104 Misc. 243 | N.Y. Sup. Ct. | 1918
The subcontractor, Kuhs, claims that he found hardpan in the excavation to be done under the contract and that it was represented that the soil was made up of earth and gravel and also that it was represented that there was sufficient gravel in the excavation and on the premises for use in making concrete, and the owner, the Flower City Tissue Mills Company, claims that the foundation walls of the building were not made watertight as required by the contract and that it is entitled to damages against the contractor for his omission .to ■ make the walls watertight.
The ultimate guide in determining whether or not there can be a recovery for the extra cost of doing work under a contract is the contract itself. It is always a question of the intention of the parties and it is this fact which gives rise to the difficulty of reconciling some of the eases. No two contracts are exactly alike and a difference in the language may make inapplicable a decision under some other contract. It may be said, however, that if there are positive representations in a contract as to the conditions, character or nature of the work amounting substantially to a warranty,- there may be a recovery based upon such representations (Hollerbach v. U. S., 223 U. S. 165; U. S. v. Sage Co., 199 id. 414), and this may be true even though the contractor was required to make investigations and satisfy himself upon these matters. On the other hand, the representations may be such that it was clearly the intention of the parties that the contractor should rely upon his own investigations and examinations and in such cases he can
The first claim of the subcontractor is that he encountered hardpan in the excavation where it was represented that there were earth and gravel and that he is entitled to recover for the additional expense in excavating the hardpan. The specifications provide that “ good gravel will be encountered in the excavation, etc.,” but contain no representations as to the extent of the gravel. They provide, on the contrary,
This conclusion applies to the subcontractor’s claim for the additional cost of procuring gravel. There is no representation in the contract that he would find sufficient gravel with which to fulfill his contract. The specifications say that good gravel will be encountered, but that if sufficient gravel is not encountered he is to' supply whatever is necessary. The specifications do not say that enough gravel will be found to make the concrete work, but quite the contrary. A comparatively small quantity of gravel was found on the premises but it proved insufficient. Under the rule above mentioned and the cases illustrating the application of the rule the subcontractor is not entitled to recover for this item. In order to enable him to recover he must show that there was a representation that there was sufficient gravel on the premises to fulfill his contract. All that the specifications say is that some gravel will be found in the excavation. The language of the specifications put him upon notice and required him to make an investigation and having failed to do so he cannot be heard to complain.
The claim of the owner rests upon the clause in the contract that the waterproofing shall be watertight. It is claimed that one of the walls has cracked and is not watertight. This claim rests upon the language of the contract and specifications just as does that of
The contracts provided that the payments should be made on certificates of the architect. The subcontractor obtained a final certificate but no' such certificate was issued to the principal contractor. A final
The contractor and subcontractor are each entitled to recover the amount due them, and the claims of the contractors for extra work and of the owner for damages for breach of contract are each denied, with costs to the plaintiff and to the defendant Rapp.
Ordered accordingly.