Labrador Oil Company appeals from a judgment based in part upon a jury verdict in favor of Norton Drilling Company awarding recovery for balance owing for daywork charges under a standard IADC written contract 1 for the drilling of a well, and recovery for damage to or loss of Norton’s drill pipe. By five issues, Labrador contends the trial court erred (1) in disregarding the jury’s answer to Question 6 concerning Labrador’s mitigation of damages, (2) when it refused to reduce Norton’s judgment by the salvage value of the damaged drill pipe retained by Norton, (3) when it failed to establish the salvage value offset to which Labrador was entitled at $166,650.00, (4) by applying the wrong measure of prejudgment and post-judgment interest and granted an incorrect judgment for interest in favor of Norton, and (5) by refusing to grant Labrador leave to file a trial amendment. Norton also presents one cross-issue contending the trial court erred in rendering a judgment based on the jury’s answer to Question 7, which inquired as to the amount of reimbursement owed for the damage or loss of in-hole equipment belonging to Norton, because the jury’s answer lacked the requisite evidentiary support. Based upon the rationale expressed herein, we will affirm.
Labrador (as operator) and Norton (as contractor) entered into a written con
14.2 Contractor’s In-Hole Equipment: Operator shall assume liability at all times for damage to or destruction of Contractor’s in-hole equipment, including, but not limited to, drill pipe, drill collars, and tool joints, and Operator shall reimburse Contractor for the value of any such loss or damage; the value to be determined by agreement between Contractor and Operator as current repair costs or 80 percent of current new replacement cost of such equipment delivered to the well site. 4
Norton’s rig inventory, which was attached to the IADC contract, showed among other things, 21,000 feet of drill pipe on hand. However, before Labrador signed the contract, Norton sent Labrador the following message:
Mike, I found 19 drill pipe inspections covering the period from February 1995 to present. I found 3227 jts inspected, 2786 jts premium for 86.33% good usable pipe and 13.67% unusable. If you agree we can use these figures to determine fair wear and tear. Any losses you will replace or pay for beyond 13.67%. Let me hear from you so we can get started moving the rig.
The contract also provided that Labrador would pay Norton $91,000.00 as a demobilization fee but by letter agreement dated May 10, 1996, the parties agreed that the fee would be $50,000.00 if only one well was drilled.
Inspections of Norton’s drill pipe components were made by Labrador and Labrador accepted the components as in compliance with industry standards before commencement of drilling operations on June 28, 1996. A few days after drilling commenced, drilling operations were suspended and “fishing” commenced because a shock sub furnished by Labrador parted. Drilling operations resumed but problems impaired operations from time to time. Labrador ceased using some of the components provided by Norton; however, Labrador continued using other components provided by Norton until the hole had reached a depth of near 13,000 feet. After Labrador determined that Norton’s drill pipe had worn below industry standards and was no longer suitable, it ceased using Norton’s damaged drill pipe. Labrador recognized its responsibility to repair or replace the drill pipe, but decided at that time to continue drilling operations with rented replacement pipe instead of repairing or replacing the damaged pipe on site. However, drilling ceased after several thousand feet of drill pipe, which included some components supplied by Norton, fell into the hole after a rental component failed, and the rig was released November 1, 1996. Following Labrador’s failure to pay Norton’s invoices and replacement of the lost or damaged portion of Norton’s drill pipe, Norton filed suit.
Following consideration of Norton’s motion to disregard jury findings to Questions 2, 4, 6, 7, and 8, the trial court granted the motion as to Question 8 ($26,-895.00 salvage value of Norton’s drill pipe), and partially granted the motion as to Question 6, disregarding the jury finding that $60,406.99 was the reasonable cost of renting replacement drill pipe, and denied the motion as to the remaining questions. Accordingly, while acknowledging that, per stipulation of the parties, Norton was entitled to recover a $50,000.00 demobilization fee and Labrador was entitled to a credit of $8,720.00, the trial court entered judgment that Norton recover against Labrador the sum of $463,522.97 together with prejudgment interest in the amount of $84,066.83, calculated at eighteen percent (18%) per annum on the sum of $343,-578.97 of the judgment from December 20, 1996, and at the rate of eighteen percent (18%) per annum on the sum of $119,-944.00 of the judgment from February 13, 1997.
