Koch Industries, Inc. v. United StatesKoch Industries, Inc. v. United States
I. Introduction
The government appeals the district court’s decision that taxpayer-appellee Koch Industries, Inc. was entitled to use the percentage-of-completion method of accounting under
II. Background
Taxpayer-Appellee Koch Industries, Inc. (“Koch”) is a corporation organized under the laws of the state of Kansas. During the period at issue, Koch was the common parent of an affiliated group of corporations and filed consolidated federal income tax returns on behalf of itself and its affiliated group of corporations. In 1995, Koch created Koch Performance Roads, Inc., to market higher cost, longer lasting roads made of a new polymer-modified asphalt. To offset the higher initial construction costs, Koch offered extended warranties to customers. In its vision statement, Koch explained its willingness to extend fifteen- to twenty-year warranties on its roads as follows,
The Performance Road objective is to provide a road with lower life cycle costs. Agencies currently spend less on initial construction and then incur greater maintenance and reconstruction expense. A Performance Road would spend more on initial construction but would incur far less maintenance and reconstruction expense leading to lower life cycle costs. It is typical to find that the breakeven point between these alternatives will occur around year 12. Therefore, in order to provide value to the customer, the warranty period typically needs to exceed 14 years.
The SH44 project was divided into two phases, a construction phase and a rehabilitation phase. Koch’s obligations during the rehabilitation phase were governed by two contracts: (1) a “Pavement Warranty,” that required Koch to perform all work necessary to assure performance of the pavement 1 ; and (2) a “Structures Warranty,” that required Koch to perform all work necessary to assure performance of the structures (bridges, drainage, and erosion structures). 2 Neither warranty agreement required New Mexico to show any design defects to give rise to Koch’s obligation to repair or replace pavement or structures. Instead, both warranties included detailed performance criteria which SH44’s pavement and structures were required to meet. Although it was virtually certain that some work would have to be done at some point in time under the warranty agreements, Koch had no obligation to perform any work on the highway unless and until the highway and/or structures thereon failed to meet the performancestandards included in the warranty agreements.
The Pavement Warranty divided the term of the warranty into four periods and listed the minimum acceptable criteria corresponding to each particular period of time. The Pavement Warranty provided up to a 21.5-year warranty term for the segments of the highway.
3
A number of the performance criteria, such as those pertaining to rut depth, delamination, and pot holes, remained constant over the entire warranty term. The performance criteria pertaining to smoothness, cracking, and depressions, however, became less stringent with the passage of time, indicating the parties did not intend the road to
Koch received $46,753,000 for its construction phase services and $62,000,000 under the warranties covering the rehabilitation phase. 6 Section 11.11 of the Corridor Agreement required $39,000,000 of the warranty price to be allocated to pavement reconstruction costs. However, that section also explicitly stated this allocation “in itself shall create no legal liability upon [Koch] to spend any sums under the Agreement or Warranty” and emphasized that the terms and conditions of the Corridor Agreement, Pavement Warranty, and Structures Warranty were to govern the parties’ obligations during the rehabilitation phase.
Koch used the percentage-of-completion method of accounting provided for in
The district court granted summary judgment for Koch and concluded Koch was entitled to refunds of $339,520 for 1998, $1,972,187 for 1999, $1,294,515 for 2000, and $16,596,092 for 2001, plus interest. The court concluded the warranties were long-term construction contracts to which the percentage-of-completion method could apply. The court then concluded neither of the agreements were true warranties, and the regulation did not preclude Koch’s use of the percentage-of-completion method to report the $62 million payment it received in consideration for extending the two warranties.
III. Analysis
Both parties moved for summary judgment on the issue of whether it was appropriate for Koch to use the percentage-of-completion method set out in
The interpretation of a federal statute, such as
Section 451 of the Code generally requires that “any item of gross income shall be included in the gross income of a taxpayer for the tax year in which the item is received by the taxpayer, unless, under the accounting method used by the taxpayer in computing taxable income, the item is properly accounted for as of a different period.”
Under
Income not attributable to long-term contract activities “generally must be taken into account using a permissible method of accounting other than a long-term contract method.”
Id.
§ 1.460-1(d)(1). An exception, however, exists for non-long-term contract activities “incident to or necessary for” the completion of a long-term contract.
Id.
Examples of such non-long-term activities provided by the Regulations include “the provision of architectural, design, engineering, and construction management services, and the development or implementation of computer software.”
Under the undisputed facts of this case, neither the Pavement Warranty nor the Structures Warranty are long-term contracts under
Neither warranty agreement required Koch to perform “manufacture, building, installation, or construction” to fulfill its contractual obligations. Rather, both warranties included detailed performance standards which SH44’s pavement and structures were required to meet, many of which were lowered with the passage of time. Although it was virtually certain that some work would be performed at some point during the warranty period, Koch had no obligation to perform any work on the highway unless and until the highway and/or structures thereon failed to meet the performance standards included in the warranty agreements. 8 Indeed, the contracts explicitly stated that Koch is not obligated “to spend any sums under the Agreement or Warranty” and emphasized that the terms and conditions of the Corridor Agreement, Pavement Warranty, and Structures Warranty were to govern the parties’ obligations during the rehabilitation phase.
