MEMORANDUM OPINION
I. INTRODUCTION
On August 20, 2009, Kuhn Construction Company (“plaintiff”), a Delaware business entity, filed suit against Ocean and Coastal Consultants, Inc. (“OCC”), a Connecticut corporation, and Robert F. Waite, P.E., P.C. (“Waite”), a New York entity (collectively, “defendants”). (D.I. 1) In connection with a wharf reconstruction project, plaintiff brought negligence/negligent misrepresentation claims against Waite and OCC, and fraud and misrepresentation, interference with existing contracts, and common law conspiracy claims against OCC. (Id.)
On October 5, 2009, OCC moved to dismiss this case pursuant to Federal Rules of Civil Procedure (Fed.R.Civ.P.) 12(b)(7) and 12(b)(1), claiming that plaintiff failed to join a required party—Diamond State Port Corporation (“DSPC”)—and that such joinder would destroy the court’s subject matter jurisdiction over this case.
Currently before the court are two motions to dismiss under Fed.R.Civ.P. 12(b)(6): one motion has been filed by defendant Waite (D.I. 65) and the other has been filed by defendant OCC. (D.I. 66) The court has jurisdiction over this case pursuant to 28 U.S.C. § 1332. For the reasons that follow, the court denies Waite’s motion and grant’s OCC’s motion.
II. BACKGROUND
At some point prior to February 2007, DSPC retained OCC in connection with the rehabilitation of Wharf Unit 2, Berth 4 (“the project”). (D.I. 62 at ¶ 6) In anticipation of contractors bidding on the project, OCC prepared (and DSPC distributed) bid documents, which included voluminous drawings and specifications. (Id. at ¶¶ 8-10) These bid documents, which contained the words “FOR BID PURPOSES ONLY,” were meant to provide prospective bidders with the information they would need to submit their bids. (Id. at ¶¶ 11-13) Plaintiff alleges that it reasonably relied on these documents when making its bid. (Id. at ¶ 15) As the lowest responsive and responsible bidder, plaintiff was eventually hired by DSPC to be the general contractor on the project; DSPC and plaintiff entered into a $10,750,000 contract for plaintiffs services. (Id. at ¶ 17) DSPC also hired OCC to assist with the construction.
Plaintiff references three activities which it claims resulted in the current dispute: (1) undisclosed changes to the bid documents after the contract award; (2) undisclosed subsurface conditions and obstructions; and (3) welding issues.
A. Changes to the Bid Documents
On or about May 24, 2007, OCC prepared and provided plaintiff with “Issued For Construction” drawings. (Id. at ¶ 24) These drawings, which indicated that zero revisions existed, were meant to be the drawings that plaintiff relied on in the construction of the project. (Id. at ¶¶ 25-27) Because there was no indication of revisions, plaintiff requested that OCC mark any changes between the bid documents and the Issued For Construction drawings. (Id. at ¶¶ 27-28) Plaintiff alleges that OCC purposefully obscured material changes. (Id. at ¶¶ 29-31) One such change related to welding requirements. According to plaintiff, the bid documents indicated that welding would only be required to connect the lower sections of the steel pipe pile; the upper connection would not require welding. (Id. at ¶ 22) Plaintiff claims that OCC knowingly and intentionally misrepresented that there was language in the bid documents that required welding of the upper sections of the steel pipe piles. (Id. at ¶¶ 32-38)
Another material change that was allegedly obscured concerned datum and elevation changes. According to plaintiff, there were numerous changes that were not disclosed, and were obscured, by OCC. (Id. at ¶¶ 39-53) Plaintiff also claims that these changes had a serious impact on plaintiffs ability to work since these changes meant much of the construction would be affected by the tides. (Id. at ¶¶ 54-63) Apparently neither OCC or DSPC would address the issue with plaintiff. (Id. at ¶¶ 57-58)
B. Undisclosed Subsurface Conditions
In anticipation of preparing the bid documents, OCC undertook a review of the subsurface conditions. (Id. at ¶ 65) Plaintiff alleges that OCC misrepresented, in the bid documents, the effect that the subsurface conditions would have on the cost and duration of the project; plaintiff further states that it relied on these misrepresentations in calculating its bid. (Id. at
C. Welding Issues
While the plaintiff-DSPC contract did not contain any specific welding requirements or a requirement that plaintiff use American Welding Society (“AWS”) prequalified base metals, OCC developed a weld acceptance criteria to test plaintiffs work against. {Id. at ¶¶ 92-99) Waite was hired by OCC to examine, and report to OCC and DSPC, about the quality of plaintiffs welds. {Id. at ¶ 102) In accordance with a plan devised by OCC, Waite examined the welds on 110 of the 360 steel pile pipes and issued several reports on the quality of those welds. {Id. at 103-04) In an August 15, 2008 report to OCC, Waite concluded that 27 of the 110 welds were problematic. Specifically, the report states that, “[o]f the 110 top welds inspected, 8 had fully dislodged backrings, 12 had mostly dislodged backrings, 7 had partly dislodged backrings and 11 other exhibited a notable flaw.... The dislodgment rate should have been 0% but it was 25% (27 of 110). This indicates a severe problem with the weld quality in the top welds.” {Id. at ¶¶ 105-07; see also id. at ex. E) The report ultimately concludes that there is a “more than adequate justification for the rejection of all the top and extension welds due to gross non-conformance to the contract and ANS/AWS Dl.l:2006, Structural Welding Code ... requirements. Although the welds are rejectable, engineering judgment may be exercised based on anticipated service loading.” {Id.)
