This action was brought by plaintiff Jim Kristek against defendant James Catron to recover damages for the negligent construction of plaintiff’s residence. Following a bench trial plaintiff was awarded judgment in the amount of $1,470 and costs. Defendant appeals.
The house now owned by plaintiff was constructed by defendant under a contract with Centurian Investments. The house was completed in 1975 and sold to plaintiff by Centurian in March 1976. Over two years later, in December 1978 plaintiff noticed several stains on the ceiling and walls of the house resulting from water leakage. At trial, an experienced roofer testified on behalf of plaintiff that in his opinion the lack of felt under the shingles and the incorrect placement of nails on the roof caused the leaking which stained the walls and ceiling. This expert also testified that to properly remedy the leaking, the entire roof would have to be replaced.
Defendant first contends that the trial court erred in ruling that the two-year statute of limitations on negligence did not bar this action (K.S.A. 60-513) because construction of the residence was completed in October 1975, while the lawsuit was not filed until October 1979.
*496 K.S.A. 60-513(h) provides:
“Except as provided in subsection (c) of this section, the cause of action in this action [section] shall not be deemed to have accrued until the act giving rise to the cause of action first causes substantial injury, or, if the fact of injury is not reasonably ascertainable until some time after the initial act, then the period of limitation shall not commence until the fact of injury becomes reasonably ascertainable to the injured party, but in no event shall the period be extended more than ten (10) years beyond the time of the act giving rise to the cause of action.”
Defendant argues that the leak in the roof must have existed prior to December 1978 when plaintiff first noticed water spots on his ceiling. Plaintiff agrees that the leak must have existed prior to the time the water spots appeared on the ceiling but argues that discovery of the leak prior to that time would have required him to either remove the shingles on the roof or regularly inspect the crawl space above the ceiling. Plaintiff further argues that these are not normal inspection procedures that a homeowner would make; therefore, the leak was not reasonably ascertainable under 60-513(h) until the water spots first appeared on the ceiling.
When, as here, the evidence is in dispute as to when substantial injury first appears or when it becomes reasonably ascertainable, the issue is for determination by the trier of fact.
Friends University v. W.R. Grace & Co.,
Defendant also contends that as a matter of law, he could not be liable to plaintiff for negligence because the work he performed as a building contractor was completed and accepted by the party to whom the performance was owed. 13 Am. Jur. 2d, Building and Construction Contracts § 139. This principle of the non-liability of building contractors to third parties has a long if largely discredited history. See Annot.,
“A building or construction contractor is liable for an injury to a third party resulting from work negligently performed even though the injury occurs after completion of the work and its acceptance by the owner, where such work is reasonably certain to endanger third persons if negligently done.”
Because the facts of
Talley
involved a personal injury, defendant argues that the holding is limited to personal injury cases and should not be extended to cases such as this one which only involve economic injury. The rationale for the non-liability rule is generally premised on the lack of privity of contract between the building contractor and third persons.
Talley,
Talley
also noted that only one previous Kansas case had employed the accepted work doctrine but observed that the plaintiff in that case failed to allege in his petition negligence by the defendant.
Engler v. Aldridge,
If the Talley rule were intended to be limited to personal injury cases, no such disapproval would have been necessary.
Further support for rejecting the limitations on
Talley
urged by defendant is found in the fact that some of the cases cited by that court in justifying rejection of the non-liability rule involved property damage. See,
e.g., Russell v. Whitcomb,
In
McDonough v. Whalen,
The Supreme Court of South Dakota concluded in
Brown v. Fowler,
Navajo Circle, Inc. v. Development Concepts,
We agree with these authorities and hold that a purchaser of a residence may recover property damage caused by the negligence of its builder despite the lack of any contractual relationship with the builder. Therefore, a construction contractor is liable for any injury to a third party, personal or economic, resulting from work negligently performed even though the injury occurs after completion of the work and its acceptance by the owner, when such injury is reasonably certain to occur if the work is negligently done.
Defendant also maintains that the trial court erred in finding that the defendant’s negligence was the proximate cause of plaintiff’s damages. Plaintiff’s expert witness testified that in his opinion the leak was caused by lack of felt and improperly placed nails. When there is no evidence of any other cause for the leaks complained of in this case, the expert’s evidence is sufficient to sustáin the verdict on appeal.
Marcotte Realty & Auction, Inc. v. Schumacher,
Finally, defendant claims that the judgment awarded plaintiff was excessive. The trial court awarded as damages the cost of replacing the entire roof. Defendant argues that this award is unsupported by the evidence and that the award should be the cost of repair rather than the cost of replacement. Again, the only evidence on this point was that of the plaintiff’s expert witness who testified that it was necessary to replace the roof in order to stop the leak and estimated such cost to be $1,460, the amount of damages actually awarded. Therefore, we are compelled to find that there was substantial competent evidence to support the damage award.
Affirmed.