OPINION
These consolidated cases have their genesis in temporary reductions made by the Department of Interior’s Bureau of Reclamation (the Bureau) on the use, for irrigation purposes, of the water resources of the Klamath Basin of southern Oregon and northern California. In their amended complaints, plaintiffs aver that the Bureau’s actions effectuated, alternatively, a takings and a breach of contract. Previously, this court held that plaintiffs’ interests in the use of Klamath Basin water did not constitute cognizable property interests for purposes of the Takings Clause, and, therefore, that plaintiffs were not entitled to compensation under the Fifth Amendment. Klamath Irr. Dist. v. United States,
I. BACKGROUND
This court’s prior opinion fully describes the factual background of this litigation and held that the facts listed therein would be deemed established for purposes of future
A.
The plaintiffs in these consolidated actions are 13 agricultural landowners and 14 water, drainage or irrigation districts (the irrigation districts) in the Klamath River Basin area of Oregon and northern California. They receive, directly or indirectly, water from the Klamath Project irrigation works constructed and operated by the Bureau pursuant to the Reclamation Act of 1902, ch. 1093, 32 Stat. 388 (codified, as amended, at 43 U.S.C. §§ 371 et seq.) (the Reclamation Act). The Reclamation Act gives the Secretary of the Interior (the Secretary) legal authority to reclaim arid lands in certain states through irrigation projects. Once land has been so claimed, the Department of the Interior, through the Bureau, is responsible for constructing reclamation projects and for administering the distribution of water to agricultural users. See Reclamation Act, §§ 2-10, 32 Stat. 388-90. The original terms of the Reclamation Act permitted the United States to enter into irrigation contracts with individual homesteaders, but, as a result of several amendments, current law provides that the United States may only enter into new water distribution contracts with organized irrigation districts. 43 U.S.C. §§ 423(e), 485h(d).
The Klamath River Basin, naturally a semi-arid region, is the site of extensive water reclamation and irrigation projects constructed pursuant to the Reclamation Act. See Bennett v. Spear,
The Endangered Species Act (ESA), compels the Bureau, like all federal agencies, to ensure that its operation of the Klamath Project is not “likely to jeopardize the continued existence of any endangered species.” 16 U.S.C. § 1536(a)(2). Under the ESA, the Bureau is required to perform a biological assessment “for the purpose of identifying any endangered species which is likely to be affected” by the operations of the Klamath Project. 16 U.S.C. § 1536(c)(1). If the Bureau determines that its proposed action may affect an endangered or threatened species, it must request a “formal consultation” with the National Marine Fisheries Service (NMFS) or the Fish and Wildlife Service (FWS), in response to which the appropriate agency will produce a biological opinion. See 16 U.S.C. §§ 1536(a)(2), 1536(b); 50 C.F.R. § 402.14. If that opinion concludes that the proposed action is likely to jeopardize a protected species, the Bureau must modify its proposal to alter that result.
For decades, Klamath Basin landowners generally received as much water for irrigation as they needed. In severe drought
B.
The distribution of Klamath Project water is governed, in part, by contracts between the individual irrigation districts and the Bureau, which set forth, inter alia, the districts’ respective priorities to water use within the Project in the event of a water shortage, and the United States’s resultant liability therefor. The Bureau recognizes three basic types of contracts for reclamation water, designated, in descending order of priority, as “Class A,” “Class B,” and “Class C,” respectively.
Class A contracts are entered into pursuant to Section 9(d) of the Reclamation Act, under which irrigation districts that receive deliveries of water from the Project are obligated to pay a proportionate share of the Project’s initial construction costs and its annual operation and maintenance costs. See 43 U.S.C. § 485h(d). As exemplified by the Tulelake Irrigation District contract, these districts typically have a contractual right to receive “all water needed by the District for beneficial irrigation uses,” and in times of a water shortage, the right of the district to water is “equal to those of others executing similar contracts under the Reclamation Act ... and shall be prior to those rights conferred pursuant to contracts executed under ... the Warren Act.” Plaintiffs Tulelake Irrigation District and Klamath Irrigation District both have such “Class A” contracts with the Bureau.
