rights such that they should be allowed to continue construction of buildings that would exceed the height restrictions imposed by a new statute.
In the first case, a company had planned a sixteen-story office building, had erected the first eight stories, and had placed a temporary roof above them, postponing completion of the building until the extension of its business required the additional floors. Before passage of the law, the company had decided to complete five more stories, and had expended $30,000 in engineering and architect fees, and had incurred additional liabilities before the new law took effect. Id., 181 Wis. at 530-531, 195 N.W. at 549. The court concluded:
[L]ong before the passage of the act the... company in good faith not only resolved but actually arranged for the completion of its original plans and to that end had incurred great expense. To construe this law as applying to the... company‘s building would work great hardship, a serious invasion of vested rights, and would give to the statute a retro-
spective effect which should not be given in the absence of a plain legislative purpose.
Id., 181 Wis. at 532, 195 N.W. at 549.
In the second case, the property owner had begun construction of a hotel before enactment of the law. Construction had progressed to the fourth floor before passage of the law. However, it was not until after the law‘s enactment that the property owner decided to add a ninth story to the building. Only after enactment of the law did the property owner apply for a building permit. Id., 181 Wis. 532-533, 195 N.W. at 549-550. The supreme court concluded:
Although it is alleged... that this defendant decided to add a ninth story to the building before the passage of the law, nothing whatever had been done to accomplish the purpose. Defendant had incurred no additional expense or liability and had not even obtained a permit. We can see nothing here in the nature of vested rights which are affected by the law distinct from the effect which the law has upon the rights of all other property owners.
Id., 181 Wis. at 533, 195 N.W. at 549-550.
In the third case, the property owner had received a permit to erect a hotel, but had not begun actual construction of the building. The owner had, however, proceeded with the project which included erection of another building across the street from the property. The owner had engaged architects, arranged for financing, and had begun tearing down the structure on the site where the hotel was planned. Although the hotel would be less profitable if its intended height would have to be reduced in compliance with the new law, the expenditures would not be wasted. Id., 181 Wis. at 533-534, 195 N.W. at 550. The supreme court concluded:
These facts place this case on middle ground as compared with the other two cases. While these defendants secured a permit and commenced building operations prior to the enactment of the law, there is no allegation that they had incurred any expense which will be lost to them if the building cannot be erected to a height of more than 100 feet. True, it is alleged that they had actually commenced work on thе project and had arranged for its financing. Whether these facts constitute vested rights entitled to judicial protection is much more debatable than the situation presented in the other cases already disposed of, and the question must rest for the most part a matter of individual opinion.
Id., 181 Wis. at 534, 195 N.W. at 550.
In the Building Height Cases, the supreme court recognized fundamental principles that are of great significance in the determination of this case:
A construction of a statute which gives it a retrospective effect is not favored, and this is especially true where vested rights are affected....
“Every law that takes away or impairs rights that have vested under existing law is generally unjust and may be oppressive. Hence, such laws have always been looked on with disfavor.”
Id., 181 Wis. at 531, 195 N.W. at 549 (citation omitted). Additionally, although one might hope for a clear standard or an exact set of criteria, the Building Height Cases clarify that no single factоr is necessarily determinative of vested rights. As Lake Bluff has argued in this case, the words of a New York court are fitting:
“[T]here is no fixed formula which measures the content of all the circumstances whereby a party is said to possess ‘a vested right’ “. Rather, it is a term which sums up a determination that the facts of the case render it inequitable that the State impede the individual from taking certain action.
In re the Estate of Kadin, 163 A.D.2d 308, 309 (N.Y. App. Div. 1990).
In Rosenberg v. Village of Whitefish Bay, 199 Wis. 214, 225 N.W. 838 (1929), the supreme court considered an ordinance that, like the statute considered in the Building Height Cases, “‘is silent concerning buildings in process of erection at the time the law took effect.’ ” Id., 199 Wis. at 217, 225 N.W. at 839 (citation omitted). Unlike the Building Height Cases, however, Rosenberg is comparable to the instant action because neither razing of an existing building nor construction of a new building had begun. See id., 199 Wis. at 216-217, 225 N.W. at 839. Thus, the principles Rosenberg declares become all the more significant in this case where vested rights were claimed although construction had not begun:
“A construction of a statute [or ordinance] which gives it a retrospective effect is not favored, and this is especially true where vested rights are affected.”
... [E]xpense had been incurred in the preparation of plans.... [T]he plans prepared and all expenses incurred by the plaintiffs will be rendered of no value if the ordinance prevents them from proceeding with the building of hotel and apartment buildings.
