150 Minn. 436 | Minn. | 1921
In the purchase of material for the construction of a large factory building on his premises plaintiff applied to defendant for a supply of the necessary quantity of cement for use in the walls and floor of the structure., Negotiations resulted in the purchase from defendant of the required quantity, and it was subsequently delivered upon the premises of plaintiff and used for the purposes stated. After the construction had come well under way, the main floor and parts of the walls were found weak, defective and inadequate by reason of the fact, as claimed by plaintiff, that the cement used therein, and so supplied by defendant, was of a poor and inferior quality and wholly unfit for the particular purpose, and had to be torn down and rebuilt at a considerable cost and expense. R. reason of this, plaintiff claims to have suffered damage in the sum of $4,000, and he brought this, action to recover the same. The basis of the action, as stated in the complaint, is that defendant represented and warranted the cement as good in quality and fit and suitable for the use intended, upon which plaintiff relied in making the purchase. Defendant interposed by answer, in addition to a denial of the alleged warranty, a counterclaim for the value of the cement and for the foreclosure of a mechanic’s lien therefor which had been filed against the property.
At the close of the trial defendant moved the court for a directed verdict for the amount of its asserted lien, which was denied. Thereupon all the issues were submitted to the jury with the result that plaintiff had a verdict for $2,621. Defendant appealed from an order denying its alternative motion for judgment or a new trial.
The assignments of error, challenging the rulings of the court in the admission and exclusion of evidence and in the instructions and refusals
The case of Liljengren F. & L. Co. v. Mead, 42 Minn. 420, 44 N. W. 306, cited by defendant is not in point. That action involved a breach of contract to deliver window-sash and frames for use in the construction of a building, and defendant’s answer to an action to recover the purchase price thereof, alleging damage occasioned by the delay of plaintiff in the delivery of-the material as required by the contract, was held defective in not alleging that like sash and frames could not have been procured elsewhere and the delay thus avoided; the damage there claimed was the loss of the use of the building. „ The rule does not apply to the case at bar, for here the cause of the delay was not discovered until the cement had been used, and the poor quality thereof was not known for some time thereafter.
It is finally urged that deduction in plaintiff’s recovery should have been made by the jury to the extent of the value of the cement of good
This covers the ease and all that need be said in disposing of the appeal. The complaint states a cause of action, the evidence supports the verdict and the record presents no reversible error. The court did not err in overruling the objection to evidence of the payment of $97.50 on the purchase price of the cement. The payment was admitted by the answer of defendant. It was proper evidence at the stage of the case when objected to, and was not again, so far as we discover from the record, referred to on the trial. If counsel were of opinion that the amount thereof should be deducted from plaintiff’s recovery, request to that effect should have been made at the time of the charge to the jury; the attention of the court should have then been called to the matter. That was not done.
Order affirmed.