One of the Class A contracts, that of Van Brimmer Ditch Company (VBDC), has first priority to irrigation water from the Project. VBDC was the first entity to contract with the Bureau for Klamath Project water, and by the terms of its original contract, was subject only to priorities established prior to reclamation by the United States and not to any priority of the United States or any party claiming through the United States. In 1922, VBDC’s contract was superceded when the United States entered into a contract with the Klamath Irrigation District (KID), under which KID assumed liability for the annual cost of carrying and delivering water to VBDC. Klamath Irr. Dist.,
Class B contracts are entered into pursuant to the Warren Act, Ch. 141, 36 Stat. 925, codified at 43 U.S.C. § 523, which permits the Secretary to contract for Project water to the extent that it has excess storage or carrying capacity. The Warren Act makes clear that these Class B contracts must “preserv[e] a first right to lands and entrymen under the project,” id., that is, to Class A contract holders. Accordingly, when there is no excess capacity, water is not provided to
Class C contracts are entered into with individual farmers for rental water on an “if and when available” status. They have third priority of use, and are the first to be deprived of water in the event of a shortage. None of the plaintiffs in this case have such contracts.
In all the contracts but that with VBDC, the United States expressly disclaims liability for water shortages attributable to drought. For example, in this regard, the Klamath Irrigation District contract states—
On account of drought or other causes, there may occur at times a shortage in the quantity of water available in Project reservoirs and, while the United States will use all reasonable means to guard against such shortage, in no event shall any liability accrue against the United States or any of its officers, agents, or employees for any damage, direct or indirect, arising therefrom____
Most of the other district contracts have identical provisions, while a few have similar provisions that do not include the phrase “or other causes” in the first line of the above quote.
C.
This litigation arose not long after the Bureau issued its revised operation plan on April 6,2001, in which it terminated altogether the delivery of irrigation water to plaintiffs.
In September 2003, plaintiffs filed a motion for partial summary judgment seeking a determination that their interests in Klamath Project water were not property interests at issue in an ongoing state-law adjudication of rights proceeding in Oregon state courts. On October 3, 2003, defendant filed a cross-motion for summary judgment on the issue of the nature and scope of plaintiffs’ property interest in Klamath Project water and the question whether that interest was a compensable property interest for purposes of the Takings Clause of the Fifth Amendment. On November 13, 2003, this court, by unpublished order, granted plaintiffs’ motion for partial summary judgment, but did not resolve defendant’s outstanding cross-motion. Shortly thereafter, on January 27, 2004, plaintiffs filed a cross-motion for summary judgment on the issues of the nature and scope of their property interest, and whether
This case was transferred to the undersigned on December 9, 2004. On January 11, 2005, plaintiffs were permitted to file a second amended complaint, in which they reduced their damages claim. On February 28, 2005, the court granted a motion to intervene filed by the Pacific Coast Federation of Fishermen’s Associations. See Klamath Irr. Dist. v. United States,
As a result of this ruling, plaintiffs are left only with their claims for breach of contract. The water districts seek damages on their own behalf for breach of their contracts with the United States, while the landowning plaintiffs seek damages as beneficiaries of the district plaintiffs’ contracts. On February 17, 2006, defendant filed a motion for summary judgment. Extensive briefing on that motion has been completed. After carefully considered the briefs of the parties and their respective positions, the court concludes that oral argument is unnecessary.
II. DISCUSSION
Following the court’s prior opinion, one question remains—did the Bureau breach the subject contracts? The court previously made several observations in this regard, which provide a helpful starting point.
A.
First, the court observed that, under most of the district contracts, plaintiffs did not have an absolute contractual right to water, limited, as claimed, only by appurtenancy and beneficial use. “This is particularly true,” the court concluded, “as to those contracts which provide, either in exact or similar terms, that the government shall not be liable for “water shortages’ resulting from ‘drought or other causes.’” Klamath Irr. Dist.,
As it turns out, however, the court need not resolve these questions. Instead, they serve merely to frame the court’s consideration of what turns out to be the controlling issue here, to vnt, whether the contracts must be read to imply that the United States reserved its ability to exercise its sovereign powers without the threat of liability for failing to deliver water.
B.
1. This court previously observed that “even as to the contracts that do not contain broad water shortage clauses, it is at least arguable that any reductions ordered by the Bureau here did not result in a
The Supreme Court first recognized the sovereign acts doctrine in Horowitz. There, the Court found no breach of contract where a wartime embargo on certain railroad shipments interfered with a contractor’s receipt of a shipment from a government agency. It reasoned that “the United States when sued as a contractor cannot be held hable for an obstruction to the performance of the particular contract resulting from its public and general acts as a sovereign.” Id. at 461,
The two characters which the government possesses as a contractor and as a sovereign cannot be thus fused; nor can the United States while sued in the one character be made hable in damages for their acts done in the other. Whatever acts the government may do, be they legislative or executive, so long as they be public and general, cannot be deemed specially to alter, modify, obstruct or violate the particular contracts into which it enters with private persons.
