193 Ind. 219 | Ind. | 1923
This was originally an action by appellee’s decedent and his partner to recover the reasonable value of work done under a contract with A. J. Yawger and Company in clearing, grubbing and grading the railroad right of way of the appellant traction company, and to. foreclose a mechanic’s lien on the right of way and railroad built thereon, for the amount due from A. J. Yawger and Company for such work. One partner having died, the action was continued in the name of the surviving partner until he died; when a supplemental complaint was filed by his administrator, substituted by order of court as plaintiff. On proper request, the court made a special finding of facts, and stated conclusions of law thereon in favor of appelleé, on which judgment was rendered in its favor, as administrator, against A. J. Yawger and Company, for $12,896.81, together with a decree foreclosing a. mechanic’s lien for that amount against the railroad of the appellant traction company, and ordering it sold to
The firm of appellee’s decedents were subcontractors under A. J. Yawger and Company, who were subcontractors under W. H. Schott Company, which had a general contract with the appellant traction company for the construction and completion of the railroad. The traction company alone has perfected an appeal, and the amount due appellee from A. J. Yawger and Company is fixed by the judgment. But the traction company reserved separate exceptions, filed a separate motion for a new trial, and has assigned errors separately.
The general contract between the traction company and W. H. Schott Company w'as dated June 16, 1911, and consisted of a written proposal by the latter to complete the interurban railway for $320,000, as per specifications which it recited were attached thereto and by reference made part thereof, the money to be paid as the work progressed, up to ninety-five per cent, of said contract price, and the acceptance of such offer by the traction company. This contract fixed no time limit within which the work or any part of it should be completed, but at the end of the proposal, following a “detail of estimate” therein set out, was the following: “Said entire construction herein provided for to be furnished, done and performed within the time and in accordance with the terms and provisions of this agreement, and upon completion to be delivered to purchaser free from all material, labor or other liens, except such as may be placed thereon by purchaser, its successors and assigns.”
The subcontract of Joseph and Ricards stipulated that a monthly estimate of the work done should be made, and ninety per cent, of the amount earned should be paid to them within five days after the contractors
It will, be observed that the contract between the owner and the principal contractor provided only that the work should be performed in accordance with the terms of such agreement, “and upon completion to be delivered to purchaser free from all material, labor or other liens, except such as may be placed thereon by purchaser, its successors and assigns.” It contained no express covenant that liens should not be filed pending
Appellant cites and relies on the case of Baldwin, etc., Works v. Edward Hines Lumber Company (1919), 189 Ind. 189, 125 N. E. 400, 127 N. E. 275, 13 A. L. R. 1059. But it is not in point. In that case, the contract between the principal contractor and owner contained the following stipulation:
“No contractor, subcontractor, materialman, or other person furnishing labor or materials for the work herein provided for, or any alteration or additions thereto, shall have any right to file any mechanics’ lien, or claim of any sort or kind against the premises, or any part thereof.” The court there held that the language quoted was binding on the subcontractor (see Acts 1921 p. 135, §8295 Burns’ Supp. 1921, since enacted), and barred his right to acquire a mechanics’ , lien.
But a different rule applies where the principal contractor has merely bound himself to deliver the building or works free from liens, upon its completion. Smalley v. Gearing (1899), 121 Mich. 190, 79 N. W. 1114, 80 N. W. 797; Gray v. Hickey (1917), 94 Wash. 370, 162 Pac. 564; Howarth v. Chester City Presbyterian Church (1894), 162 Pa. 17, 29 Atl. 291; Davis v. LaCrosse Hospital Assn. (1904), 121 Wis. 579, 99 N. W. 351; Advance Terra Cotta Co. v. Moran (1917), 207 Ill. App. 17.
In the case first cited, the subcontractor was held entitled to a lien where the principal contract stipulated as follows: “The building or works must be delivered up free of all mechanics’ liens or other claims chargeable to the contractor.” Smalley v. Gearing, supra.
In the next case, the court held that the appellant was not precluded from enforcing a mechanic’s lien by a stipulation that the contractor “agrees to do all of said
In the next case, the court held that a subcontractor could hold a lien,.and that it was reversible error to give an instruction that he could not, where the contract between the owner and the principal contractor provided that final payment should be made “when the entire contract is • completed and delivered to said (owner) with release of all liens,” and that the principal contractor “hereby agrees to deliver the said building all complete as aforesaid, * * * free from the claims of mechanics and materialmen and all claims whatever.” Howarth v. Chester City, etc., Church, supra.
In the next case, a lien in favor of the principal contractor was upheld and judgment was . ordered in his favor where the contract stipulated for delivery of the completed building “free from all claims, liens and charges,” on or before a date named, and provided that, after payment of certain installments of the contract price, the reserved amount should be paid when the contract was completed and the architect was satisfied that the building was, in fact, free from all liens. Davis v. LaCrosse Hospital Assn., supra.
In the next case, it was held that the principal contractor was not precluded.from enforcing a lien on a building by a stipulation in his contract “to complete same free and clear of any liens or incumbrances.” Advance Terra Cotta Co. v. Moran, supra.
All of these cases recognized the rule of law that a builder may waive the right of himself and those claiming under him to the lien given by statute, where the statute imposes no restriction on this right, and that he does so by expressly agreeing that
The stipulation in the contract under consideration in the case at bar that the work of construction should be done according to agreement, and “upon completion to be delivered to purchaser free from all material, labor and other liens,” was not such a clear and unambiguous agreement not to permit any liens to be acquired as will bar the enforcement of appellee’s lien.
Appellant complains that the trial court overruled its motion to require the plaintiff to pay certain costs adjudged against it before proceeding with the action. Such a motion is addressed to the sound legal discretion of the court to which it is presented, and it is not made to appear that the court abused its discretion in this matter. -
No error is shown to have been committed by permitting the surviving partner of the plaintiff firm to continue the action as such surviving partner after the death of his coplaintiff, nor in ordering that his administrator be substituted upon the filing of a supplemental complaint alleging that such surviving partner had died.
Mere insufficiency in form of the demurrer to a pleading is not cause for reversing the judgment, if the pleading to which it was addressed was bad. Duffy v. England (1911), 176 Ind. 575, 584, 96 N. E. 704; Board v. Crone (1905), 36 Ind. App. 283, 290; Pattie v. State, ex rel. (1921), 75 Ind. App. 233, 130 N. E. 241.
The judgment is affirmed.