301 Mass. 340 | Mass. | 1938
This is a petition, described in the petitioners’ bill of exceptions as one “for the assessment of damages” for an alleged diversion on and after September 15, 1935,
The petitioners excepted to the refusal of the judge to give certain requests for rulings. These requests, in effect, seek to raise the question that the construction of the tunnel with fixed openings was unauthorized, and that St. 1926, c. 375, and St. 1927, c. 321, did not permit the taking of water by percolation. St. 1927, c. 321, under the provisions of which the tunnel was constructed, provides in § 4, among
It follows that it was not open to the petitioners under their petition to recover damages alleged to have been caused by unauthorized acts of the commission. The requests for rulings were not applicable to the issue that was tried, and there was no error in the refusal to give them.
Exceptions overruled.