Lead Opinion
L.S. Starrett Company (“Starrett”) appeals from two orders by the Federal Energy Regulatory Commission (“FERC” or “Commission”). The Commission concluded that Starrett would be required to seek licensing pursuant to Section 23(b) of the Federal Power Act (“FPA”)
I. Background
The Project is located on the non-navigable Millers River in Athol, Massachusetts, on property that belongs to Starrett. It consists of (1) an 87-acre-foot reservoir; (2) a 20-foo1>-high, 127-fooh-long concrete gravity dam; (3) two powerhouses, one at each end of the dam; and (4) various appurtenant facilities. The turbine generator in the powerhouse on the right side of the dam (“the right-side generator”) currently has an installed capacity
After the left-side generator failed, Starrett began to investigate its options for replacement or repair. In early 2007, Starrett retained GZA GeoEnvironmental, Inc. (“GZA”), which prepared a feasibility study that examined the financial costs and benefits of repairing the left-side generator. The study concluded that it would be cost effective to use hydropower generated by a new left-side turbine generator (“the new left-side generator”). The new left-side generator’s installed and actual capacity would be 198 kW. Installing the new left-side generator would increase the Project’s combined installed capacity approximately 24%, to 448 kW, and its total actual capacity approximately 45%, to 278 kW. The total actual capacity of the Project, however, would remain less than the previous total installed capacity (i.e., 362 kW,
In September 2008, believing that it did not require FERC licensing in order to proceed with its proposed changes,
In March 2009, as Starrett was working to replace its left-side generator, the U.S. Fish and Wildlife Service (“USF & WS”) wrote to the Commission to request that the Commission investigate the work oc
On May 4, 2009, the Commission notified Starrett that its proposed work would increase the capacity of the Project and would be considered post-1935 construction, thus triggering the Commission’s licensing jurisdiction. The Commission asked Starrett to submit various details about its dam and the proposed changes. Starrett provided the requested details but maintained that its proposed work would not lead to an increase in capacity above the 362 kW total memorialized in Starrett I because only the installed capacity, not the actual capacity, would be over 362 kW. After reviewing these materials, the Commission issued an order finding that licensing of thе Project was required. See L.S. Starrett Co.,
II. Discussion
We are now required to review the Commission’s determination that the Project fell within its jurisdiction under Section 23(b) of the FPA. Under that section, a hydroelectric project “without a valid pre1920 permit” is subject to the Commission’s licensing jurisdiction if it
(1) is located on a navigable water of the United States;
(2) occupies lands of the United States;
(3) utilizes surplus water or water power from a government dam or
(4) [a] is located on a stream over which Congress has Commerce Clause jurisdiction, [b] is constructed or modified on or after August 26, 1935, and [c] affects the interests of interstate or foreign commerce.
Starrett II,
A. Standard of Review
Reviewing the Commission’s orders under the Administrative Procedures Act, we “must reverse an agency action that is ‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.’ ” Knott v. FERC,
“We review FERC’s findings of fact for ‘substantial evidence,’ and if so supported, such findings are conclusive.” Knott,
“ ‘Pure’ legal errors require no deference to agency expertise, and are reviewed de novo.” Id. at 372 (quoting Ne. Utils. Serv. Co.,
B. A “Commerce Clause Stream”
Section 23(b) requires us to ask whether L.S. Starrett’s dam is on “a stream over which Congress has Commerce Clause jurisdiction,” see 16 U.S.C. § 817(1), i.e., a “Commerce Clause stream.” The Commission concluded, and L.S. Starrett does not dispute on appeal, that the Millers River is a “Commerce Clause stream.” See Starrett III,
C. Post-1935 “Construction”
In 1935, Congress amended the FPA “to require that persons ‘intending to construct a dam or other project works’ on nonnavigable streams obtain a license.” Thomas Hodgson,
The Commission argues that, because Congress has not spoken on the precise question at issue here — which it frames as “what constitutes ‘construction’ ”
1. Standard of Review
We must first determine whether Congress unambiguously expressed an intent about the precise question at issue here. If we conclude that Congress did unambiguously express such an intent, our analysis ends there. If we conclude that Congress did not unambiguously express an intent on the precise question here, we must analyze whether the Commission’s cоnclusion that the work here constituted jurisdictional construction was unreasonable.