III. STANDARD OF REVIEW
In reviewing a motion filed under Fed.R.Civ.P. 12(b)(6), the court must accept all factual allegations in a complaint as true and take them in the light most favorable to plaintiff. See Erickson v. Pardus,
IV. DISCUSSION
A. Waite’s Motion
As discussed, the only claim made against Waite in plaintiffs amended complaint is one of negligent misrepresentation. The parties agree that, in order to prove negligent misrepresentation under Delaware law, a plaintiff must show: (1) the existence of a pecuniary duty to provide accurate information; (2) the supplying of false information; (3) that the defendant failed to exercise reasonable care in obtaining or communicating the information; and (4) that the plaintiff suffered a pecuniary loss caused by reliance upon the false information. See Lincoln Nat. Life Ins. Co. v. Snyder,
The crux of Waite’s motion to dismiss is that plaintiff has failed to properly plead element two. Waite argues that the complaint does not set forth any false statements, only statements based upon Waite’s professional judgment. (D.I. 65 at 9-10; D.I. 74 at 5)
Plaintiff responds to Waite’s motion with two arguments. First, plaintiff points the court to Fed.R.Civ.P. 12(g)(2), which provides: “Except as provided in Rule 12(h)(2) or (3), a party that makes a motion under this rule must not make another motion under this rule raising a defense or objection that was available to the party but omitted from its earlier motion.” On the basis of this rule, plaintiff argues that it was procedurally improper to file a motion under 12(b)(6) since Waite had already filed a motion under 12(b)(7). (D.I. 72 at 4-5) What plaintiff fails to recognize is that Rule 12(h)(2) specifically permits plaintiff to file this 12(b)(6) motion; filing a motion under 12(b)(7) does not prohibit a party from filing a subsequent motion under 12(b)(6). The advisory committee notes emphasize this point: “[WJhile [certain 12(b) motions] are subject to waiver ... the more substantial defense[ ] of failure to state a claim upon which relief can be granted ... [is] expressly preserved against waiver by ... subdivision (h)(2).” Fed.R.Civ.P. 12, advisory committee notes to the 1966 Amendment, subdivision h.
Second, plaintiff points the court to its July 15, 2010 memorandum opinion (
The court also notes that Waite has not cited any Delaware case law for the proposition that a negligent misrepresentation claim must be dismissed where a complaint provides only allegations of professional opinions or conclusions.
B. OCC’s Motion
As discussed, plaintiffs amended complaint sets forth four causes of action against OCC: 1) negligent misrepresentation; 2) fraud and misrepresentation; 3) interference with existing contracts; and 4) common law conspiracy. OCC argues that each claim should be dismissed under Fed.R.Civ.P. 12(b)(6).
1. Negligent misrepresentation
OCC argues that plaintiffs claim for negligent misrepresentation is barred by the economic loss doctrine. (D.I. 66 at 10-13) The economic loss doctrine is a judicially created doctrine that allows a party to recover in tort only if losses are accompanied by bodily harm or property damage; in other words, the doctrine prevents plaintiffs from recovering in tort for losses suffered that are solely economic in nature. Delaware Art Museum v. Ann Beha Architects, Inc., Civ. No. 06-481,
One who, in the course of his business, profession or employment, or in any other transaction in which he has a pecuniary interest, supplies false information for the guidance of others in their business transactions, is subject to liability for pecuniary loss caused to them by their justifiable reliance upon the information, if he fails to exercise reasonable care or competence in obtaining or communicating the information.
Id.
