Kronberg Bros. v. SteeleKronberg Bros. v. Steele
- Reporters:
- , ,
- Before:
- Dranginis
Opinion
The plaintiff, Kronberg Brothers, Inc., appeals from the judgment of the trial court rendered in favor of the defendants, John Steele and Eileen Steele. On appeal, the plaintiff claims that the court improperly (1) concluded that the contract in this case violated the Home Improvement Act (act),
At some point during the performance of the work by the plaintiff and its subcontractors, a dispute arose between the defendants and the plaintiff as to the scope, cost and quality of the work. After the parties failed to resolve the issues, the plaintiff commenced this action to foreclose on the mechanic’s lien that it had filed against the defendants’ property. The defendants denied the plaintiff’s claims and, by special defense, claimed that the contract was in violation of the act and that the plaintiff had breached its obligations in other material respects. The defendants also filed a counterclaim sounding in CUTPA, seeking costs and attorney’s fees plus punitive damages.
I
First, the plaintiff claims that the court improperly determined that the contract violated the act.
In its memorandum of decision, the court found that the contract in this case violated the act in three specific respects. First, the court found that the contract did not contain proper notice of the homeowners’ cancellation rights as required by
Second, the court found that the plaintiff had failed to enter the date of the transaction on any copy of the “Notice of Cancellation” as required by
Last, the court found that a fully completed receipt or copy of all contracts and documents was not pro
In support of its position, the plaintiff claims that Wright Bros. Builders, Inc. v. Dowling, supra,
In Dowling, our Supreme Court stated: “The [Home Improvement Act] is a remedial statute that was enacted for the purpose of providing the public with a form of consumer protection against unscrupulous home improvement contractors. . . . The aim of the statute is to promote understanding on the part of consumers with respect to the terms of home improvement contracts and their right to cancel such contracts so as to allow them to make informed decisions when purchasing home improvement services. . . . While the purposes of the statute are advanced by an interpretation that makes compliance with the requirements of
The cancellation notice in Dowling failed to contain the date of the transaction and the date by which the defendants could cancel the contract. Our Supreme Court determined that “the plaintiffs failure to enter the required dates on the notice of cancellation did not, under the circumstances, constitute such a deviation from the precise specifications of the [act] as to compel the conclusion that the contract failed to comply with the [act].” Id., 233. The court further explained that “[t]he missing information, however, easily could have been gleaned from even the most cursory review of the contract” because in immediate proximity to the space reserved in the contract for the homeowner’s signature was language providing cancellation notice. Id. The court also determined that the transaction date was on the first page of the contract and from that information, the buyer could have easily determined what the cancellation period was.
In this case, however, not only did the cancellation notice fail to contain the date of the transaction and the date by which the defendants could cancel the contract, the contract itself lacked a transaction date. Furthermore, the contract did not contain the required cancellation notice in immediate proximity to the space reserved in the contract for the signature of the buyer. Near the top of the second page of the contract, there was language that notified the defendants of their right to cancel the contract, but the language failed to comply with
We conclude that the plaintiffs failure to comply with the act in this case amounted to more than a mere
II
The plaintiff next claims that the court improperly awarded damages under CUTPA.
“A party seeking to recover damages under CUTPA must meet two threshold requirements. First, he must establish that the conduct at issue constitutes an unfair or deceptive trade practice. . . . Second, he must present evidence providing the court with a basis for a
In its memorandum of decision, the court found that there was a per se violation of CUTPA because the contract violated the act. In addition, the court cited other bases for its finding that the plaintiff had violated CUTPA. For example, the court found that the plaintiff had failed to obtain building and electrical permits for the work it performed even though the cost of the permits was billed to the defendants. In addition, live wires were sealed behind closed walls in at least three locations. The court found that “[t]he sum total of all of the above dictates the conclusion that the plaintiff in various and numerous instances was guilty of business practices which the CUTPA seeks to discourage and punish,” and the defendants “lost time from work and had to spend over $6000 for corrective work, as well as the disruption of their lives . . . .”
Ill
Finally, the plaintiff claims that the court improperly applied the law with respect to the claim of bad faith and failed to apply properly the evidence that was offered at trial. Specifically, the plaintiff asserts that the court improperly rejected its claim of bad faith by the defendants on the basis of its finding that none of the acts alleged was committed prior to the execution of the contract. We do not agree.
“In Barrett Builders v. Miller, [
In its memorandum of decision, the court stated: “[N]one of the acts alleged was committed prior to the execution of the disputed contract. There is no evidence that the defendants did anything to create the defects in the cancellation notice. . . . The balance of the acts complained of arose out of the deteriorating relationship between the parties and can hardly be held to be actions in bad faith when the defendants were confronted with what must have been an exasperating ordeal. The plaintiff overlooks the evidence in this trial, which hardly depicts a neat, orderly and efficient project proceeding on time and without delay. The bad faith claim must be rejected.”
Although the court specifically mentioned the time period before the execution of the contract, it is clear that the court did not rely solely on those acts as a basis for its decision. The court clearly considered the defendants’ acts before and after the execution of the contract when it rejected the plaintiffs bad faith claim.
The judgment is affirmed.
In this opinion the other judges concurred.
Notes
* ** *
“(c) The contractor shall provide and deliver to the owner, without charge, a completed copy of the home improvement contract at the time such contract is executed.
* * *
“(e) Each home improvement contract entered into shall be considered a home solicitation sale pursuant to chapter 740 and shall be subject to the requirements of said chapter regardless of the location of the transaction or of the signing of the contract.
“(f) Nothing in this section shall preclude a contractor who has complied with subdivisions (1), (2), (6), (7) and (8) of subsection (a) of this section from the recovery of payment for work performed based on the reasonable value of services which were requested by the owner, provided the court determines that it would be inequitable to deny such recovery.”
In its reply brief, the plaintiff raises for the first tune the issues of the award of punitive damages and attorney’s fees, and the application of the “cigarette rule” under CUTPA. “It is a well established principle that arguments cannot be raised for the first time in a reply brief. . . . Claims of error by an appellant must be raised in his original brief ... so that the issue as framed by him can be fully responded to by the appellee in its brief, and so that we can have the full benefit of that written argument.” (Citations omitted; internal quotation marks omitted.) Kelley v. Tomas,
We note that the plaintiff filed a motion for articulation with the trial court and a motion for review of the denial of that motion with this court. This court granted the motion for review, but denied the relief requested therein. In both motions, the plaintiff sought to have the trial court further articulate “the conduct of the defendants which occurred prior to the execution of the original contract documentation . . . .” Now, on appeal, the plaintiff claims that the court improperly relied on the defendants’ actions prior to the execution of the contract.