Kirk v. United StatesKirk v. United States
These consolidated appeals are from money judgments which were awarded by
Prior to the commencement of the tests the FAA announced that it would pay for any damages caused by its sonic booms. In fact, the FAA set up a claims program through the Department of the Air Force under the Military Claims Act (10 U.S.C § 2733) for the purpose of processing claims flowing from sonic booms. Numerous of these claims were paid. Many others were determined to be invalid and were rejected.
A large number were filed in federal district court under the Federal Tort Claims Act,
The cases which are before us on appeal were filed in court after the running of the two-year statute of limitations applicable to the Federal Tort Claims Act. Becausе of this fact the cases were considered under the Tucker Act,
The suits on behalf of Frey and Kirk were filed under both the Federal Tort Claims Act and the Tucker Act. The case on behalf of Cox was brought under the Tucker Act only. Similar suits were filed and were disposed of by Judge Bohanon who granted the government’s motion to dismiss based upon his prior decision in Bennett v. United States,
The government here moved to dismiss on the basis that the plaintiffs were barred from recovery under the Federal Tort Claims Act by the two-year statute of limitations and, further, that there could be no recovery under the Tucker Act since there had been no taking of property.
The government concedes that in order to win public acceptance of the testing program, the FAA announced at the outset that it would pay for damages caused by sonic booms and it repeated this announcement of policy in conjunction with the defense of an injunction case filed in state court by citizens claiming that they had no adequate remedy under the Federal Tort Claims Act. The mentioned injunction was granted, and subsequently the case was removed to the federal district court, where the injunction was vаcated and the action was dismissed for lack of jurisdiction. This latter decision was reversed by this court in Coxsey v. Hallaby,
The question presented then is whether a litigant claiming that his property was injured as a result of a series of high altitude tests at speeds in excess of the speed of sound producing sonic booms has a remedy under the Tucker Act either on the theory that there was a taking of his property by the govеrnment contrary to the Fifth Amendment of the Constitution of the United States or, in the alternative, whether the representation of government agents just prior to the commencement of the tests that it would pay damages resulting from injuries to property arising in connection with the mentioned activity constituted a contract, express or implied, giving rise tо a claim under the Tucker Act.
I
The facts of this case do not lend themselves to a conclusion that there was a taking of property in violation of the Fifth Amendment to the Constitution of the United States. The guiding lights in this determination are the decisions of the Supreme Court in United States v. Causby,
In Causby the flights were at low levels and were so repeated and permanent as to constitute the imposition of a servitude on the land; thus, there was an effective taking of property interests of the land owner farmers whose chickens were lost as a result of fright. Furthermore, the occupants of the house were deprived of sleep and suffered ill health as a result of the activity. The Court in Causby recognized that the owner of land has limited rights to control the air space above his property. The Court also recognized that there need not be an actual trespass in order for there to be a taking. The fact that the easement might not have been permanent was not regarded by the Court as a factor which detracted from its being a taking.
The Supreme Court’s later decision in Griggs in essence applied the identical principle. Here the Court recognized the airport’s need for adequate takeoff and landing space and held that where noise from aircraft landing and taking off rendered a home located at the end of the runway unbearable for residential use, there was a taking of an air easement over the property. The county which was responsible for designing the airport was held liable to property owners.
It is clear from a careful examination of Causby and of Griggs that the present judgment cannot be affirmed upon the basis that there was a constitutional taking in accordance with the first faсet of the Tucker Act.
Next we consider whether there was an implied contract, and in this connection it is necessary that it be a contract implied in fact as opposed to one implied in law, commonly called a quasi-contract.
This * * * class consists of obligations arising from mutual agreement and intent to promise but where the agreement and promise have not been expressed in words. Such transactions are true contracts and have some times been called contracts implied in fact. (1 Williston, Contracts, s. 3).
Professor Corbin has said that an implied contract includes those contracts actually intended and tacitly understood. 3 Corbin on Contracts § 563, 1960 Ed. Thus, then, there must be either circumstances or conduct from which it can be inferred that there was a meeting of the minds.
This court has said that the elements of an express and implied contract are the same. The difference between them is оne of proof. The express contract is proven by testimony showing the promise and the acceptance, whereas the implied contract is inferred from the acts of the parties and other circumstances showing an intent to contract. See Woodruff v. New State lee Co.,
The government contends that there was no contract and could be no contract because the agents of the government were not authorized to enter into contracts. However, it is unnecessary — in view of our conclusion that no valid contract was entered into — to determine whether there was such authority. Offhand, it would appear in view of the breadth of the program that suсh authority did exist.
