This is a suit by a material supplier against the principal contractor and his surety for the value of material furnished to the contractor in the building of a church school. The case was submitted to the court without a jury on a stipulation of facts. The court rendered judgment against the contractor for $3,046.74, with interest, but in favor of the surety. Plaintiff appealed; the contractor did not. Hence, our problem lies in the issue between plaintiff and the surety. On appeal to the St. Louis Court of Appeals, that court reduced the recovery of plaintiff against the contractor to $2,805, with interest, and affirmed the judgment in favor of the surety. On application for transfer, we determined to review the case because of the holding of nonliability as to the surety.
On July 22, 1960, defendant Largen contracted with Union Lutheran School Association to build the “Green Park Lutheran School”; we shall refer to the latter as the “owner” or#the “school.” That contract is not in evidence, an oversight which should not have occurred. In anticipation of that contract, Largen contracted with plaintiff for the furnishing of structural steel and miscellaneous iron to be used in the construction for a price of $2,805; plaintiff fully performed that contract and furnished the material. It is further stipulated that, during the construction, plaintiff and Lar-gen agreed that plaintiff should supply additional material of the reasonable value of $139.74; the stipulation does not state that this material was actually furnished, an apparent inadvertence. On July 28, 1960, Largen as principal and defendant Universal Surety Company, a Nebraska corporation, as surety, executed a “contract bond” to the Green Park Lutheran School as obli-gee, in the sum of $271,977 to secure the performance of the principal contract, which was made a part of the bond by reference. Since that bond is the source of the only real issue, we quote its controversial paragraph, as follows:
“Now, Therefore, the condition of this obligation is such that, if the Principal shall faithfully perform the contract on his part, and shall fully indemnify and save harmless the Obligee from all cost and damage which the Obligee may suffer by reason of failure so to do and shall fully reimburse and repay the Obligee all outlay and expense which the Obligee may incur in making good any such default, and shall pay all persons who have contracts directly with the Principal for labor or materials, then this obligation shall be null and void, otherwise it shall remain in full force and effect.” Plaintiff demanded payment of Largen who refused or failed to pay, and subsequently the surety also refused to pay; hence this suit.
We relate the contentions of the parties in reverse order, giving first the contentions of defendant surety in support of its supposed nonliability. It says in substance: that this bond was given solely for the benefit of the obligee, the school, and that it gave plaintiff no right of action; that plaintiff was neither a creditor beneficiary nor a donee beneficiary and that it did not maintain the burden of showing that the parties intended to benefit it. Plaintiff asserts that it is one of the persons for whose benefit the bond was executed and that it has a direct right of action; and it questions the distinction frequently made between the liability of sureties on bonds for private and public works.
*89
The trial court expressly based its judgment in favor of the surety on the decision in Uhrich v. Globe Surety Co.,
We first discuss the Uhrich case. It is a decision of the Kansas City Court of Appeals, rendered in 1914. There the plaintiff sold and furnished materials to a contractor who, with the surety, executed a performance bond. The case was decided upon the sustaining of a demurrer to the petition and a refusal to plead further. The contractor had agreed to erect the building and to pay for all labor and materials; the owner contracted to pay the agreed sum provided that all persons dealing with the contractor should be paid so that they would have no liens, with further provisions for the retention of funds and direct payments if so desired. The bond, in so far as its terms appear, was conditioned “ ‘that, if the said contractor shall duly perform said contract and fulfill all the several stipulations therein provided, then this obligation is to be void, but, if otherwise, the same shall remain in full force and virtue. It is hereby expressly agreed that the said L. G. Hill may make payments in any amounts to the contractor, subcontractor, and materialmen and laborers, and such payments shall in no wise limit, affect, or reduce our liability hereunder.’ ” The bond does not appear to have contained any condition concerning the payment of claims for material and labor. The plaintiff there had filed a lien and had a suit pending to enforce it. The court recognized, with limitations, that a third person for whose benefit a contract was made could enforce it, although not privy to the consideration; but it emphasized the element of mutual intent of the parties “as expressed in the instrument” and “in the light of the circumstances * * * where there is uncertainty or ambiguity * * *.” The court concluded that the payment of debts such as plaintiff’s was not intended by the parties as one of the “direct objects” of the bond, but was only incidental to the idea of “protecting the property of the owner from liens * * And the court noted the distinction between cases such as that and those cases involving public bonds where no lien may be obtained. The court emphasized the dominant thought of liens, and the omission from the bond of any provision giving materialmen a right of action. We shall return to this case later.
