KRIST OIL COMPANY, QUALITY RENTALS OF HOUGHTON, LLC, KEVIN KING, GREGG NOMINELLI, DEBBIE AGUILAR, ALBERT AGUILAR, PAUL KOVACIC, and ZBIGNIEW BELL, Plaintiffs-Appellees, v SEMCO ENERGY, INC., doing business as SEMCO ENERGY GAS COMPANY, Defendant/Cross-Plaintiff/Third-Party Plaintiff-Appellee, and MJO CONTRACTING, INC., Defendant/Cross-Defendant-Appellant, and PORTAGE LAKE WATER & SEWAGE AUTHORITY, Third-Party Defendant.
No. 367243
STATE OF MICHIGAN COURT OF APPEALS
March 20, 2025
UNPUBLISHED; Houghton Circuit Court LC No. 23-18056-NZ
Before: RIORDAN, P.J., and YATES and ACKERMAN, JJ.
PER CURIAM.
I. FACTS AND PROCEDURAL HISTORY
In 2008, the Portage Lake Water and Sewer Authority hired MJO to install a sewer line between the cities of Houghton and Hancock, which included the necessary excavation work. On March 13, 2022, there was an explosion in Houghton. Various injured parties allege that the explosion was caused by a leak in a gas line owned by SEMCO Energy Gas Company and that the leak resulted from MJO‘s negligence during the sewer line installation. Exactly one year after the explosion, plaintiffs sued MJO and SEMCO, alleging negligence on multiple grounds.
In its answer, MJO raised
II. ANALYSIS
Trial court rulings on motions for summary disposition are reviewed de novo, Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999), as are issues of statutory interpretation, Ford Motor Co v Woodhaven, 475 Mich 425, 438; 716 NW2d 247 (2006). Although MJO nominally recited
MJO seeks to invoke what the Supreme Court has described as “the contractor statute of repose,”2
A person shall not maintain an action to recover damages for injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective or unsafe condition of an improvement to real property, or an action for contribution or indemnity for damages sustained as a result of such injury, against any state licensed architect or professional engineer performing or furnishing the
design or supervision of construction of the improvement, or against any contractor making the improvement, unless the action is commenced within either of the following periods: (a) Six years after the time of occupancy of the completed improvement, use, or acceptance of the improvement.
(b) If the defect constitutes the proximate cause of the injury or damage for which the action is brought and is the result of gross negligence on the part of the contractor or licensed architect or professional engineer, 1 year after the defect is discovered or should have been discovered. However, an action to which this subdivision applies shall not be maintained more than 10 years after the time of occupancy of the completed improvement, use, or acceptance of the improvement.
MJO contends that plaintiffs’ allegations do not amount to gross negligence, so the six-year repose period under
That reasoning ignores our decision in Abbott v John E. Green Co, 233 Mich App 194; 592 NW2d 96 (1998). In Abbott, the defendants were “contractors who allegedly designed, manufactured, or installed asbestos-containing materials” in a Saginaw factory. Id. at 196. The plaintiffs claimed that the defendants were “liable for injuries . . . caused when the construction activity associated with the installation of the improvements resulted in asbestos fibers being released.” Id. at 196-197. When the defendants moved for summary disposition under
[S]tatutes of repose, like statutes of limitation, are to be construed in a manner that advances the policy they are designed to promote. The purpose of the statute of repose is to protect engineers, architects, and contractors from stale claims and to eliminate open-ended liability for “defects in workmanship.” The term “workmanship” encompasses not only the quality of the finished product, but the manner of construction as determined by the “art, skill, or technique of [the] workman.” In this case, plaintiffs contend that the manner of construction was defective in that the components were cut and assembled on-site resulting in the release of asbestos. Plaintiffs thus challenge defendants’ “workmanship,” and it would be contrary to the purpose of the statute to allow this stale claim to proceed. Contractors would not enjoy the “repose” that the statute intends to guarantee if plaintiffs, barred from bringing claims arising out of the finished result of an
improvement, could nonetheless bring claims arising out of the construction practices employed in making the improvement. [Id. at 200-201 (cleaned up).]
Abbott‘s reasoning was applied to a project similar to the one at issue here in Citizens Ins Co v Scholz, 268 Mich App 659; 709 NW2d 164 (2005). In Citizens, Zinger Sheet Metal hired F.C. Scholz as the construction manager for an addition to Zinger‘s building. Scholz, in turn, hired subcontractors to perform the work. They excavated below the foundation of the existing building for the addition, but while doing so, the wall of the existing building collapsed. The plaintiff insurer paid out on an insurance claim to Zinger and then sued Scholz and the subcontractors as subrogees. That suit was filed just shy of six years later. The defendants argued that the matter was time-barred by the general three-year limitations period for negligence actions, and the trial court agreed. On appeal, the plaintiff averred—at a time when
Defendants’ interpretation does not comport with our previous decisions, which consider the project as a whole and not as isolated components in determining whether the injury involves an improvement to real property. More importantly, decisions of this Court that have addressed the applicability of § 5839(1) to construction activities have, in effect, held that § 5839(1) applies regardless of whether the claim accrues during construction and is based on the contractor‘s workmanship rather than on the completed improvement. [Id. at 666.]
As a result, we rejected the defendant‘s argument that “the act of excavating is not a ‘defective and unsafe condition’ nor does it constitute an ‘improvement’ to real property“; rather, “[b]ecause the excavation was an integral part of the construction of the building addition, we hold that it was an improvement to real property.” Id. at 671.
That reasoning is equally applicable here. This Court has held that an “improvement” for purposes of the statute is a “permanent addition to or betterment of real property that enhances its capital value and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.” Pendzsu v Beazer East, Inc, 219 Mich App 405, 410-411; 557 NW2d 127 (1996) (citation omitted). The sewer line at issue enhanced the value and utility of the properties it served and was intended to be permanent. In light of Abbott and Citizens Ins Co, both the physical object and the labor expended in its construction constitute the “improvement” under
Plaintiffs contend that the caselaw interpreting the statute is distinguishable because, in those cases, “the component involved in the improvement was in fact an integral part of the contracted for improvement.” Here, by contrast, “[t]he sewer line and gas line are two distinct utility lines and one has nothing to do with the other.” However, the trench in which the sewer line is buried is integral to its function. Plaintiffs allege that, in digging that trench and installing the sewer line, MJO damaged the gas line in a manner that ultimately led to the 2022 explosion. That theory of causation falls squarely within the framework established in Abbott and Citizens Ins Co. They further contend “that a claim cannot be considered stale when there was never any notice of a potential claim.” However, a statute of repose operates independently of notice, aiming solely to provide finality by barring claims regardless of when the injury is discovered.
SEMCO offers a variety of alternative bases on which the trial court‘s decision could be affirmed. We find its arguments unpersuasive. It points to
Accordingly, we reverse the trial court‘s decision and remand for further proceedings not inconsistent with this opinion. Defendant-appellant MJO, having prevailed in full, may tax costs as the prevailing party pursuant to
/s/ Michael J. Riordan
/s/ Christopher P. Yates
/s/ Matthew S. Ackerman