“In determining congressional intent, we employ the traditional tools of statutory construction, including a consideration of the language, structure, purpose, and history of the statute.” In re Hill,
a. Language of the Statute
“We begin with the actual language of the statute, and ask whether ... [“construction”] has a ‘plain and unambiguous meaning with regard to the particular dispute in [this] case.’ ” Perez-Olivo v. Chavez,
Black’s Law Dictionary defines “construction” as “[t]he act of building by combining or arranging parts or elements.” Black’s Law Dictionary 355 (9th ed.2009). Another dictionary defines “construction” as “the act- of putting parts together to form a complete integrated object,” and the verb “construct” as “to form, make, or create by combining parts or elements.” Webster’s Third New International Dictionary (Philip Babcock Gove et al. eds., 1971). These definitions do not suggest
b. Statute as a Whole
If we conclude that the “plain language of the statute, standing alone, is ambiguous,” the next step is to “ask whether this ambiguity can be resolved by looking to the ‘specific context in which [the] language is used, and the broader context of the statute as a whole.’ ” Perez-Olivo,
2. Reasonableness
The Commission argues that its conclusion here — i.e., that Starrett’s proposed work would constitute jurisdictional construction- — was reasonable because the proposed changes involved (1) an increase in installed capacity and (2) an increase in head. Responding to the Commission’s argument about increased capacity, Starrett contends that the Project’s new actual capacity (278 kW, up from 192 kW) would remain below the 1992 installed capacity (362 kW), and thus the Commission should not have exercised its jurisdiction. We conclude that the Commission’s dеtermination was reasonable because there is no doubt that, under Starrett’s plan, there would be an increase in capacity no matter how the capacity was measured; both the actual and the installed capacities would be greater than their respective 1992 values.
Given the state of the law, we must conclude that the Commission’s interpretation of “construction” as including the work here was reasonable. In 1965, the Supreme Court explained that
[t]he central purpose of the Fedеral Water Power Act was to provide for the comprehensive control over those uses of the Nation’s water resources in which the Federal Government had a legitimate interest; these uses included navigation, irrigation, flood control, and, very prominently, hydroelectric power-uses which, while unregulated, might*27 well be contradictory rather than harmonious.
Union Elec. Co.,
Thе cases that Starrett cites to support its position are distinguishable because they did not involve increases in capacity. In Thomas Hodgson, the court relied in part upon the fact that there was no increase in capacity when concluding that no posF-1935 construction had occurred. See Thomas Hodgson,
In short, we conclude that the Commission’s determination that Starrett’s facility met the second required prong was not unreasonable.
D. The Effect on Interstate Commerce
Before allowing the FERC to exert its licensing jurisdiction over projects involving post-1935 construction, Section 23(b) requires the Commission to “find that the interests of interstate or foreign commerce would be affected by [the] proposed construction.” 16 U.S.C. § 817(1). The Commission argues that Starrett’s construction meets the interstate commerce requirement because its dam is a member of a class of small hydroelectric projects that collectively have a substantial impact on interstate commerce becausе they produce power that would otherwise have to be produced elsewhere on the interstate grid. Starrett responds that (1) it is improper for the Commission to rely on this “cumulative effect” theory because it leaves the Commission’s Commerce Clause jurisdiction without boundary; and (2) in any case, the Commission has not shown that Starrett’s facility belongs to a class of small hydroelectric projects that collectively affect interstate commerce.
1. The “Cumulative Effect” Theory
The Supreme Court has noted that the language of the FPA “strongly implies that Congress drew upon its full authority under the Commerce Clause” in enacting the statute. Union Elec. Co.,
2. Substantial Evidence
Starrett contends that its situation is comparable to the one in City of Centralia, where the Ninth Circuit concluded that the record failed to support the Commission’s conclusion that a hydroelectric project either (1) itself had a substantial effect on commerce,
III. Conclusion
For the reasons stated, we affirm.
Affirmed.
Notes
. Section 23(b), codified at 16 U.S.C. § 817(1), governs the licensing of dams and other project works on non-navigable waters and provides, in relevant part, as follows:
Any person, association, corporation, State, or municipality intending to construct a dam or other project works across, along, over, or in any stream or part thereof, other than those defined in this chapter as navigable waters, and over which Congress has jurisdiction under its authority to regulate commerce with foreign nations and among the several States shall before such construction file declaration of such intention with the Commission, whereupon the Commission shall cause immediate investigation of such proposed construction to be made, and if upon investigation it shall find that the interests of interstate or foreign commerce would be affected by such proposed construction, such person, association, corporation, State, or municipality shall not construct, maintain, or operate such dam or other project works until it shall have applied for and shall have received a license under the provisions of this chapter. If the Commission shall not so find, and if no public lands or reservations are affected,*21 permission is granted to construct such dam or other project works in such stream upon compliance with State laws.
16 U.S.C. § 817(1).
. Given the state of the law as herein expounded, we are required to affirm the exercise of the FERC’s jurisdiction over the dam in question. We do so without muсh enthusiasm, however. It may not be coincidental that Starrett, which was established in 1880 and is the principal employer in Athol, Massachusetts, is the last of its kind remaining within our borders. Its attempt to keep its manufacturing costs down to allow it to remain competitive with foreign industry has unfortunately come to naught in the face of bureaucratic outreach. Cf. United States v. ' Johnson,
. Starrett explains that "installed capacity," or "nameplate capacity,” is the maximum potential generating capacity of a turbine generator. "Actual capacity,” on the other hand, is the measured capacity upon installation, which is affected by various site conditions.
.Starrett believed that it was not required to obtain FERC licensing because of certain conversations that GZA had with Michael Spencer, a FERC employee. According to Starrett, on August 9, 2007, GZA contacted the Commission’s small hydropower hotline, and Spencer informed GZA that repairs to the Project would not trigger FERC licensing jurisdiction so long as the total capacity of the Project would not exceed the total listed in Starrett I (i.e., 362 kW) and the height of the dam was not being increased.
