Kohlbeck v. Reliance Const. Co., Inc.Kohlbeck v. Reliance Const. Co., Inc.
¶ 1. Jill and Jeffrey Kohlbeck sued the Wisconsin Department of Transportation (DOT) and Reliance Construction Company, Inc., alleging that a highway construction project supervised by DOT and performed by Reliance damaged their property. DOT filed a motion to dismiss for failure to state a claim. The circuit court granted the motion, concluding alternatively that the Kohlbecks could not state a claim under Wxs. Stat. § 88.87 (1999-2000)
1
because they had failed to ask for equitable relief in their complaint and because, regardless of the sufficiency of their complaint, they had an adequate legal remedy under Wis. Stat. ch. 32. In addition, the court concluded that the
¶ 2. We conclude that the Kohlbecks have stated a claim under
Factual Background and Statutory Overview
¶ 3. In the Spring of 1997, the State of Wisconsin began a road construction project on Highway 8 in Dunbar. The State repaved the highway, widening the lanes and creating a curb. DOT was responsible for designing and constructing the highway. The Kohlbecks own a gas station and reside along a portion of Highway 8 that underwent construction.
¶ 4. The Kohlbecks served a notice of injury on DOT in November 1999. They claimed that the State was negligent in its design, supervision, and maintenance of the construction project, and as a result, they suffered damages. The record does not indicate what action, if any, the State or DOT took at this time in relation to the Kohlbecks' notice.
¶ 5. The Kohlbecks filed this lawsuit in July 2000, naming both DOT and Reliance Construction Co., Inc., the company that performed the construction project, as defendants. The Kohlbecks again alleged that DOT was negligent in its design, construction, inspection, and supervision of the project. More specifically, they alleged that the construction project diverted surface and ground water to their property, causing environmental contamination. In addition, they claimed that
¶ 6. DOT filed a motion to dismiss, arguing that
Whenever any county, town, city, village, railroad company or the department of transportation has heretofore constructed and now maintains or hereafter constructs and maintains any highway or railroad grade in or across any marsh, lowland, natural depression, natural watercourse, natural or manmade channel or drainage course, it shall not impede the general flow of surface water or stream water in any unreasonable manner so as to cause either an unnecessary accumulation of waters flooding or water-soaking uplands or an unreasonable accumulation and discharge of surface waters flooding or water-soaking lowlands. All such highways and railroad grades shall be constructed with adequate ditches, culverts, and other facilities as may be feasible, consonant with sound engineering practices, to the end of maintaining as far as practicable the original flow lines of drainage. Thisparagraph does not apply to highways or railroad grades used to hold and retain water for cranberry or conservation management purposes.
¶ 7. The essence of this provision is that DOT is prohibited from "imped[ing] the general flow of surface water or stream water in any unreasonable manner."
Id.
When DOT fails to follow this requirement, an injured property owner "may bring an action in inverse condemnation under ch. 32 or sue for such other relief, other than damages, as may be just and equitable" if DOT fails to remedy the problem on its own.
¶ 8. The circuit court granted DOT'S motion to dismiss. The court agreed with DOT that
A. Standard of Review
¶ 9. We review de novo a circuit court's decision granting a party's motion to dismiss for failure to state a claim. In determining whether a party has stated a claim, we are concerned only with the legal sufficiency of the complaint.
Lane v. Sharp Packaging Sys., Inc.,
B. Relief Requested in Complaint
¶ 10. As noted above, a plaintiff alleging that DOT has injured him or her by unreasonably impeding the flow of water in constructing or maintaining a highway "niay bring an action in inverse condemnation under ch. 32 or sue for such other relief, other than damages, as may be just and equitable."
¶ 11. DOT acknowledges that the Kohlbecks' complaint seeks injunctive relief but then suggests that there is no injunctive relief to be had. In its brief and citing to the Kohlbecks' amended complaint, DOT writes: "It is undisputed that plaintiff-appellants repaired the highway to their satisfaction on their own initiative prior to this suit." Because the Kohlbecks have already fixed everything that needs fixing, DOT argues, the Kohlbecks cannot request any further in-junctive relief. %
¶ 12. This is a mischaracterization of the Kohl-becks' complaint. First, although the Kohlbecks' complaint alleges that they installed a higher curb line to
¶ 13. The circuit court concluded alternatively, and DOT also argues on appeal, that the Kohlbecks may not seek injunctive relief because they have failed to meet the necessary requirements for obtaining such
¶ 14. These common law requirements may be modified by statute.
See County of Columbia v. Bylewski,
¶ 15. Although we agree that these are the general requirements for obtaining a permanent injunction, we disagree that the Kohlbecks' suit must be dismissed at the pleading stage because they have failed to show an injunction is necessary to prevent future injury or that they have no adequate remedy at law. The Kohlbecks must be given an opportunity to prove that an injunction is necessary to prevent future harm; they were not required to do this in their complaint.
¶ 16. It is also too soon to tell if the Kohlbecks have an adequate remedy at law. The circuit court pointed to Wis. Stat. ch. 32, which provides for inverse condemnation actions and is an authorized remedy under
¶ 17. DOT argues incorrectly that we held in
Negus v. Madison Gas & Elec. Co.,
¶ 18. It may be that the Kohlbecks' injuries are adequately compensable in damages, but we must give them an opportunity to prove otherwise. If the Kohl-becks are continuing to suffer harm as a result of DOT's negligence, then damages under Wis. Stat. ch. 32 may not be adequate. But none of this can be decided at the pleading stage, when no facts have been developed. Admittedly, the Kohlbecks' complaint is not clear regarding exactly how DOT's past conduct continues to harm them. But both we and the supreme court have continually emphasized that notice pleading is not a "game of skill in which one misstep by counsel may be decisive of the outcome."
Korkow v. General Cas. Co. of Wisconsin,
¶ 19. After concluding the Kohlbecks were barred from seeking injunctive relief, the circuit court determined that the Kohlbecks' complaint should be construed as seeking relief under
¶ 20. We first note that, even if we agreed with the circuit court that the Kohlbecks' had failed to state a claim under
¶ 21. The solution to the venue issue, however, is not as easy as a venue transfer to the county where the Kohlbecks' property is located, as directed by
¶ 22. DOT suggests that the propriety of venue in Marinette County need not be decided because the Kohlbecks have failed to state a claim under
¶ 23. The standard for determining a violation under
¶ 25. Although the Kohlbecks could theoretically have initiated separate actions in both counties, given both the practical difficulties of trying the claims separately and the interest in judicial economy, it would be an erroneous exercise of discretion for a court in that situation to deny a motion for a change in venue in the interests of justice under
D. Takings Claim
¶ 26. In their amended complaint, the Kohlbecks alleged: "The actions of [DOT] have resulted in a taking of the Plaintiffs private property for public use pursuant to [DOTJ's powers of eminent domain." The circuit court dismissed the Kohlbecks' takings claim, concluding that
¶ 27. We agree with the Kohlbecks that
¶ 28. The Kohlbecks have stated a claim for relief under
By the Court. — Judgment reversed and cause remanded with directions.
Notes
All references to the Wisconsin Statutes are to the 1999-2000 version unless otherwise noted.
DOT also initially argued that the Kohlbecks' notice of claim was defective, but the circuit court concluded that DOT had abandoned this argument. DOT does not challenge that ruling on appeal, or otherwise assert that the Kohlbecks failed to comply with notice requirements.
DOT also cites to
Stern v. Credit Bureau of Milwaukee,
We also note that
Wisconsin Stat.
We also need not decide how Reliance Construction Co. affects the venue analysis. Because venue is not jurisdictional, it can be waived.
See