Ernst Ludwig KIPP, Appellant,
v.
Sigrun KIPP, Appellee.
District Court of Appeal of Florida, Fourth District.
*692 Elliot H. Scherker and Julissa Rodriguez of Greenberg, Traurig, P.A., Miami, for appellant.
Joel M. Weissman of Joel M. Weissman, P.A., Doreen M. Yaffa, P.A., Denise Calegan Desmond, P.A., West Palm Beach, for appellee.
DAMOORGIAN, DORIAN, Associate Judge.
Appellant, Ernst Ludwig Kipp ("former husband") timely appeals the "Final Judgment on Former Wife's Application For Contempt on Paragraph 4D and Exhibit A-1 of Marital Settlement Agreement Incorporated into Final Judgment." We disagree with the lower court and reverse.
The trial court entered a final judgment of dissolution of marriage, specifically incorporating a marriage settlement entered into between the parties. The agreement provided in paragraph 4D that as part of the equitable distribution, the former husband was to pay to the appellee, Sigrun Kipp, n/k/a Sigrun Kaliwoda ("former wife"), "[a]n additional sum up to TWO MILLION ($2,000,000) [DOLLARS] in cash at the time that the wife closes on any subsequent parcel of real estate which is used for the primary residence of the children."
Soon after the dissolution, the former wife purchased a house. The parties stipulated that the total purchase price of the house was $970,000.[1] The former husband wired funds in that amount to the former wife. Soon after closing, counsel for the former wife inquired as to whether the former husband had paid the former wife $2,000,000. Counsel for the former husband replied that the amount due under the agreement had been paid.
The former wife filed an application for civil contempt against the former husband for failure to pay the sum of $1,030,000 out of the $2,000,000 allegedly due under paragraph 4D of the agreement.
After a non-evidentiary hearing, the trial court entered a final judgment concluding that paragraph 4D of the contract was clear on its face and that the former husband was obligated to pay the former wife a total of $2,000,000 with respect to her purchase of a residence, regardless of the *693 amount actually paid by the former wife to purchase the residence.
The issue before us is whether the trial court erred, as a matter of law, in its interpretation of the agreement. "The interpretation of the wording and meaning of the marital settlement agreement, as incorporated into the final judgment, is subject to de novo review." McIlmoil v. McIlmoil,
Here, the operative language in the provision in question is the phrase "up to." The phrase "up to" is a phrase of limitation used to set a cap or maximum amount contract. See Enter. Leasing Co. S. Cent., Inc. v. Hughes,
In the context of paragraph 4D the plain meaning of the phrase "up to" leads us to the inescapable conclusion that the phrase set a cap but not the amount the former husband would have to pay for the cost of the house to be purchased by the former wife.
The former wife argues that paragraph 4D does not state that the "up to" limitation correlates to the cost of the home to be purchased and that the words "the cost of the home actually purchased" would have to be added to the provision for the former husband to prevail. This additional modifier would not be necessary after a reading of the plain language of the provision. The term "up to" modifies the amount the former husband would have to pay. The provision implies that the husband could potentially pay $2,000,000 but only "up to" that amount.[2] Contrary to the former wife's argument, a proper reading of the agreement does not require that a modifier be added to the provision.
The fact that both sides ascribe different meanings to the language does not mean the language is ambiguous so as to allow the admission of extrinsic evidence. See Lambert v. Berkley S. Condo. Ass'n,
We, therefore, reverse the final judgment of the trial court ordering the husband to pay $1,024,696.40.
GROSS and MAY, JJ., concur.
NOTES
Notes
[1] In their briefs, the parties rounded off the dollar amounts.
[2] Where the contract is susceptible to an interpretation that gives effect to all of its provisions, the court should select that interpretation over an alternative interpretation that relies on negation of some of the contractual provisions. Inter-Active Servs., Inc. v. Heathrow Master Ass'n, Inc.,