Horowitz,
2. The ESA “contains a variety of protections designed to save from extinction species that the Secretary of the Interior designates as endangered or threatened.” Babbitt v. Sweet Home Chapter of Communities for a Great Oregon,
The findings provision of the statute emphasizes that this and other provisions of the ESA were passed because Congress found that “various species of fish, wildlife and plants in the United States have been rendered extinct as a consequence of economic growth and development untempered by adequate concern and conservation” and that such species “are of esthetic, ecological, historical, recreational, and scientific value to the Nation and its people.” 16 U.S.C. §§ 1531(a)(1), (3). Congress added that the development and maintenance of conservation programs is “key to meeting the Nation’s international commitments and to better safeguarding, for the benefit of all citizens, the Nation’s heritage in fish, wildlife and plants.” Id. at § 1531(a)(5). Similar sentiments were echoed in the statute’s purposes clause, see id. at 1531(b), as well as in its legislative history, making it amply clear that the ESA was enacted with the broadest possible public purposes in mind.
While the court must be vigilant to ensure that action designed to benefit the government is not couched in “vocabulary of the public weal,” McGrath v. Rhode Island Retirement Bd.,
Based on the foregoing, it thus would appear preliminarily that the sovereign acts doctrine applies here, absolving defendant of any breaches that might otherwise have arisen when, as a result of the ESA, it failed to deliver irrigation water in 2001.
C.
Plaintiffs, however, mount a multi-front attack on this proposition.
1. Their first thrust asserts that the Bureau was not compelled by the ESA to diminish water deliveries in 2001. This claim, however, runs headlong into the host of rulings construing the ESA that essentially dic
Later, in May of 2000, the PCFFA and others filed a lawsuit challenging the Bureau’s plan to release water for irrigation, claiming that the agency had violated the ESA by failing to consider the impact of its plan on threatened coho salmon. The Klamath Water Users Association (KWUA) intervened in this action as a defendant. On April 3, 2001, the United States District Court for the Northern District of California found that the Bureau had failed to comply with the requirements of the ESA before implementing its 2000 operations plan for the Klamath Project. PCFFA,
the Bureau of Reclamation hereby is enjoined from sending irrigation deliveries from Klamath Project whenever Klamath River flows at Iron Gate dam drop below the minimum flows recommended in the [NMFS] report, until such time as the Bureau completes a concrete plan to guide operations in the new water year [2001], and consultation concerning that plan is completed, either by (1) formal consultation to a “no jeopardy” finding by the NMFS, or (2) the Bureau’s final determination, with the written concurrence of the NMFS, that the proposed plan is unlikely to adversely affect the threatened coho salmon.
Id. at 1250. On April 6, 2001, three days after this injunction was issued, the FWS and the NMFS issued their 2001 biological opinions, which concluded that the low flow levels proposed by the Bureau for 2001 were likely to jeopardize the continued existence of coho salmon and suckers, and adversely modify their habit. On that same date, the Bureau issued its 2001 operations plan, which incorporated the conclusions and flow recommendations contained in the biological opinions.
Subsequently, several of the irrigation districts, the KWUA and others filed suit in the United States District Court for the District of Oregon, challenging the 2001 operating plan as violative of their contractual rights to irrigation water and seeking an order enjoining the Bureau from implementing the plan and instead requiring it to “release unspecified ‘historic’ amounts of irrigation water.” Kandra,
Accordingly, in 2000 and 2001, the Bureau was caught in a crossfire of lawsuits, sued both parties seeking to preclude and to compel the release of irrigation water. The former won out, as the courts concluded that the ESA compelled the Bureau to reduce irrigation deliveries in 2001. Compare Precision Pine & Timber,
2. Again all but treating these eases as nonevents, plaintiffs would have this court revisit the issues addressed by these courts, contending, inter alia, that numerous alternatives to shutting down water deliveries were available to the Bureau and that, in particular, the decision to withhold water was not supported by sound biological science. But, this court must decline this open invitation to leap outside the realm of government contract law for at least two reasons.