Mitigation of Damages
By its first issue, Labrador contends that the trial court erred in disregarding the jury answer to the mitigation of damages portion of Question 6. We disagree. By Question 6, Labrador sought to set off the reasonable and necessary expenses which it “incurred in renting replacement drill string components.”
6
At the charge conference, Norton objected to the submission of the question because (i) there was no evidence to support any expenses incurred in renting replacement pipe, (ii) as a matter of law, Labrador was not entitled to credit or any repayment for replacement pipe, and (iii) as a matter of law, Labrador was not entitled to any credit for any alleged problems with the drill pipe. By its answer, the jury found that the reasonable and necessary expense for “renting replacement drill string components” was $60,406.99. Following consideration of Norton’s motion to disregard such jury finding, the trial court granted the motion. Labrador contends it was entitled to credit for the expense it incurred obtaining “drill string to replace Norton’s inadequate drill string.” Although Labrador contends that the drill pipe furnished by Norton did not meet industry stan
As above noted, subparagraph 14.2 of the written contract contemplated that Norton’s equipment might be damaged or destroyed while it was “in-hole.” By this paragraph, if any of Norton’s equipment was damaged or destroyed while it was “in-hole,” Labrador assumed the performance obligation of either repairing the damaged equipment or paying 80% of the current new replacement cost of the damaged or destroyed equipment. The contract did not give Labrador the alternative to rent pipe at Norton’s expense or to replace the damaged equipment or drill pipe with used pipe.
First, the doctrine of mitigation of damages is not applicable to Norton’s action against Labrador because of Labrador’s failure to perform its obligation either to repair the equipment or pay 80% of the current price of the equipment delivered to the well site. Norton, being the party entitled to performance by Labrador to either repair the equipment or pay 80% of current new replacement cost may have had the duty to mitigate its losses, but the burden of proof on the issue was on Labrador.
Walker v. Salt Flat Water Co.,
Moreover, the written contract contemplated that Norton’s equipment might be damaged or destroyed while it was “in-hole.” By the provision, the parties agreed that Labrador assumed liability for damage or destruction and that Labrador would either repair the equipment or pay 80% of the current new replacement cost of such damaged or destroyed equipment, but this provision did not authorize Labrador to continue drilling operations with rented pipe at Norton’s expense. A jury finding is immaterial only if the question should not have been submitted or if the question, though properly submitted, was rendered immaterial by other findings.
Salinas v. Rafati,
Labrador also contends that Norton’s poor drilling practices brought about excessive fatigue or damage to the drill pipe; however, we note that per the contract, drilling operations were under the “direction, supervision and control” of Labrador. Moreover, under the specific provisions of subparagraph 4.4 of the contract, where Labrador furnished the drill pipe, the day rate payable to Norton could have been reduced from $6,216.00 to $6,000.00, but Labrador did not elect to claim that adjustment. 7 Accordingly, Labrador’s first issue is overruled.
Salvage Value
Because issues two and three concern salvage value, we will consider them
By Question 8 the jury was asked to determine “[wjhat sum of money, if any, if paid now in cash, is the salvage value of the drill string for which Norton Drilling Company is suing Labrador Oil Company”? At the charge conference, Norton objected to the submission of Question 8 on the ground that there “is no basis under which salvage value of the drill pipe is relevant to any issue in this case. We submit that is an irrelevant issue and, therefore, constitutes a comment on the weight of the evidence.” Norton also moved to disregard the jury finding that the salvage value was $26,895.00, and the trial court rendered judgment denying Labrador any credit for the salvage value.