Spencer callеd GZA back the following day regarding an outstanding question about the need to notify the Commission prior to starting the repair and rehabilitation project. Spencer said that Starrett did not need to notify the Commission so long as neither the dam nor the powerhouse was to be enlarged and so long as the Project’s total capacity would not exceed the capacity listed in Starrett I.
The Commission, however, notes that the opinions of staff do not bind the Commission, and Starrett does not argue otherwise. Furthermore, the Commission pointed out in its order denying rehearing, L.S. Starrett Co.,
. According to a GZA employee, a cross-flow turbine was chosen because of its efficiency over a wide range of flows, and because of certain self-cleaning characteristics that are helpful when the river is carrying a heavy leaf load. The cross-flow turbine has had a good performance record in New England.
. According to Starrett, it planned to lower the powerhouse floor in order to "reduce the amount of suction head that the turbine experiences and prevent cavitation.” "Cavitation” is "the pitting of a solid surface such as metal or concrete.” McGraw-Hill Dictionary of Engineering 88 (Sybil P. Parker ed., 1997).
. A "plunge pool” serves to dissipate hydraulic energy before the water that passed through a turbine rejoins a river. See Stefano Pagliara et al., Plunge Pool Scour in Prototype and Laboratory, in Hydraulics of Dams and River Structures: Proceedings of the International Conference on Hydraulics of Dams and River Structures, 26-28 April 2004, Tehran, Iran 165, 165 (Farhad Yazdandoost & Jalal Attari eds., 2004).
. A "draft tube” is a tube through which water travels after it passes through the turbine and beforе it rejoins the river. See Anand Prakash, Water Resources Engineering: Handbook of Essential Methods and Design 271 (2004).
. A "penstock” is the pipe in which water travels toward the turbine. See Prakash, supra note 8, at 270.
. The Commission points out that although the statute defines other terms, it does not define ''construction” or otherwise clarify the meaning of the term.
. "Head” can refer to a number of different things. According to Starrett's brief, "gross head” is the difference between the water surface elevation immediately upstream of the dam and the water elevation immediately
. The Commission makеs much of the fact that its own opinions have held that an increase in installed capacity constitutes post-1935 construction. See, e.g., Gilman Bros. Co.,
. The Commission argues that the proposed work would increase the head of the Project, and that under its precedent, this increase constitutes post-1935 construction. See, e.g., Cent. Vt. Pub. Serv. Corp.,
. Starrett encourages us to reverse by arguing that the FERC inappropriately grouped Starrett’s facility with projects that generate power back to the grid. As Habersham notes, however, this distinction does not matter: "whatever they do with their electricity, ... small projects [across the nation] displace power that otherwise would be generated by facilities cоnnected to the interstate grid.”
. We do so regretfully because we are not blind to the economic realities of the situation. Under the facts of this case, the FERC could have certainly exercised its administrative discretion.
Concurrence Opinion
concurring, joined by TORRUELLA, Circuit Judge.
I join this opinion with great reluctance. I do so because Chevron deference requires the result reached here, not that the result makes economic or realistic sense.
Here, we have the last full-line precision tool company producing its product within the United States. Although Starrett has several manufacturing locations worldwide, the Athol location produces most of the precision tools and has remained the company’s headquarters since its fоunding in 1880. Starrett is the largest employer in the greater Athol area, and its payroll typically contributes over $2 million per month to the economy.
In order to remain competitive in the global marketplace, Starrett has aggressively sought to lower its cost structures and has instituted many energy conservation measures, which have both saved operating costs and reduced the company’s carbon footprint. One of these measures included the replacement of the failed left turbine generator with a new, energy-efficient generator, the source of controversy in this case.
Innovations like those taken by Starrett аre a necessary concomitant if we are to reinvigorate the nation’s manufacturing base. Our decision today, however, may well mean that this company loses the economic advantage it would have from its low-cost, nonpolluting power structure. Cost-saving measures like those instituted by Starrett are particularly key for companies based in high energy cost states, like Massachusetts, and may well make the difference in keeping the plant open, providing good paying jobs, and maintaining an essential business such as this in our country. Indeed, machine tools are the lifeblood of industry, and when we have lost all of our domestiс capacity, we become less secure and less able to compete. It is said by some that American industry has died from a thousand cuts, and many contend that over-regulation bears a share of the responsibility.
Further, it is unfortunate that a small power producer like the Starrett facility falls within the ambit of the Commission’s jurisdiction because it is located on a non-navigable stream that is a tributary to a
Perhaps a better argument not advanced by Starrett would have been that, although Chevron applies, the Commission’s definition of posW1935 construction was unreasonable in view of the realities presented by this project. Defining construction to include any increase in capacity still less than that originally authorized, without a de minimis exception and without consideration of a project’s increased efficiency and economic impact, strikes me as troubling. But Starrett did not make this point, nor was there evidence of the costs it would incur in seeking the Commission’s licensing and whether those costs and the necessary delay would take away from the project’s economic advantages. We must deal with the record we have.
