650 F.2d 270 | Ct. Cl. | 1981
delivered the opinion of the court:
This case comes before the court on the parties’ motions for rehearing and to amend judgment under Ct. Cl. Rule 151.
The facts in this case are fully set forth in our earlier opinion. Laka Tool and Stamping Co. v. United States, 226 Ct. Cl. 83, 639 F.2d 738 (1980). The case involved a contract to manufacture and deliver certain rifle magazines. The original specifications proved impossible of performance and were modified. Subsequently, plaintiff was unable to comply with even the modified specifications although they were found not to be impossible. Eventually plaintiff was terminated for default. It should be emphasized that plaintiffs eventual failure to perform was unrelated to the earlier impossible specifications. The court upheld the default as proper. However, the court held plaintiff entitled to recover those excess costs, if any, which plaintiff expended in attempting to comply with the original impossible specifications before modification. Since plaintiffs unexcused default was a breach, the court also allowed the Government’s counterclaim for the amount of all progress payments it had made to plaintiff during the course of the contract, subject, of course, to any offsetting recovery by plaintiff. Plaintiffs claim was remanded to the Armed Services Board of Contract Appeals to allow plaintiff to make a showing that it had indeed made expenditures in attempting to comply with the impossible specifications and the amount of such unreimbursed expenditures. Although that showing remains yet to be made, we assume for the purposes of this opinion that there were such expenditures in some amount.
Defendant now contends that plaintiff should not be entitled to recover anything since it was properly defaulted and never delivered any acceptable goods under the contract, citing Century Hone Div. of Desert Labs., ASBCA No. 18360, 78-1 BCA ¶ 12,990 (opinion by Trial Division recommending affirmance, filed Sept. 5, 1980, in Ct. Cl. No. 44-79) and A. C. Hoyle Co., ASBCA No. 15363, 71-2 BCA ¶ 9137. This is an entirely new contention. It was not made to the court when the case was previously before us, nor were these cases cited and our opinion therefore has no discus
We have here a case where both parties defaulted on their contractural obligations. Defendant was the first to default by supplying impossible specifications. Plaintiff defaulted later by failing to deliver conforming goods under the modified specifications although such failure was unrelated to defendant’s default. Defendant’s default injured plaintiff by causing it an out-of-pocket loss in the form of expenditures for efforts wasted because of the impossible specifications.
We decline to follow Century Hone, supra. The case does not bind us as there has been no decision therein by a panel of this court. In that case the contractor was terminated for default for failing to produce a machine that conformed to the Government’s specifications. The contractor was held to be entitled to no relief for 37 unspecified constructive changes on the ground that the default termination was proper and the contractor had contributed nothing of value to the Government. If the case is read to hold that no claims survive a contractor’s failure to perform under any and all circumstances, we find it too broad and decline to follow it. We express no opinion on whether or not the case reaches the correct result since in our view that would depend on facts not specified in the opinion.
Although we hold that a contractor’s failure to perform is not a complete defense to an earlier arising claim against the Government in all cases, it is difficult to fashion a rule of universal application at this point, the issue being one of first impression. Accordingly, we are left to delineate the factors which we feel make plaintiffs recovery just and equitable in the instant case. We do so without holding that all these factprs are necessary or that any one is determinative. We keep that open to be resolved by later cases. The first factor we note is that plaintiffs default was not willful and deliberate. Rather it came only after bona fide attempts to complete the contract which plaintiff was simply unable to do. Second, plaintiffs initial efforts were wasted solely by and as a direct consequence of defendant’s default on its contractual obligation to supply specifications possible of performance.
This last factor distinguishes the case where a contractor terminated for default would seek to recover for a mere change. The Government does have the right under the contract to issue change orders. If, instead of supplying impossible specifications, the Government had simply increased the amount of magazines required under the contract by change order and plaintiff had completed the contract, it would have been entitled to the contract price for the originally required work plus an equitable adjustment for the additional work. However, should plaintiff be properly terminated for default without making any acceptable deliveries in such a case, it would get nothing for the original work. Furthermore, our opinion today should not be read as allowing a recovery for work covered by a change order, even though the change order might have caused a plaintiff to do extra work just as the impossible specifications did here. A crucial distinction is that the Government does have the right to issue change orders. Furthermore, the work under such a change order is so comparable to the original work required under the contract that in fairness no distinction should be made between them and no recovery allowed for either the original or change order work.
It may next be seen that many constructive changes are so closely analogous to the change order in the above hypothetical that again there would be no cause for distinction and no recovery allowed the defaulting contractor. If the Government requested additional magazines by change order, it would have acted within its rights. If the Government requests extra magazines indirectly by a mistaken interpretation of the contract, we see no cause for distinction from the case of the change order.
The above analysis distinguishes the case of A. C. Hoyle, supra, which defendant also cites, from the case before us. There the contractor was required to manufacture and deliver two winches but failed to do so in a manner conforming to the specifications. In that case the contractor participated in the drafting of the specifications. That is not the case here. The winches were rejected and the board held
We believe our holding is consistent with the common law of contracts. Williston and the Restatement of Contracts have broad language which suggests a contrary view. That language is to the effect that an accrued right of action against a promisor for breach of contract is extinguished by a plaintiffs subsequent inability to perform. Restatement of Contracts § 277; 6 S. Williston, Contracts § 884 (1962). However, the position in those texts is based on cases where the accrued right of action is for the plaintiffs expectancy where plaintiff has suffered no out-of-pocket loss. Their analyses are not specifically
In summary, we are satisfied that our original judgment was correct. The parties’ motions for rehearing and amendment of judgment have been considered without oral argument and are denied.
Ct. Cl. Rule 151 is similar to Fed. R. Civ. P. 59.
We reiterate that this loss is assumed only for purposes of this opinion.
By "default” in this context we mean a failure to comply with a contractural duty, whether such failure would be normally redressable as a constructive change or as a breach of contract.
See note 1.
Cases where the Government does get some benefit from the contractor’s work are distinguishable from the instant case and have permitted recovery despite the contractor’s default, as defendant concedes. Systems & Industry Optical, ASBCA No. 21635, 79-2 BCA ¶ 13,966; Harent, Inc., ASBCA No. 16206, 73-2 BCA ¶ 10,074.