First, while plaintiffs argue that the prior eases are not binding precedent, they seemingly overlook the fact that many of the plaintiffs herein also were involved in the prior litigation, making the rulings in those cases binding under the doctrine of res judicata. Under that doctrine, also known as “claim preclusion,” “a judgment on the merits in a prior suit bars a second suit involving the same parties or their privies based on the same cause of action.” Parklane Hosiery Co., Inc. v. Shore,
Second, even to the extent this is not the ease, the court rejects the notion that this contract case should be a vehicle for challenging the provenance and ultimate validity of every action taken by the Bureau and other Federal agencies leading up to and including the application of the ESA here. Under the Administrative Procedures Act, 5 U.S.C. §§ 702 et seq., those actions were reviewable—indeed, were reviewed—under a
But are such broad inquiries really relevant to the question at hand? Must the court, in order to apply the sovereign acts doctrine, consider the entire course of conduct that led up to the application of statute or, perhaps, even all the actions that led up to the passage of the statute itself, so as to determine that the United States had no other alternative but to violate the contract terms? Certainly, no decision has employed this tour d’horizon approach to the sovereign acts doctrine, despite ample opportunities to do so. Instead, the decisions have approached cautiously questions regarding what “caused” a sovereign act to occur. For example, in Derecktor v. United States,
As a matter of judicial economy, predictability and precedent, plaintiffs’ argument leaves much to be desired. Their backward-looking approach threatens to convert every invocation of the sovereign acts doctrine into a far-reaching, de novo examination of agency or even Congressional conduct, likely putting this court in the position of having to second guess decisions rendered by other courts. Their approach would deprive defendant of any predictability in taking truly sovereign acts without fear of contract liability. If plaintiffs are correct, an agency riveted upon the public good, and unmotivated whatsoever by any desire to reheve itself of any contractual obligations, would still be subject to liability unless it could show that, over an extended period of time, perhaps spanning multiple Administrations, it could have chosen no path that would have avoided the sovereign act that violated the contract. Of course, in making this contention, plaintiffs disregard the possibility that these earlier actions themselves qualify as sovereign acts that would also be protected by the doctrine. Indeed, they do not assert that the Bureau or any other Federal agency failed to adopt the cited ameliorative steps with some view toward eventually violating the contracts or otherwise because of self-interest. Rather, they would predicate liability here based upon an extended concept of negligence (perhaps approaching strict liability) that hinges on a healthy dose of 20-20 hindsight—that the Bureau failed to appreciate and adopt, prior to 2001, alternatives which, if executed, would have avoided the breaching application of the ESA. But, no authority—certainly, nothing that plaintiffs cite—■ suggests that the sovereign acts defense, and, correspondingly, defendant’s liability in contract, should hinge on such captious considerations.
D.
Relatedly, plaintiffs next assert that the act which must be sovereign here is not the passage of the ESA, but rather the agency’s application of that statute to their contracts. They contend that the latter actions “targeted” their contracts and should not qualify as sovereign acts. This claim, however, again fundamentally misconceives the nature of the sovereign acts defense. First, the critical focus here must be on the extent to which the ESA compelled the agency to act. If, as concluded above, the statute left the agency with little alternative but to deny water, it makes little sense legally to focus on the individual application of the law, rather than its passage, in applying the sovereign acts doctrine.
It is further obvious that, in performing this analysis, the court should avoid semantics. While the sovereign act doctrine sometimes is framed as excluding actions that “target” a contract, the latter phrase, despite plaintiffs’ claims, neither reflects any metonymic logic nor subsumes every action directed at a contract or taken by the government with knowledge thereof. The question instead is why a particular action is taken. If the violation of a contract occurs owing to
E.
1. Lastly, plaintiffs asseverate that, even if applicable, the sovereign acts defense does not necessarily excuse defendant’s nonperformance here, as defendant has not shown that it meets the common law test for impossibility of performance. There is certainly decisional support for this analysis. Thus, the plurality in Winstar clearly felt that the sovereign acts doctrine was merely a prelude to the application of a common law impossibility defense:
As Horowitz makes clear, that defense simply relieves the Government as contractor from the traditional blanket rule that a contracting party may not obtain discharge if its own act rendered performance impossible. But even if the Government stands in the place of a private party with respect to “public and general” sovereign acts, it does not follow that discharge will always be available, for the common-law doctrine of impossibility imposes additional requirements before a party may avoid liability for breach. As the Restatement puts it,
“[wjhere, after a contract is made, a party’s performance is made impracticable without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his duty to render that performance is discharged, unless the language or the circumstances indicate the contrary.” Restatement (Second) of Contracts § 261.