... [T]his ordinance should not be so construed as to prevent the erection of the proposed buildings where substantial rights had vested prior to the enactment of the ordinance which would be unrea-
sonably injured by such a construction because such a purpose is not made clearly to appear by the language of the ordinance itself.
Id. (quoting Building Height Cases; bracketed portion in Rosenberg).
Rosenberg has additional significance for the instant case because the court, in Rosenberg, granted declaratory relief to the plaintiffs giving them a right to proceed with the construction of а hotel and an apartment building according to plans prepared before the passage of a rezoning ordinance “providing always that such buildings comply with the restrictions contained in the deed of the property in question ....” Id., 199 Wis. at 219, 225 N.W. at 840 (emphasis added). Therefore, the existence of vested rights did not, absolutely or completely, turn on whether the plans complied with all restrictions or satisfied all prerequisites to construction. This premise became all the more clear in State ex rel. Humble Oil & Refining Co. v. Wahner, 25 Wis. 2d 1, 130 N.W.2d 304 (1964).
In Humble, the property owner seeking to build a gas station petitioned for a writ of certiorari to reverse the decision of the town board of appeals denying permission to build, and for an alternative writ of mandamus to compel the building inspector to issue a building permit. Id., 25 Wis. 2d at 6, 130 N.W.2d at 307. As part of its defense, the town raised the issue of Humble‘s alleged failure to comply with all building permit application requirements. The supreme court rejected the town‘s argument, stating:
For the first time the town argues on this appeal that Humble did not comply with all the formal filing requirements or the zoning ordinance and that, therefore, Humble is not entitled to mandamus under any circumstances. It is apparent that
Three times the board acted on a Humble petition for a permit. Any failure on the part of Humble to follow formalities was waived by the board‘s three denials of the Humble applications, each time made without comment or stated reasons.
Id., 25 Wis. 2d at 16, 130 N.W.2d at 312 (footnote omitted). Although Lake Bluff incorrectly argues that this case is “no different” from Humble, the differences are less significаnt than the similarity: in neither case is the alleged failure to comply with zoning requirements necessarily fatal to the property owner‘s theory.
Thus, from Building Heights Cases, Rosenberg, and Humble Oil, the following principles emerge: (1) a property owner can have vested rights in a planned building before actual construction begins; (2) “retrospective effect” of an ordinance is “not favored, and this is especially true where vested rights are affected“; and (3) conceptually, vested rights can be separated from zoning compliance. That is, a court can conclude that a property owner has a vested right to build, contingent on compliance with previously existing restrictions.6
Thus, this court‘s affirmance of the trial court requires the City to treat Lake Bluff‘s application under C-2 zoning. This affirmance does not, however, strip the City of authority to monitor construction in order to enforce C-2 compliance. Accordingly, we need nоt consider the parties’ additional arguments on equitable estoppel regarding the existence, extent, or severity of any deficiencies in Lake Bluff‘s plans prior to the changes that corrected them.
“Clearly this was an eleventh-hour attempt to prevent this relator from using her property for its highest use and for which it had been zoned for seven years, during which time its assessed value had been substantially increased because it was so zoned. Such action was ill-advised, capricious and unreasonable. It was doubtless precipitated because of public excitement and clamor.”
Id., 257 Wis. at 384, 43 N.W.2d at 353 (quoting Vine v. Zabriskie, 3 A.2d 886, 887 (N.J. 1939)). Similarly, in Humble, despite the absence of vested rights, the supreme court‘s determination was explicitly connected to equitable considerations:
Equitable considerations bar the town from giving Humble such a fast shuffle at this late stage in the game.... [I]t is apparent that the town officials were trying to keep one jump ahead of Humble and were attempting to change the rules after they had been haled into court for what Humble believed was arbitrary, unreasonable, and capricious action.
The situations in Schroedel and in the instant case are similar in that in both cases there was a last-minute effort by the city to zone out a use. Id., 25 Wis. 2d at 14, 130 N.W.2d at 311.10
By the Court.—Judgment affirmed.
