L & W Supply Corp. v. A.D.F. Drywall, Inc.L & W Supply Corp. v. A.D.F. Drywall, Inc.
Plaintiff furnished building materials that were used by defendant A.D.F. Drywall, Inc. (hereinafter ADF), a subcontractor hired by the general contractor, defendant Zandri Construction Corporation, for its work on a public works construction project. Defendant Federal Insurance Company, acting as surety for Zandri, issued a labor and material payment bond on the project. ADF left the job in July 2004 without completing its subcontract and failed to pay plaintiff for some of the materials plaintiff had supplied. In October 2004, plaintiff filed a mechanic‘s lien for the cost of those materials. After the lien was discharged by a bond filed by Federal, again as surety for Zandri, plaintiff commenced this action to recover the amount owed, and the parties moved and cross-moved for summary judgment. To the extent relevant on this appeal, Supreme Court found questions of fact and denied plaintiff‘s motion for summary judgment on the second cause of action to recover against
As the proponent of the motion for summary judgment on its second cause of action based upon the mechanic‘s lien, plaintiff had the burden of presenting evidentiary facts showing the existence of a valid lien and that there were funds due and owing from Zandri to ADF to which the lien could attach (see
As plaintiff points out, the record contains an affidavit of Jeffrey Lino, the vice-president of Zandri, indicating that ADF was owed $41,335.16 when the lien was filed. However, in its opposition to plaintiff‘s motion, Federal cited other evidence that Lino had merely stated the amount remaining to be earned by ADF on the subcontract. Federal also alleged that when ADF walked off the job, there was $16,703.16 of its work still incomplete, the project architect had asked for $39,750 in offsets and the project owner held retainage attributable to ADF‘s work in the amount of $24,632. Inasmuch as these offsets were alleged to have been asserted before plaintiff filed its lien, we agree with Supreme Court that there is a question of fact as to the amount, if any, due at the time the lien was filed.
We also agree that Supreme Court properly denied plaintiff‘s motion for summary judgment as to the fourth and fifth causes of action, which are based upon a personal guarantee executed by Lavigne in 1995. In response to plaintiff‘s claim that the guarantee applied to all of its sales to ADF, Lavigne averred that it did not cover materials provided on Zandri‘s project because two of plaintiff‘s employees had agreed to and did set up a separate billing account for those materials covered by Zandri‘s payment bond, rather than the guarantee. Although plaintiff then argued that oral modification of the guarantee was precluded by the statute of frauds (see
As for the ninth cause of action, we agree with plaintiff that its final invoice to ADF, which lists Zandri‘s project and is dated July 1, 2004, made a prima facie showing that materials were last supplied to ADF for Zandri‘s project less than 120 days before it gave written notice of its claim against the payment bond, as required to satisfy
Cardona, P.J., Peters, Kavanagh and Stein, JJ., concur.
Ordered that the order is modified, on the law, without costs, by reversing so much thereof as denied plaintiff‘s motion for summary judgment as to the ninth cause of action; motion stayed as to said cause of action pending the expeditious completion of discovery by defendant Federal Insurance Company; and, as so modified, affirmed.