Citing over fifteen cases, Labrador contends that when damages to personal property are sought, they consist of the pre-loss fair market value less the post-loss fair market value and therefore, it was entitled to a credit in the amount of the salvage value of the pipe retained by Norton. However, the cases cited by Labrador are either negligence, insurance, tort, products liability, or DTPA cases, and none arise from a contract as applicable here. As discussed earlier, subparagraph 14.2 fixed liability upon Labrador for damage or destruction to Norton’s drill pipe while “in-hole.” By the contract, the parties agreed that Labrador would either pay “current repair costs” or pay 80% of the current new replacement cost, but the paragraph did not mention salvage value and did not contemplate that Labrador could fulfill its obligation by providing used replacement pipe. Here, the parties contracted for Labrador’s performance if any of Norton’s equipment or drill pipe was damaged or destroyed while “in-hole.” Because parties to a contract may stipulate the amount of recoverable damages, and may contract to have an agreed remedy to be applied in the case of breach, the general rule allowing credit for salvage value does not apply to the obligation of Labrador under subparagraph 14.2 of the contract.
Lacy v. Ticor Title Ins. Co.,
To complete our analysis of Labrador’s second and third issues regarding salvage value, we need to consider the jury’s answers to Questions 7 and 8. Also, because Norton’s cross-issue, by which it contends the trial court should have disregarded the jury’s answer to Question 7 relates to this discussion, we will review Norton’s cross-issue together with Labrador’s second and third issues. Question 7 and its answer reads as follows:
What sum of money, if any, if paid now in cash, would compensate Norton Drilling Company for the failure to comply by Labrador Oil Company with the parties’ agreement concerning replacement pipe?
The value of the replacement pipe is to be determined at the time and place of performance.
Answer in dollars and cents for damages, if any:
Answer: $127,400.00. 8
The record shows the following announcements occurred during the charge conference, regarding Question 7:
MR. SPENCE: And then the only other thing I would like to say is in — I think it is Question Number 7 — that is the one that we, amongst Counsel, we agreed to just ask about the replacement pipe agreement in a global damage question, so that the jury will ultimately decide really what that agreement consisted of, but both parties agree to stipulate that there was an agreement regarding replacement pipe, but there is a hot dispute as to what it entails.
So neither party is waiving their understanding of what that agreement was, but we are agreeing to submit all of that to the jury. Is that your understanding, Mr. Pouts?
MR. FOUTS: Yeah. My understanding is: We are not submitting any questions to the jury about what the agreement was. Both sides have a different view about what it is.
THE COURT: We are just going to submit the — My understanding is: Everybody is agreeing that there was an agreement, and it was not complied with, and we are submitting it as damage, and we will let the jury decide what the agreement was, without having to go through multiple questions. I think, by setting the damage, they are going to determine what the agreement was.
MR. FOUTS: All right.
THE COURT: We will see. I don’t know any other way to do it.
During the charge conference, Norton also objected to Question 8 as being irrelevant, contending there was no basis under which salvage value of the drill pipe would be relevant to any issue in the case. Regarding Question 7, Norton also took the position that the written contract was controlling, but if the court was going to submit a question about any deviation, it would not object to the form of Question 7. Except for the trial court’s refusal to submit requested questions regarding fraud and breach of warranty, which are not presented on appeal, Labrador did not otherwise object to the charge as submitted.
As in the trial court, Norton contends that the evidence of new replacement cost conclusively shows that Norton should recover $420,512.18, in accordance with sub-paragraph 14.2 of the contract; however, before Labrador signed the contract, Norton advised Labrador that according to its review of drill pipe inspections, ordinary wear and tear on the drill pipe was 18.67% and requested that Labrador advise if that factor should be considered. Contrary to Norton’s assertion, there is some evidence in the record that Norton agreed to accept used pipe provided by Labrador as fulfillment of Labrador’s obligation under sub-paragraph 14.2, and also included in the record is evidence of referrals as late as January 1, 1997, from Norton to Labrador advising where used pipe could be purchased at $12.00 per foot. Some evidence also showed that Norton purchased used pipe at prices ranging from $2.40 per foot to $7.00 per foot, which was substantially below the prices of $29.00 to $34.00 per foot for new pipe reflected on Norton’s invoices. The announcements of counsel for both parties at the charge conference acknowledged that the parties did have an agreement regarding replacement pipe, but the parties did not agree as to the terms of the agreement.