____Thus, since the object of the sovereign acts defense is to place the Government as contractor on par with a private contractor in the same circumstances, Horowitz,267 U.S., at 461 [,45 S.Ct. 344 ] ... the Government, like any other defending party in a contract action, must show that the passage of the statute rendering its performance impossible was an event contrary to the basic assumptions on which the parties agreed, and must ultimately show that the language or circumstances do not indicate that the Government should be hable in any ease.
Winstar,
But, the portion of the plurality’s opinion quoted above did not enjoy the support of five justices and thus is not binding.
2. For starters, with all due respect, Horowitz plainly enunciated an independent defense to government liability, not one subservient to the separate application of a common law impossibility defense. The latter defense is neither mentioned nor even obliquely referenced in the one-page opinion in Horowitz—an observation made by Chief Justice Rehnquist in his dissent in Winstar. See Winstar,
Treating the sovereign act doctrine as a prelude to a common law impossibility de
Grafting the sovereign acts doctrine onto a common law impossibility defense thus largely deprives the former of its raison d’etre— enabling “the government to serve the public and respond to crises without fear of liability for the incidental effects its actions may have on its wide range of contracts.” “The Sovereign Acts Doctrine After Winstar,” supra, at 130; see Deming,
3. For these many reasons, the court concludes that there is no callus bridge between the scion of the sovereign acts doctrine and the stock of the traditional common-law impossibility defense. Rather, Horowitz, as well as a more than a dozen cases pre- and post-dating that decision, establish that if the sovereign acts doctrine is applicable, the government is not hable for contract violations caused by a sovereign act, unless the unmistakability doctrine is triggered. With all due respect, the plurality opinion in Winstar neither alters this conclusion nor upsets the phalanx of binding precedent from which it springs. Here, as plaintiffs readily admit, there are no unmistakable terms in any of the contracts precluding the government from exercising its sovereign powers—indeed, the water shortage clauses in most of the contracts reflect the opposite intent. Instead, plaintiffs assert that any silence of the contracts on this point should be read in their favor, as precluding the United States from enforcing the ESA. That claim, however, is decidedly contrary to the law regarding the unmistakability doctrine and, indeed, would turn that doctrine on its head. See Winstar,
Finding the remainder of plaintiffs’ arguments unpersuasive, the court, therefore, concludes that sovereign acts occurred here that prevented defendant from performing under the contracts and that no breach of the contracts at issue occurred.
III. CONCLUSION
This court need go no farther. Based on the foregoing discussion, the court GRANTS defendant’s motion for summary judgment. The Clerk is hereby ordered to dismiss the complaints in question, with prejudice.
IT IS SO ORDERED.
Notes
. The ESA directs the Secretary of the Interior or the Secretary of Commerce to suggest "reasonable and prudent alternatives” when consulted about Federal activities that might adversely affeet endangered species. See Tulare Lake Basin Water Storage Dist. v. United States,
. See Tulelake Irrigation District contract, art. 26; Klamath Drainage District contract, art. 24; Sunnyside Irrigation District contract, art. 9; Klamath Basin Improvement District contract, art. 4; Malin Irrigation District contract, art. 11; Westside Improvement District No. 4/Colonial Realty Company contract, art. 13; Shasta View Irrigation District contract, art. 11. Others of the contracts contained water shortage clauses that are somewhat different from that in the Klamath District contract. See Poe Valley Improvement District contract, art. 11; Midland District Improvement Company contract, art. 5; Enterprise Irrigation District contract, art. 10 Pine Grove Irrigation District contract, art. 10
. Plaintiffs concede that defendant released 70,-000 acre-feet of Klamath Project water to users in July of 2001, but assert that this water came too late to allow them to grow crops.
. Subsequently the reasoning of this court was adopted by a California appellate court, see Allegretti & Co. v. County of Imperial,
. Commenting on this same inquiry, the plurality in Winstar stated—
[G]overnmental action will not be held against the Government for purposes of the impossibility defense so long as the action’s impact upon public contracts is, as in Horowitz, merely incidental to the accomplishment of a broader governmental objective. The greater the Government’s self-interest, however, the more suspect becomes the claim that its private contracting partners ought to bear the financial burden of the Government’s own improvidence, and where a substantial part of the impact of the Government's action rendering performance impossible falls on its own contractual obligations, the defense will be unavailable.