Unquestionably the government stated publicly that it would pay for damage caused by the test program and had there been circumstances manifesting acceptances and a detriment or forbearance suffered in response to the statements of the government, it might be possible to conclude that there was an enforceable contract. The closest that the evidence comes to -something of this nature is the forbearance on the part of some of the people to proceed with injunctive actions. See Coxsey v. Hallaby,
So, therefore, the plaintiffs have not contended, and cannot contend, that they either had an understanding or werе even lulled into a feeling of security whereby they did not file their claims within the two-year period required by law. The fact that the plaintiffs have now filed lawsuits does not constitute any acceptance of an offer on the part of the government. As we view it the government’s conduct was no open ended offer in any event. It was merely an expression that it intended to pay actual damage suffered, following which it set up machinery for the purpose of processing the claims. It did not undertake to entertain them and pay them indefinitely and long after the fact.
Apart, then, from the Tort Claims Act which has, as previously noted, a two-year limitation statute, and the Tucker Act which as has bеen shown does not embrace the damage in question, the government is immune from suit, and it is not possible to fashion a remedy which will permit the plaintiffs to prevail.
Accordingly, the claims are invalid and the judgments must be reversed with directions to vacate the judgments in favor of the plaintiffs-appellees. It is directed that the causes of action be dismissеd.
Notes
. In Gravelle this court described the events out of which the present suit arose:
Beginning February 3, 1964 and continuing through July 30, 1964, controlled test flights of from one to eight were flown daily over Oklahoma City by aircraft flying at supersonic speeds and at altitudes of from 21,000 to 50,-000 feet. The general purpose of the tests was to gain information probing the feasibility of developing supеrsonic commercial aircraft and the particular purpose was to measure structural response to sonic booms as well as “determine the normal reaction of ground population over a significant period of time to sonic boom pressures. * * * ” Eleven test houses in the Oklahoma City area, varying in age from new to 50 yeаrs old, were used in the program. Five of the test houses had instrumentation designed to measure the response of their various structural components to the sonic booms. Instruments were also set up in special stakes driven into the ground to measure and record movement in the earth (“seismic response”) caused by sonic booms. In addition, threе measuring stations were established to measure the overpressure from the sonic booms. One of these measuring stations was located directly under the flight path the test aircraft were to take; the other two were located at five and ten miles distance from the flight path.407 F.2d at 966 .
. § 1346(a) (2) :
Any other civil action or claim against the United States, not exceeding $10,-000 in amount, founded either upon the Constitution, or any Act of Congress, or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.
. The trial court said in pertinent part:
It also seems just as clear that the Tucker Act, Section 1346(a) (2), does grant jurisdiction since none of these claims exceeds $10,000 and they are founded upon either the Constitution,an Act of Congress or upon an express or implied contract with the United States and/or are for unliquidated damages in cases not sounding in tort. The Government had the obligation under the Constitution to pay just compensation. The damage to the property сonstituted a taking within the terms of the Constitution and it may rationably be said that the Government did take that part of the property which it damaged. It appears also that tests were made under the authority of an Act of Congress authorizing the sonic boom tests and if the agreement of the Federal Aviation Authority to pay any damage is not an express contract it is a contract implied in fact. It constituted a promise to pay.
. In Batten v. United States,
. See Knight Newspapers, Inc. v. United States,
See also Goodyear Tire & Rubber Co. v. United States,
. Baltimore & O. R. Co. v. United. States,
. Federal Aviation Program,
. Perhaps generally illustrative of the type of testimony offered is that of Mrs. Inez Vanderlick, found at pp. 229-230 of the Appendix:
Q. Will you state whether or not this was reported to the FAA officials?
A. Yes, it was. There were letters sent to Washington and I received two letters back from them and they were turned in to an attorney and in the meantime I haven’t been able to recover them.
Q. But you did make a complaint?
A. Yes, we did.
Q. Did someone from the Air Force or FAA come out to look at your home?
A. No. They didn’t come out to the house. It was a letter you received from the government. You were supposed to send the estimates in. They were done by Billings Lumber Company and Francis T. Smith, and I don’t believe either one of them are any more operative.
Q. Did someone from the government come out and look at your house?
A. I don’t remember that. I believe there were.
No effort was made to determine why Mrs. Vanderlick did not follow up the initial contact. The excerpt here quoted is the entire testimony given by this plaintiff having to do with her relations with the Government in any wise; it is, if anything, more comprehensive than that of the other plaintiffs.