215 Mich. 668 | Mich. | 1921
For 75 cents an hour and 3 per cent, of the value, commonly called a bonus, plaintiff agreed to superintend the building of several houses for defendants. When the work was partially completed, trouble arose between the parties and their relations ended. Plaintiff sued for the percentage, claiming $867. He had verdict and judgment for $525.41.
Defendants, assigning error, say:
1. That the court erred in allowing an amendment
Seemingly, the claim of the defendants that plaintiff had breached the contract led plaintiff’s counsel at the conclusion of, the proofs to ask an amendment of the declaration by adding the common form of quantum meruit count. When defendants’ counsel objected, the court said :
“Under the provisions of the judicature act, I think I am obliged to grant the motion to amend the declaration. Do you care to offer any additional proof under this count, before the case is submitted to the jury?”
and defendants’ counsel replied:
“No, we prefer to stand on the pleadings as they were and not in any way obscure the issue.”
That the amendment was necessary for a recovery by plaintiff we need not determine. Its allowance cannot be said to be reversible error. See Lian v. Bradford & Co., 209 Mich. 172, and cases cited.
2. That there was error in the charge. The plaintiff’s claim in his declaration and bill of particulars was for the percentage on the work done, compensation at the contract price, and the evidence in his behalf was in support of such claim. To the instruction
“And in addition thereto, he would be entitled to recover for the loss of profit, if any, which he sustained by reason of the defendants’ refusal to permit him to complete the houses which he had started under orders received from the defendants.”
This was error, and. we cannot say that it was not prejudicial to defendants. As the case must go back for a new trial, other questions should be considered.
Each side claimed a breach of contract. In his charge the trial court sought to explain plaintiff’s right of recovery as affected by these conflicting claims, and the instructions are said to be erroneous. The following is so characterized:
“In case you find that the plaintiff breached the contract, nevertheless, plaintiff should be entitled to the credit of three per cent, upon the finished houses and upon such proportion of the unfinished houses as had been built at the time he was ordered to leave, if he was ordered to leave.”
But there was further instruction:
“Now, I say to you, gentlemen, that all of these several claims of the defendants are for your consideration. It is for you to determine whether or not defendants have suffered loss and damage because of plaintiff’s conduct and if you find that defendants have suffered loss and damage, then they are entitled to a judgment against plaintiff for the amount of that loss and damage.
“In arriving at your verdict, if you find a judgment in favor of plaintiff for some amount and should also find a judgment in favor of 'defendants for some amount, then you will off-set the amount found in favor of the one against the amount found in favor of the other and rénder a judgment in favor of the party who shall have a balance due after offsetting the one claim against the other.
“If the claim of plaintiff shall be fully off-set by the*672 claim of defendants and there is no balance in favor of either, then your verdict will be, as the court already advised you, one of no cause of action. If you find a balance in favor of the defendants, then your verdict will be for the defendants, naming the amount.”
If the plaintiff did not breach the contract, under the evidence he was entitled to the percentage claimed. If he did breach the contract, as against defendants’ claim for damages arising from the breach, he was entitled, on the quantum meruit, to credit and compensation for the services rendered not exceeding the contract price, being under the evidence the said peri centage on the work done, and if such credit exceeded the said damages of defendants, plaintiff was entitled to judgment. See Allen v. McKibbin, 5 Mich. 449. It does not seem to be questioned that the percentage represented the fair value of plaintiff’s services not exceeding the contract price, but the proof should be specific as to the value of the work done, for which compensation is sought. The jury should not be permitted to speculate on the value of the houses, completed or partially completed. But we quote again from the charge:
“I advise you further that if you find that plaintiff breached this contract, then he cannot recover, for it is not the policy of the law that one can make a contract and then breach it and then claim damages because of the breach, and so in this case, if the contract relations between the plaintiff and the defendants terminated because of the wrongful act of the plaintiff or because he breached the contract, then he cannot recover.”
Of this instruction, requested by the defendants, they may not complain. It was not favorable to plaintiff. One may not profit by his own wrong, have damages because of his breach of contract, but, as we have seen, a! plaintiff may be entitled, on the quantum
Plaintiff’s counsel says that if in the excerpt from the charge last above quoted the word “recover” in each instance had been followed by the word “damages,” it would not be objectionable. But plaintiff sought recovery only for the percentage on the work done, and, though contending that defendants breached the contract, he claimed judgment for the percentage only.
An instruction respecting the right to recover upon an implied contract was given. This was not required under the proofs.
For the error pointed out, the judgment is reversed, with costs to defendants. New trial granted.