Prior to entering into the warranties, Koch created'preliminary financial models in an effort to assess their profitability. According to one of its managers, Koch’s liabilities under the warranties depended on “the ultimate pavement design, the ultimate quality of construction, the ultimate quality of the materials used, the traffic and loading of that traffic and the weather conditions.” Koch forecasted it would spend between $17,493,180 and $94,010,183 to fulfill its obligations under the warranties. However, Koch’s manager testified these projections were based on “future events that cannot be predicted.” The undisputed facts demonstrate there was a lack of certainty regarding what specific long-term construction work, if any, would be necessary to fulfill Koch’s obligations under the warranties. As a result, the warranties are not “long-term contracts” for the purpose of
Non-long-term contract activity means the performance of an activity other than manufacturing, building, installation, or construction, such as the provision of architectural, design, engineering, and construction management services, and the development or implementation of computer software. In addition, performance under a guaranty, warranty, or maintenance agreement is a non-long-term contract activity that is never incident to or necessary for the manufacture or construction of property under a long-term contract.
Id.
The regulation’s statement that “performance under a guaranty, warranty, or maintenance agreement is a non-long-term contract activity” applies beyond the context of activities incident to or necessary for the completion of a long-term contract and forecloses warranty income from long-term contract treatment under
Although the Regulations do not define the terms “guaranty, warranty, or maintenance agreement,” this phrase must be interpreted to harmonize with the objectives of
That the warranties may have been separately negotiated and executed, involved a lengthy warranty period, were expensive, could require Koch to perform work regardless of whether the road was defective, and involved a virtual certainty that some warranty work would be performed does not foreclose them from being within the scope of the terms “guaranty, warranty, or maintenance agreement.” In its modern usage, the term warranty is not limited to warranties against manufacturing defects. Rather, it extends to warranties for future performance that guarantee a product will perform at a certain level for a stated period of time.
See, e.g., Liberty Lincoln-Mercury, Inc. v. Ford Motor Co.,
In its agreements, Koch unmistakably warranted SH44’s pavement and structures would meet certain criteria, and that it would repair or replace them to the extent necessai-y to bring them into compliance with the agreed upon criteria. Koch did not unconditionally obligate itself to perform any specific construction services. Instead, it offered New Mexico a performance warranty covering its work on SH44. Under the Regulations, this type of contingent activity is “a non-long-term contract activity that is never incident to or necessary for the manufacture or construction of property under a long-term contract.”
Based on a review of the record, there are no disputes of material fact relevant to either the question of whether the warranties are long-term contracts under § 460 or whether they fall within the scope of the terms “guaranty, warranty, or maintenance agreement.” The district court erred in granting summary judgment in favor of the taxpayer. Instead, summary judgment in favor of the government is appropriate.
IV. Conclusion
For the foregoing reasons, the court holds that the undisputed facts demonstrate Koch was not entitled to use the percentage-of-completion method of accounting under
Notes
. The Pavement Warranty states:
PDC warrants that during the term of this Warranty the Pavement shall meet the Pavement Performance Criteria. If at any time during the term of this Warranty any portion of the Pavement described in the Pavement Performance Criteria shall fail to meet the applicable Pavement Performance Criteria, PDC, shall Repair or Replace the Pavement to the extent necessary to cause such portion of the Pavement to meet the Pavement Performance Criteria.
. The Structures Warranty states:
PDC warrants that during the term of this Warranty the Structures shall meet the Structures Performance Criteria. If at any time during the term of this Warranty any of the Structures shall fail to meet the Structures Performance Criteria, PDC shall Repair or Replace the Structure to the extent necessary to cause it to meet the Structures Performance Criteria.
. The exact term of pavement warranty was dependent on SH44's rate of completion and use. The warranty remained in effect until the earlier of: (1) 20 years after substantial completion of the last segment, (2) 21.5 years after substantial completion of a particular segment, or (3) the end of the calendar year in which the equivalent standard axle loads ("ESALs”) for a particular segment reached or exceeded 4,000,000.
. For example, Koch warranted that SH44’s smoothness, as measured through the International Roughness Index ("IRI”) in meters per kilometer, would be no worse than 1.25 m/km during the first period, 1.70 m/km during the second period, 2.10 m/km during the third period, and 2.50 m/km during the final period. IRI measures a standard vehicle's accumulated suspension motion over a particular section of road.
. The Structures Warranty remained in effect until the earlier of: (1) 11.5 years after substantial completion of the first segment, or (2) the end of the calendar year in which the ESALs for a particular segment reached or exceeded 2,000,000.
. A total of $420,000,000 of federal funding was allotted to the project.
.
. Koch touted the low maintenance costs of its Performance Road concept, claiming "[a] Performance Road would spend more on initial construction but would incur far less maintenance and reconstruction expense leading to lower life cycle costs.” Koch reeognized that the “breakeven point” between a conventional road and a Performance Road "occurred] around year 12” of the road’s life cycle, and that it was therefore necessary for "the warranty period typically ... to exceed 14 years.”
. Section 1.460 — 1(d) provides an exception allowing long-term contract methods to be used to account for non-long-term activities which are "incident to or necessaiy for” the completion of a long-term contract. In briefing the question of whether the warranties at issue are stand-alone long-term contracts, Koch emphasized it was not claiming the warranties were “incident to or necessaiy for” the completion of the underlying contract for the construction of SH44. Nevertheless, discussion of