There has been a vast amount of litigation on this subject, and it will be physically impossible to discuss even a substantial proportion of the cases. An exhaustive annotation appears in
77
A.L.R., beginning at page 21. This is supplemented by another annotation at
Counsel for the surety seem to concede that the numerical weight of authority is contrary to its contentions here; so did the Court of Appeals as to the “weight of the precedents”; we are not attempting to keep a “running score,” as that court said was an improper test, but it is material in any organized legal philosophy that we note a substantial weight of authority on a controversial issue. Defendant insists that Uhrich, supra, represents the established Missouri law, and also the correct interpretation of this present bond. We have discussed the facts and the holding in that case. Admittedly, there are cases supporting the tenor of defendant’s arguments and contentions. Maryland Casualty Company v. Johnson (D.C.Mich.),
In a supplemental brief counsel rely very largely upon certain statements in the Restatement of Contracts, Ch. 6, § 133(a) and (b) to the general effect that a third person, in order to receive the benefit of a contract between others, should be a donee beneficiary or a creditor beneficiary; they insist that this plaintiff is neither. These sections, and the comments and illustrations thereunder, deal with legal theories supposedly applicable to contracts in general and in the abstract; we are influenced to a greater extent here by the reasoning of the specific, decided cases on facts like our own. We note, however, that the restatement does not really seem to exclude re *92 covery in a situation such as we have; it states that a third person may be a donee beneficiary when it appears from the terms of the promise and the circumstances that the purpose of the promise is to confer upon such third person a right against the promisor to some performance not due from the promisee. We construe the terms of the present bond as evidencing an intent to confer a right of action upon material-men against the surety; unless the bond is so construed the provision for payment to such persons is meaningless.
Sundry Missouri cases are cited pro and con which we do not find of sufficient applicability to merit discussion. Fellows v. Kreutz,
Counsel argue that the provision in question was necessary in order to prevent the filing of mechanics’ liens and thus to protect the owner-obligee; in support of this argument, they seem to say that the contractor may have only been required by the terms of his contract to furnish all labor and materials' and not to pay for them. The contract is not in evidence and we may assume no such provision; moreover, despite language in one or two old cases attempting to make some distinction between the phrases “to furnish” and to “pay for” (for which there may be some justification under other facts), we would regard it as rather ridiculous to hold that one who had contracted to furnish all labor and material for the construction of a building had not agreed to furnish it fully paid, at least in so far as liens are concerned. To hold otherwise would exalt technicalities over practicalities. Also, the other conditions of the bond here (as originally quoted) for full indemnity and reimbursement of the owner for all cost, damage, outlay and expense, constituted full protection to it as to mechanics’ liens. If the condition in this bond for payment did not mean that ma-terialmen and laborers should be paid, then it had no meaning. The condition was most specific in designating the class of suppliers who should be paid, namely, those who had contracts directly with the principal. We hold that it did impose upon the surety the duty to pay them, and upon unpaid materialmen the right to sue on the bond. In so far, as an intent of the parties may be necessary, such intent was shown by this wording of the bond itself, there being nothing in the bond to create an ambiguity, and nothing in the facts or circumstances to the contrary.
Reverting to the case of Uhrich v. Globe Surety Co.,
As previously noted, the stipulation of facts did not state that plaintiff had furnished the extras agreed upon, although it did state their reasonable value. We cannot supply such an omission. The stipulation states that the original contract price was $2,805; the letter-exhibit constituting the contract states the figure as $2,850, creating an inconsistency. We adopt the *93 figure stated in the stipulation, especially since that figure is also the amount stated in plaintiff’s petition. It is further stated in the stipulation that demands were made on both defendants for the sum of $3,046.-74, an amount in excess of the contract price, even with the extras added. However, if demands were necessary here, neither defendant pleaded any lack of proper demand, § 509.410, RSMo 1959, V.A.M.S., and the surety admitted that plaintiff “made demand” upon it, and that it refused to pay the sum demanded or any part thereof. The judgment against defendant Largen should be reduced to the sum of $2,805 with interest at 6% from September 19, 1961; judgment should be entered in favor of plaintiff and against Universal Surety Company, for $2,805 with interest at 6% from June 29, 1962. The judgment as to Largen, as thus modified, is affirmed. The judgment in favor of defendant Universal Surety Company is reversed, with directions to the trial court to enter judgment against it as herein indicated. It is so ordered.
