Kitkas v. Windsor Place Corp.Kitkas v. Windsor Place Corp.
Ordered that the order is reversed, on the law, and the motion of the second third-party defendant/third third-party defendant, Boca Electric Corp., for summary judgment dismissing all causes of action for contribution and common-law indemnification asserted against it is granted; with one bill of costs payable to the appellant.
On January 22, 2003, the plaintiff was performing electrical work on a construction project in Long Island City and allegedly was injured when an electrical panel exploded. At the time of the accident, the plaintiff was employed by the second third-party defendant/third third-party defendant, Boca Electric Corp. (hereinafter Boca).
In support of its motion for summary judgment dismissing all causes of action for contribution and common-law indemnification asserted against it, Boca met its burden of demonstrating that the plaintiff‘s injuries to his right hand did not constitute a “grave injury” within the meaning of
The remaining contentions of the plaintiff and the defendant/third-party plaintiff/third third-party plaintiff either are without merit or are improperly raised for the first time on appeal. Dillon, J.P., Florio, Miller and Austin, JJ., concur.