249 F. 181 | 7th Cir. | 1917
Lead Opinion
While several counts were filed in this action, counsel agree that, the common counts and another count on the contract having been expressly abandoned, the trial proceeded on the amended first additional count. In this count plaintiff alleged the execution of a written contract to furnish the material and labor
. While the count does not state that the moneys so expended were the reasonable outlays of the plaintiff in the performance of the contract, the omission of this allegation could not be taken advantage of on motion in arrest of judgment or on writ of error. Any defect in this respect was cured by the verdict. The declaration furthermore states sufficient grounds for plaintiff’s abandonment of the contract. Persistent refusal to pay installments due under a building contract, under the circumstances alleged in this declaration, amount to a renunciation on the part of the owner and justified abandonment of further performance; for obstruction to performance need not be physical. Actions such as those alleged are just as effective in absolving the other party from any further readiness or offer to perform as a condition to the enforcement of the liability to answer for the damages sustained by reason of the breach. Phillips & Colby Construction Co. v. Seymour, 91 U. S. 646, 23 L. Ed. 341; Dobbins v. Higgins, 78 Ill. 440; Keeler v. Clifford, 165 Ill. 544, 46 N. E. 248; National Tool Co. v. Standard Shoe Machinery Co., 181 Mass. 275, 63 N. E. 900.
“The claim in the case at bar is limited to compensation for the work actually done in an effort to cany out the contract. This work can only be measured by the contract price, and any other value regarding it is wholly immaterial. The contract provides no special price covering the alleged work and material i'nrnishod under the contract in the case at bar. Therefore its value could only be determined from evidence showing what work and material had been furnished, and what it would cost to complete the building; in other words, evidence from which tlie value of the labor and nuworial done and furnished could be determined, as based upon the contract, price.”
The parties are agreed that the contract is single. While payments were to he made monthly as the work progressed, the contract itself, furnished no basis for the separate items entering into the work. We need not, therefore, consider what the true measure of damages would he after such a breach, if the contract were divisible, or if a schedule of prices to he paid for each article forming part of the subject-matter were specified in the contract itself. But defendant’s deduction, that in a contract such as this plaintiff can recover only the profit, if any, that he lias been prevented from earning by reason of the breach, is contrary both to principle and to authority.
A substantial breach during the progress of the work justifying the abandonment by the other party gives rise either to an action for the damages sustained through the breach or to a quantum meruit. If the latter form he pursued, the measure of damages is the fair value, of tlie work and labor performed and the materials furnished, with a conflict in the authorities as to whether or not schedule prices when specified in the contract should limit the recovery. But if a plaintiff not in default — and one who is justified in abandoning further work is not thereby in default — -sues for the breach of the contract, he may, at his option, specify and claim as his damages either the profit which he has thus been prevented from earning or his actual outlays reasonably made in the performance of the contract plus the profits, if any, which he would have made if he had not been prevented from continuing to perform the contract.
It may well be that ordinarily there is no, or no substantial, difference in the result, because, ordinarily, an owner does not prevent further performance of a contract the carrying out of which would be unprofitable to the contractor. It may, however, happen, as defendant in the instant case claims, that such prevention is to tlie contractor’s benefit, that if he had been permitted to, carry out his contract his loss on the whole job would have equaled or exceeded the outlays made up to the time of the owner’s breach, so that, if the sole specification of damages were 'the loss of . profits, and the proof established no such loss, but, on the contrary, a gain, the plaintiff would get only nominal damages.
If, however, plaintiff specifies as his damages the outlays actually and reasonably incurred either with or, as in the instant case, without
3. While the evidence was conflicting, clearly there was sufficient to sustain the averments of the declaration. We deem it unnecessary to consider in detail the numerous assignments of error. While some evidence may have been improperly admitted, the error resulting therefrom was, in our judgment, entirely harmless. The testimony of the statements of tire architect as to the statements made to him by the owner, while not admissible as evidence that the owner made the statements, were nevertheless admissible as statements of the reason that governed the architect’s wrongful action.
Judgment affirmed.
Rehearing
On Petition for Rehearing.
In the petition for rehearing, it is again strongly urged that at best only the proportionate value of work done, in its relation to the entire work and on the basis of the entire contract price, can be recovered. To give the contractor his outlays reasonably incurred, might, it is urged, enable him in some cases to recover more than the entire contract price for an incomplete job.
As to whether or not the contract price is the maximum that in any event could be recovered, we express no opinion, because the facts in the ease before us require none; and for the same reason, we express no opinion as to the proper measure of damages if a contract specifies fixed amounts for specific materials or labor, or provides for definite payments at successive times or stages of the work, deemed by the ' parties, either expressly or impliedly, as full compensation for so much as shall then have been completed, nor where, as is not here the case, the work has so far progressed that it is practicable to determine with reasonable definiteness what proportion of the entire work contracted for remains undone. Here the price of $56,500 was for the entire job; payments were to' be made as the work progressed, but the contract fixes no basis for the amounts to be paid. After the foundation had been laid and considerable material delivered, defendant wrongfully stopped further work. We held that under these circumstances, the minimum measure of damages, whatever the form of action, is the outlay reasonably incurred1 in the course of due performance of the obligation.
The petition for rehearing is denied.