Counsel and the court were aware that Question 7 was a global question, which had the effect of invoking the rules announced in
Allen v. American National Insurance Company,
We have not overlooked Labrador’s third issue, by which it contends that salvage value was established as a matter of law at $166,650.00 based upon Norton’s answers to interrogatories. Because of our analysis that salvage value was not recoverable under the terms of the written agreement, or was subsumed into Question 7, a separate analysis is not necessary. Accordingly, Labrador’s second and third issues are overruled, and Norton’s cross-issue is overruled.
By issue four, Labrador contends the trial court applied the wrong measure of prejudgment and postjudgment interest and granted an incorrect judgment for interest in favor of Norton. We disagree. Paragraph 5 of the agreement entitled “TIME OF PAYMENT” contains three subparagraphs. Because the third provision covers attorney’s fees, it is not material to our discussion; however, subpara-graph 5.1 provides in part as follows:
5.1 Payment for mobilization, drilling and other work performed at applicable day rates, and all other applicable charges shall be due, upon presentation of invoice therefor, upon completion of mobilization, completion of the well, or at the end of the month in which such work was performed or other charges are incurred, whichever shall first occur.... 9
Subparagraph 5.2 provided that the “Operator shall pay all invoices within 20 10 days after receipt,” and if not timely paid, interest accrued at the rate of 1.5 percent per month from due date until paid. Norton invoiced Labrador for day-work and other work on November 30, 1996. Then on January 23, 1997, Norton sent four replacement invoices for the damaged drill pipe which replaced its prior invoices dated September 10, 1996, October 24, 1996, November 11, 1996, and January 3,1997.
By its argument, Labrador first contends the agreement allowing replacement of drill pipe was a separate oral contract which did not provide for interest. We disagree. Question 7 was directed to the replacement of damaged equipment while it was “in-hole,” as covered by subpara-graph 14.2 of the contract, and was not directed to subparagraph 5.2. Accordingly, although subparagraph 14.2 may have been modified, the parties effected a continuation of the remainder of the contract, except as changed.
Greenbelt Elec. Coop., Inc. v. Johnson,
By its fifth issue, Labrador contends the trial court erred by refusing to grant it leave to file a trial amendment. We disagree. Labrador asserts that during trial, Norton complained that Labrador’s pleadings were insufficient to raise defenses that (i) the rig inventory was part of the IADC contract, (ii) the written contract was orally amended; however Labrador’s brief does not make reference to where the objections and any ruling thereon can be found in the record. In connee
Accordingly, the judgment of the trial court is affirmed.
Notes
. International Association of Drilling Contractors Drilling Bid Proposal and Daywork Drilling Contract — U.S.
. Norton signed the contract on April 19, 1996. Labrador signed the contract on May 7, 1996.
.
Haas v. Gulf Coast Natural Gas Company,
.The figure 80 was inserted into the form contract.
. Tex. Bus. & Com.Code Ann. §§ 17.01-17.854 (Vernon 1987 and Pamph. Supp. 1999).
. In the oil and gas industry, "drill pipe” and "drill string” are used interchangeably.
. Norton’s letter of 4/30/90, transmitting two copies of the contract, indicated that "[w]ith regard to the daywork price, as you can see from the contract, if I furnish the pipe the price is $6,216.00 per day. After 100 days I will drop the daywork to $6,000.00 per day with or without drill pipe.”
. Emphasis added.
. Emphasis added.
. The figure 20 was inserted into the form contract.