“To determine whether a defendant is in the business of supplying information, a court must conduct a case-specific inquiry, looking to the nature of the information and its relationship to the kind of business conducted.” RLI Ins. Co. v. Indian River School Dist.,
With specific reference to architecture and engineering defendants, the court in Tolan and Son, Inc. v. KLLM Architects, Inc. explained the issue this way: “[Because the focus of an engineer’s or architect’s work is usually tangible—a building, a structure, or a product—it is not in the business of providing information. [A]ny information provided is merely incidental to the finished product.”
While “[decisions as to whether a defendant falls within the exception to the economic loss doctrine are typically made at summary judgment in Delaware,” the issue can be resolved on a motion to dismiss when the complaint unambiguously places a defendant outside of the exception. Delaware Art Museum,
Plaintiff, in support of its position, cites the Delaware Superior Court case Guardian Construction. Co. v. Tetra Tech Richardson, Inc.,
While the facts in Guardian are similar to those in the case at bar, the court nevertheless declines to adopt the holding in that case. First, the court notes that OCC, unlike TTR, remained involved past the bid phase of the construction project. Second, the court emphasizes that Guardian is a non-precedential Superior Court opinion. Third, in the twenty-plus years since Guardian adopted the § 552 exception to the economic loss doctrine, Delaware courts have clarified, refined and narrowed the scope of the exception. While Guardian may be analogous in some ways, the current weight of authority suggests that the exception does not apply; the provision of plans and drawings in connection with a construction project is considered to be information that is incidental to the sale of a finished, tangible product. See e.g. Christiana Marine,
2. Fraud and misrepresentation
OCC argues that plaintiffs fraud and misrepresentation claim should be dismissed for two reasons. First, OCC claims that the economic loss doctrine bars recovery. (D.I. 66 at 10-13) Second, OCC argues that plaintiff has not met the heightened pleading standard set forth in Fed.R.Civ.P. 9(b). (D.I. 66 at 16-20)
a. Economic loss doctrine
As discussed, the economic loss doctrine generally prohibits recovery in tort for solely economic harm. Fraudulent inducement is, however, a recognized exception to this doctrine. See Brasby v. Morris, No. C.A. 05C-10-022-RFS,
b. Heightened pleading standard
Allegations of fraud are subject to a heightened pleading standard. Under Fed.R.Civ.P. 9(b), a party alleging fraud or mistake “must state with particularity the circumstances constituting fraud or mistake.” This heightened pleading standard was meant to “place the defendants on notice of the precise misconduct with which they are charged, and to safeguard defendants against spurious charges of ... fraudulent behavior.” Seville In
Another element that is essential to a fraud pleading is scienter. Kuhn Const.,
Scienter is an essential element in pleading fraud. Plaintiff has failed to allege that defendant knew or believed that the information that was provided was either false or purposefully misleading. Further, plaintiff has not identified the content of the alleged misrepresentations or how the claimed representations were false. The failure to allege circumstances indicating conscious or reckless behavior by the defendant, or facts showing a motive or clear opportunity for committing fraud cause plaintiff’s claim to fail as a matter of law.
Id. On the basis of this holding, OCC argues plaintiffs complaint should also be dismissed. (D.I. 66 at 18-20)
As discussed, in light of the economic loss doctrine, plaintiff could only proceed on a fraud claim to the extent that the claim alleged that fraud induced the signing of the contract. In this regard, plaintiff has alleged that OCC made false representations in the bid documents in order to induce plaintiff to sign the contract with DSPC. (D.I. 62 at 138)
“A claim for tortious interference with contractual relations requires proof of five elements under Delaware law: 1) a contract, 2) about which the defendant knew, 3) an intentional act that is a significant factor in causing the breach of contract, 4) without justification, and 5) which causes injury.” Johnson v. Geico Cas. Co.,
OCC argues that it was an agent of DSPC and, therefore, cannot have tortiously interfered. (D.I. 66 at 13-15) As discussed in the court’s July 15, 2010 memorandum opinion, “an agency relationship is determinable only after appropriate discovery and, thus, is not appropriate for a motion to dismiss.” (
Alternatively, OCC argues that, even if it is not deemed an agent (or such a determination cannot be made on this motion to dismiss), under Delaware law, an “interference privilege” exists for non-parties to the contract when the non-party shares a commonality of economic interests with one of the contracting parties and acts in furtherance of the parties’ shared business interests. (D.I. 66 at 15) (citing Grunstein,
Plaintiff responds by arguing that the interference privilege applies only to “affiliated enterprises” such as parent and subsidiary companies, and would not apply to OCC. (D.I. 70 at 16) Contrary to plaintiffs assertion, the interference privilege applies to independent contractors.