. On brief, plaintiffs cite Sierra Club v. Babbitt,
. An action "jeopardize[s] the continued existence" of a species when the action "reasonably would be expected, directly or indirectly, to reduce appreciably the likelihood of both the survival and recovery of a listed species in the wild by reducing the reproduction, numbers, or distribution of that species.” 50 C.F.R. § 402.02. An action results in "destruction or adverse modification” when the action results in a "direct or indirect alteration that appreciably diminishes the value of critical habitat for both the survival and recovery of a listed species.” Id. As noted in the statute’s legislative history, section 7 "requires the Secretary and the heads of all other Federal departments and agencies to use their authorities in order to carry out programs for the protection of endangered species, and it further requires that those agencies take the necessary action that will not jeopardize the continuing existence of endangered species or result in the destruction of critical habitat of those species.” H.R.Rep. No. 93-412, at 14 (1973); see also Hill,
. See S.Rep. No. 93-307, at 1 (1973), U.S.Code Cong. & Admin.News 1973, pp. 2989, 2990 ("The purpose of this bill is to provide for conservation, protection and propagation of endangered species of fish and wildlife by Federal action and by encouraging the establishment of State endangered species conservation programs.”); id. at 2 ("It has become increasingly apparent that some sort of protective measures must be taken to prevent the further extinction of many of the world’s animal species.... Consideration of this need to protect endangered species goes beyond the aesthetic [and includes] the
. The policy section of the ESA does state that "[i]t is further declared to be the policy of Congress that Federal agencies shall cooperate with State and local agencies to resolve water resource issues in concert with conservation of endangered species.” 16 U.S.C. § 1531(c). While this statement certainly indicates that Congress was aware that the ESA could impact water resources—after all, the statute was designed to protect fish—there is no indication that Congress considered the impact of the statute on the Bureau’s water delivery contracts.
. Several other cases have held that the rights to irrigation water of the Klamath Irrigation District and the Tulelake Irrigation District "are subservient to ESA and tribal trust requirements.” Kandra,
. Cf. Franconia Assocs. v. United States,
. Both Federal courts and the Restatement (Second) on Judgments recognize that an entity that expressly or impliedly gives a party authority to represent it may be bound by the rule of res judicata as though it were a party. See, e.g., Collins v. E.I. DuPont de Nemours & Co.,
. Among the dozen or so steps that plaintiffs assert the Bureau should have taken in the decade or so prior to 2001 are: (i) instituting a water bank; (ii) compensating landowners for land idling; (iii) providing for groundwater substitution; (iv) instituting a conservation implementation program designed to promote fish recovery; (v) constructing screens and dam passages to protect suckerfish and enable them to migrate upstream to spawn; (vi) looking for water savings in other federal projects within the Klamath Basin (e.g., the Klamath Marsh Wildlife Refuge); (vii) promoting well-drilling and water conservation; and (viii) taking other steps that "could have ameliorated the water shortage in 2001."
. Indeed, the facts in Derecktor certainly suggest that there would have been room to debate whether the action taken by the State Department truly would have prejudiced foreign relations, as the transfer was prohibited because of concerns that the ship would be used to transfer Jews to Palestine. Nor did the court consider whether the State Department could have taken different actions before the Maritime Commission entered into the contract, so as to avoid the problem encountered.
. Thus, in Walter Dawgie Ski Corp. v. United States,
This Court finds, however, that the sovereign acts doctrine, if applicable, applies to all aspects of the Government act____Here, as the plaintiff admits, the reconstruction and improvement of the General Hitchcock Highway constitutes a sovereign act. As such, all the corresponding facets of that Government action likewise comprise a sovereign act. If this Court allowed the plaintiff to attack a single aspect of the action, such as the road closure schedule, this disintegration of the doctrine would subvert the justification for the precept. What would be next: where the engineers choose to locate the highway, when the majority of construction or demolition should take place, how the excavation crew should prosecute the blasting, or what process to use in transporting fill? While facially dubious, in challenging the daytime road closure schedule, the plaintiff in fact seems to challenge all of these aspects of the highway construction process. This Court, however, denies the plaintiff the opportunity to dissect this sovereign act. The subject road reconstruction and improvement comprise a sovereign act of public and general nature, as even admitted by the plaintiff, and this Court finds no authority for reviewing every minor decision that is made in implementing the sovereign act at issue.