FINE, J. (dissenting). It is not disputed that when Lake Bluff filed its application for a building permit on August 5, 1993, Lake Bluff‘s plans did not comply with the then-existing C-2 zoning code. Lake Bluff did not, therefore, have а clear legal right to a building permit based on that application. Accordingly, any mandamus action brought by Lake Bluff to compel South Milwaukee to issue such a permit would have failed. See Keane v. St. Francis Hosp., 186 Wis. 2d 637, 646, 522 N.W.2d 517, 520 (Ct. App. 1994) (party seeking mandamus “must” show a “‘clear legal right‘” to the requested relief) (emphasis in original, citation omitted).1 Indeed, had South Milwaukee issued the requested building permit, that permit could not have authorized Lake Bluff to develop its property in conformity with the application filed August 5. See Jelinski v. Eggers, 34 Wis. 2d 85, 93, 148 N.W.2d 750, 755 (1967) (“a building permit grants no vested rights to unlawful use“) (upholding trial court‘s order that property owner remove garage constructed in violation of code but pursuant to building permit).
It is the law in Wisconsin that a landowner does not get “vested rights” in a zoning classification by merely spending substantial sums in reliance on that classification. State ex rel. Humble Oil & Ref. Co. v. Wahner, 25 Wis. 2d 1, 13, 130 N.W.2d 304, 310 (1964) (Humble Oil did not acquire vested rights in a zoning classification by obtaining an option on the land, exercising that option, and by going “to considerable expense in developing plans for the development of the site.“). Rather, at the very least, a building-permit application that conforms to the zoning requirements must be filed before the land is re-zoned. Id., 25 Wis. 2d at 13-14, 130 N.W.2d at 310-311 (zoning ordinance could not be changed to adversely affect Humble Oil “more than a year after Humble‘s first petition for a permit and one month after Humble had started these court proceedings based on the ordinance in effect” at the time). See also Jelinski, 34 Wis. 2d at 93, 148 N.W.2d at 755 (building permit issued in violation of building code does not authorize construction contrary to code even if ” ‘the holder of the illegal permit has incurred expenditures in reliance thereon’ “) (citation omitted). None of the cases upon which the majority relies holds that vested rights can attach before the filing of a building permit application that conforms to the existing zoning code; indeed, those cases teach just the opposite.2
Although I admire Cardozo, as we are all taught in law school to do, his result-first, reasoning-later approach is a dangerous jurisprudential methodology to adopt. Further, “Cardozo defended the right of a judge to deliberately misstate facts: ‘I often say that one [a judge writing a judicial opinion] must permit oneself, and that quite advisedly and deliberately, a certain margin of misstatement’ (Selected Writings 339, 341).” R.A. POSNER, CARDOZO 43 (1990). (Bracketing and parenthesis in original.) Deliberate misstatements of the record is but one way the result-oriented judge forces the square peg of the desired decision into the round hole of the law; taking a rasp to the hole is another. The majority has not misstated the record; it has, however, ignored clear precedent.
Notes
The other letter read:Please be advised that we are in receipt of your application for a building permit for the above referenced apartment complex. This letter is to advise you that everything is complete for the application of the footings and foundation building permit, and except for the fact that there is a moratorium on which will not allow me to issue a building permit for this property, I would be in a position to issue said permit.
State ex rel. Schroedel v. Pagels, 257 Wis. 376, 378-380, 382, 43 N.W.2d 349, 350-352 (1950) (mandamus) (building permit that complied with the then-existing zoning code was applied for prior to rezoning); Rosenberg v. Village of Whitefish Bay, 199 Wis. 214, 216-217, 225 N.W. 838, 839 (1929) (declaratory judgment) (building permit sought prior tо enactment of new ordinance); Building Height Cases, 181 Wis. 519, 531, 532-533, 533, 195 N.W. 544, 549, 549, 550 (1923) (telephone company had “acquired a building permit ... and had actually entered upon the further construction of the building, all prior to the passage of the law” limiting the height of certain buildings; law applicable to the Hotel Wisconsin‘s attempt to add a ninth story to its building where owner “made no application for a building permit until after passage and publication of said act“; prior to the passage of the act, the Piper Brothers had been granted a permit to build their hotel in Madison).Please be advised that we are in receipt of your application for a building permit for the above referenced apartment complex. This letter is to advise you that there is a moratorium on which will not allow me to issue a building permit for this property, but even if there was not a moratorium, I could not issue you a building permit because you are missing the following items:
1.
2.
3. etc.
- set-back requirements of the zoning codex
- parking requirements of the Americans with Disabilities Act
- proper connection to existing sewer, water and street systems for the proper collection and conveyance of storm water runoff including:
- a continuous easement for storm sewer
- no easement had been dedicated
- a portion of the planned storm sewer was improperly sized
- fail to provide for a required manhole
- failed to provide sufficient inlets and inlet leads
- insufficient detail was provided to determine if the plans required driveway approaches which conform to City standards
