Koppers Co. v. Missouri Pacific RailroadKoppers Co. v. Missouri Pacific Railroad
In 1962, аppellee, Missouri Pacific Railroad Company, Inc. (MoPac), and appellant, Kop-pers Company (Koppers), entered into an agreement whereby Koppers contracted to treat crossties, switch tiеs, bridge lumber, timbers, and other lumber materials used by MoPac in its railway system. MoPac contracted to deliver the materials to Koppers by opentop railroad car, and Koppers agreed to unload and treat the lumber and reload the materials onto a railroad car to be returned to MoPac. The contract also contained a paragraph in which Koppers agreed to indemnify MoPac against any and all claims, judgments, and lossеs incident to or in any way connected with Koppers’ operations under the agreement. In accordance with its provisions, the contract was terminated by MoPac effective March 10, 1984.
On October 14, 1982, a Koppers employee was injured on Koppers’ premises when he fell between moving railroad cars owned by MoPac. In August 1984, the employee sued MoPac for injuries sustained, and that suit was settled on April 23,1987. On June 10,1985 (subsequent to suit being filed by the employee but рrior to the settlement agreement), MoPac made written demand on Koppers to defend, indemnify and hold MoPac harmless. Koppers refused to do so. On August 22, 1988, MoPac brought suit to enforce the indemnity provision in the parties’ contrаct. The trial court entered judgment for MoPac in the amount of $300,000.00, finding that the indemnity clause survived the March 10,1984, expiration of the contract and required Koppers to indemnify MoPac. Koppers brings this appeal from that ruling. We affirm.
Under the indemnity clause in the contract, Koppers agreed:
On behаlf of itself, its successors and assigns to fully protect, indemnify and save harmless the Railroad, its successors and assigns against any and all claims, demands, suits, judgments, losses and expenses incident to, or in any way connected with the Contractor’s oрerations under this agreement and howsoever arising, whether by reason of the infringement or alleged infringement of patent rights covering or relating to treating processes, machinery, apparatus, appliances or facilities, or by reason of loss or injury of whatsoever nature, to persons or property or otherwise, excepting loss by fire or by the acts of the employees of the Railroad.
Appellant and appellee stipulated that, at the time of the injury, the contract between the parties was in force. The parties further agreed that the contract terminated prior to suit being filed by the injured Koppers employee against MoPac. They also agreed that the only issue before the trial court was whether appellee’s right to indemnification from appellant survived the termination of the agreement between the parties.
In holding that the indemnity clause survived, the trial court stated that, although it had not found a case precisely on point, it was “most persuaded” by Kentucky Fried Chicken Corp. v. Collectramatic, Inc.,
Collectramatic sold a pressure cooker to KFC pursuant to the 1972 agreement. In 1980, a KFC employee was injured while using this pressure cooker. The employee sued KFC and Collec-tramatic, and both defendants settled. Then, KFC attempted to recover from Collectrаmatic the portion of the settlement KFC had paid, basing its claim for indemnity on the 1972 agreement. The court held that KFC was entitled to indemnification under the 1972 agreement and found the parties intended in the 1974 contract to merge only their prior agreements as to terms governing purchases and sales yet to be made, and the parties intended it to have no effect at all on vested rights and concomitant duties with respect to sales already concluded. In regard tо the 1972 agreement, the court said:
One would typically expect that the agreement in effect at the time equipment was bought and sold would determine the parties’ rights and duties with respect to that equipment.
Id. at 247. And in response to Collеctramatic’s argument that a provision in the 1974 agreement clearly indicated that the parties intended that the 1974 agreement would supersede all previous agreements, including the 1972 agreement, the court said:
For a party to аbandon, in a later contract of this type, a right previously bargained for and acquired would certainly be unusual.
Id. at 248.
Koppers, however, argues that the Kentucky Fried Chicken case is only marginally on point and would distinguish that case on the basis that the 1972 agreement provided that the indemnity clause “shall survive the termination of this agreement.” The court in that case did not regard this provision to be controlling. It said: “The language of each of these agreements is entirely prоspective and makes no reference to vested rights and duties.” So, although the 1972 agreement provided that the indemnity clause “shall survive the termination of this agreement” and the 1974 agreement provided that it “contains the entire understanding between [the parties] ” and that it “supersedes all prior and contemporaneous understandings or representations” between them, the court looked to the intent of the parties and said:
We therefore hold that the parties did not intend, by the 1974 agreement, to extinguish KFC’s right to indemnification for transactions already completed under the 1972 agreement, . . .
Id. at 249.
The appellant concedes that “a contract of indemnity is to be construed in accordance with the rules for the construction of contracts generally.” Arkansas Kraft Corporation v. Boyed Sanders Construction Co.,
In the present case there is no question that appellant Koppers agreed to indemnify appellee MoPac “against any and all claims, demands, suits, judgments, losses and expenses incident to, or in any way connected with the Contractor’s [Koppers’] operations under this agreement and howsoever arising. . . .” The intent to indemnify is clear enough and the parties stipulated that the only issue for the trial court, to decide was whether MoPac’s right to indemnification “survived the termination of the 1962 agreement between the parties.”
The appellant cites Jones v. Sun Carriers, Inc.,
Harvey Jones filed suit against Sun seeking a declaratory judgment that he was not required to indemnify Sun for the dioxin contamination. The trial court granted Jones’ motion for summary judgment and the Eighth Circuit Court of Appeals affirmed. The appellant in the present case contends that the Eighth Circuit Court’s reasoning is applicable here and that it leads to the conclusion that Koppers is not obligated to indemnify MoPac in the present case.
We do not agree with appellant’s interpretation of the Sun Carriers case. Although the Eighth Circuit Court cited two cases for the statement that, “[generally, no claim arises under an indemnity agreement until a specific demand is made for something as а legal right or until notice of a lawsuit is given,” the court then said: “Here, no potential plaintiffs had made any claims against Sun or JTL by the cutoff date.”
Obviously, the Sun Carriers case involved a different situation from the case at bar. Here, the contract between the parties required Koppers to indemnify MoPac for losses and expenses “incident to, or in any way connected with” Koppers’ operations under that сontract; however, the contract did not have a specified cutoff date within which claims for indemnity had to be made. Loss or expense was sustained by MoPac because of an injury sustained by an employee of Koppers while the agreement between Koppers and MoPac was in effect. Even though the employee did not file suit against MoPac until after MoPac terminated its agreement under which Koppers treated crossties, bridge timbers, and оther wood materials, we think the trial judge was correct in holding that MoPac’s obligation to the employee, which it settled, was an “expense incident to” or “connected with” Koppers’ operations under the agreement while it was in force.
Affirmed.