Id. at 133.
. It is worth noting that, earlier in this case, plaintiffs seemingly took the position that the ESA dictated the Bureau's action. Thus, in previously seeking partial summaiy judgment herein, plaintiffs asserted that it was uncontroverted that the biological opinions issued by FWS and NMFS in 2001 "prohibited Reclamation from delivering water to plaintiffs in accordance with historical practices on the ground that it was ‘likely to jeopardize the continued existence’ of the Lost River and Shortnose sucker fish and the coho salmon.” Such statements might well be viewed as "admissions on file” within the meaning of RCFC 56(c), so as to preclude plaintiffs from raising factual issues as to the same claims now, see Woods v. City of Chicago,
. While plaintiffs assert that the Bureau had ample discretion not to follow the biological opinions, the main case that they cite for that proposition, Bennett v. Spear,
. As described by Professor Schwartz—
In addition, the plurality reads preconditions into the sovereign acts doctrine that are traditionally associated with the common law impossibility doctrine applicable to private contracts. These include: (1) a requirement that the possibility of regulatory interference by governmental action must not have been foreseeable by the contracting parties and (2) a caveat that the sovereign acts doctrine creates only a rebuttable presumption that the government is immunized from liability for breach of contract arising from public and general regulatory change.
Joshua Schwartz, "The Status of the Sovereign Acts and Unmistakability Doctrines in the Wake of Winstar: An Interim Report,” 51 Ala. L.Rev. 1177, 1191-92 (2000).
. See Precision Pine,
. Although the Federal Circuit has never directly dealt with this question, the decisional law unanimously holds that an opinion that does not draw the support of a majority of voting justices is not precedential. See, e.g., Texas v. Brown, 460
. Justices Stevens and Breyer joined Justice Souter's full plurality opinion, while Justice O’Connor joined the opinion with the exception of two sections addressing the issue of whether the Financial Institutions Reform, Recovery, and Enforcement Act of 1989, Pub.L. No. 101-73, 103 Stat. 183 (1999), constituted a "public and general” act of the sovereign. Winstar,
. Indeed, the Supreme Court, in the year after Horowitz was decided, affirmed a decision of the Fourth Circuit, in which the latter applied the sovereign acts doctrine without any reference to the impossibility defense. See Maxwell v. United States,
. A long and unbroken line of cases from the old Court of Claims and the Federal Circuit, many of which arose during or shortly after the Second World War, applied the sovereign acts defense without any mention or hint of the impossibility defense. See, e.g., Atlas Corp. v. United States,
. See, e.g., Amino Bros. Co. v. United States,
. Dicta in the recent decision of this court in Stockton East Water Dist. v. United States,
. Various cases holding that the common law impossibility requirements must be met mistakenly cite older Court of Claims cases for the proposition that the sovereign acts doctrine is designed to treat the government like a private individual, with the latter able to invoke the common law impossibility defense. In fact, the early cases suggest a different rationale to the sovereign acts defense—that a private individual would not be liable if the government passes a statute that prohibits performance and that the government should fare no worse simply it is a defendant in a contract action. Summarizing these older cases, the Court of Claims, in O’Neill v. United States,
From its earliest days, however, application of the sovereign act doctrine has proceeded from the recognition that in governing the country, the Government's actions, otherwise legal, will occasionally incidentally impair the performanee of contracts. Were those contracts exclusively between private parties, the party hurt by such governing action could not claim compensation from the other party for the governing action. Given the large number of contracts the Government enters, its contracts will sometimes be affected by those same governing acts. The policy underlying the sovereign act doctrine is that in those circumstances, the Government in its contracting role, like its private counterpart, should not incur liability for its act done in the governing role.
Id. at 826 (emphasis in original); see also Jones,
. To appreciate this, consider Justice Scalia’s exegesis on how the sovereign acts and unmistakability doctrines interact—
[I]t is reasonable to presume (unless the opposite clearly appears) that the sovereign does not promise that none of its multifarious sovereign acts, needful for the public good, will incidentally disable it or the other party from performing one of the promised acts.... Governments do not ordinarily agree to curtail their sovereign or legislative powers, and contracts must be interpreted in a common-sense way against that background understanding.
Winstar,
