39 Mo. 165 | Mo. | 1866
delivered the opinion of the court.
This was a suit brought in the St. Louis Land Court, under the provisions of “An act entitled an act for the better security of mechanics and others erecting buildings, or furnishing materials for the same, in themounty of St. Louis.”
The account was for work and labor done and materials furnished in making certain additions and. alterations to property located in the city of St. Louis, of which the said Blakesly was the owner and Franz Oeclislin the lessee. After the performance of the labor and the furnishing of said materials, there was a forfeiture of the lease and a re-letting of the premises to the other defendant, Florian Mueller.
Upon the trial there was a verdict and a judgment for the plaintiff, from which an appeal was taken to this court. It is shown by the testimony that the property was leased by Oochslin for the purpose of carrying on a restaurant and hotel business; that the w.ork and materials furnished were for the general purpose of fitting up the premises and adapting them to the business for which he had taken the property. No question is presented by the record for the com sideration of the court, except as to the instructions asked by the defendants, and refused by the court.
The case was tried by the court sitting as a jury, and three declarations of law asked by the counsel for defendants. The first was framed upon the theory that the work and labor done, and materials furnished, must have been directly
The court committed no error in refusing the instructions. The special law for St. Louis county differs from the general law, principally in the fact that it gives a lien to mechanics and others upon leasehold property. If it be said that the intention was to give such a lien only when the work done and materials furnished amounted to an actual amelioration of the freehold, then there could be no security whatever to the very class of men for whose benefit the law was passed. Shall the mechanic and laborer, when their services are demanded, stop to have the question first determined whether the proposed work will really benefit the freehold or not ? And if so, who is to decide that question ? They must ascertain for themselves whether there is such an interest in the property as will be sufficient to save them harmless in the event that the necessary steps have to be taken to secure a lien. In addition to this, they must look to the fact whether the work and labor performed, or the materials furnished, is for the purpose of making such improvements upon the premises as will become permanent fixtures of the freehold. If they are such improvements or additions to the premises as the lessee would be permitted to remove at the end of his term, they are not improvements within the meaning of the act under which this suit is brought, andaré not the subjects of a lien.
Judgment affirmed.