4. Common law conspiracy
Under Delaware law, a civil conspiracy is not an independent cause of action; rather, it must be predicated on an underlying wrong. Ramunno v. Cawley,
V. CONCLUSION
For the reasons discussed above, the court denies defendant Waite’s motion to dismiss but grants defendant OCC’s motion. An appropriate order shall issue.
ORDER
At Wilmington this 14th day of February, 2012, consistent with the memorandum opinion issued this same date;
IT IS ORDERED that:
1. Defendant Waite’s motion to dismiss the amended complaint (D.I. 63) is denied. The trial date originally set for April 16, 2012 will be rescheduled in order to accommodate the parties’ need to conduct discovery and submit summary judgment motions.
2. Defendant OCC’s motions to dismiss the amended complaint (D.I. 64) is granted.
Notes
. To the extent that DSPC would be deemed an indispensable party, its joinder would have eliminated diversity between the parties.
. Waite’s citation to Massachusetts law is neither binding nor persuasive. (D.I. 65 at 8-9)
. A trial date is set for April 16, 2012 and a pre-trial conference is scheduled for March 29, 2012. In light of the court's decision, the trial date will be re-scheduled, after consultation-with the parties, in order to accommodate discovery and a summary judgment motion .practice.
. Plaintiff argues, as it did in its defense of Waite's motion, that Fed.R.Civ.P. 12(g)(2) bars OCC from filing this 12(b)(6) motion. (D.I. 70 at 6-7) For the reasons discussed in section IV.A., supra, the court finds this argument to be without merit.
. Delaware employs a “narrow application and strict construction of § 552.” Christiana Marine Serv. Corp. v. Texaco Fuel and Marine Mktg., No. Civ.A.98C-02-217WCC,
. While Tolan and Son is an Illinois case, Delaware courts have looked to Illinois law, and specifically Tolan and Son, in an effort to explain and apply the exception at issue. See e.g., Christiana Marine,
. Aside from preparing bid plans and "Issued for Construction” drawings, a review of plaintiff's amended complaint reveals that OCC was also tasked with overseeing and monitoring the progress of the construction project and, more specifically, tasked with raising and addressing construction-related concerns with plaintiff. (See e.g., D.I. 62 at ¶ 32 (OCC held "Progress Meetings” in which it raised construction-related concerns and told plaintiff how to address those concerns); id. at ¶ 73 (noting that, during the project, OCC directed plaintiff to alter its plans and proceed in a different fashion); id. at ¶ 88 (noting that plaintiff, during the course of the construction project, would seek answers to construction-related questions from OCC); id. at ¶¶ 101-04 (noting that OCC coordinated an inspection of plaintiff's work product)). Thus, while the preparation of these plans and drawings is, alone, sufficient to place OCC outside of the exception, OCC's other activities are further evidence that OCC was not in the business of supplying information. While plaintiff would have the court view the preparation of the bid documents in a vacuum, separate and apart from any other work OCC did on this project (D.I. 70 at 11-12), the court declines to do so. In determining whether a defendant is in the business of supplying information, the court must consider "the nature of the information and its relationship to the kind of business conducted.” RLI Ins.,
. Both parties cite to Brasby v. Morris and agree that its holding is accurate and applicable. (D.I. 70 at 14; D.I. 75 at 6-7)
. Specifically, plaintiff alleges that OCC made the following "false and fraudulent misrepresentations” in the bid documents: 1) there was no welding requirement for the upper sections of the piles; 2) plaintiff could perform work "in the dry,” without regard for tidal issues; 3) the subsurface conditions would not detrimentally affect pile driving and overall construction; and 4) OCC would effectively communicate and work with plaintiff to resolve all issues. (D.I. 62 at ¶ 138) The other alleged fraud concerns OCC misrepresenting the existence of, and obscuring changes made between the issuance of the bid documents and the Issued For Construction drawings (with specific respect to welding issues and datum/elevation changes). {Id. at ¶¶ 139-40) These alleged misrepresentations occurred after plaintiff entered into the contract.
. As argued by OCC: "[i]n order to accept [plaintiffs] fraud claims as plausible, the Court would have to accept that OCC had
. As discussed, the precise nature of the DSPC-OCC relationship is not properly determined on a motion to dismiss. While OCC makes a strong argument, based upon the contracts incorporated by reference into the complaint, that it was DSPC's agent, the court declines to decide the relationship at this stage of the proceedings. Nevertheless, the court notes that, if OCC is not deemed DSPC's agent, it will be considered an independent contractor as there is no dispute that DSPC hired OCC to act on its behalf.
