92 Mo. App. 669 | Mo. Ct. App. | 1902
Suit was commenced by the filing of the following complaint in a justice’s court in the city of St. Louis:
“That heretofore, to-wit: on the ninth day of March, 1897, one Lave N. Cross and defendant entered into a contract in writing, by which defendant agreed to pay to the said Lave N. Cross, the sum of two thousand one hundred dollars for service to be rendered as baseball player for the playing season of 1897.
“Plaintiff states it was further provided in an extra stipulation in said contract, that in the event of the manager of the party of the first part (this defendant) certifying at the close of the season of 1897 that said Lave Cross has implicitly obeyed the orders and faithfully performed all the covenants*671 in tlie above contract and totally abstained from late hours and other dissipation, and has, in bis opinion, played first-class ball, then the party of the first part (this defendant) shall pay, in one payment, three hundred dollars extra to said Lave Cross.
■ “Said contract is in possession of said defendant and can not be filed herewith, but a copy thereof is here filed, marked Exhibit ‘A.’
“Plaintiff further states that said Lave N. Cross did implicitly obey the orders and faithfully perform all the covenants of said contract, and did totally abstain from late hours and other dissipation, and did play first-class ball, and thereby became entitled to the said three hundred dollars extra compensation.
“Plaintiff states that at the close of' the playing season -of 1897, said Lave N. Cross demanded the certificate aforesaid from the defendant’s manager, and said manager promised and agreed to give him such certificate, and stated to him that he was justly entitled thereto; but plaintiff says that said manager of defendant, through fear and caprice, and with the intention to fraudulently deprive said Lave N. Cross of said sum of money and to strengthen his own position with his employers, this defendant, withheld said certificate and has since refused to give the same for the reasons aforesaid.
“Plaintiff further says that heretofore, to-wit, on May 16, 1900, by a certain instrument in writing herewith filed, marked Exhibit T3,’ said Lave N. Cross for value received, sold, assigned, transferred, set over and delivered to this plaintiff all his right, title and interest in and to the said three hundred dollars, and the cause of action sued on herein, and this plaintiff is now the assignee and owner thereof.
“Wherefore, plaintiff prays judgment against the said defendant for said sum of three hundred dollars, with inter- ■ est from October 15, 1897, and costs of suit.”
By appeal from the judgment of the justice on the merits,
Defendant introduced evidence tending to prove that Cross did not fulfill the conditions of the contract and was not entitled to the certificate of the manager and the extra pay of three hundred dollars; that he did not play first-class ball; that out of one hundred and thirty-two games played by the club during the season, Cross "only played in eighty:eight of the games; that defendant’s manager did not promise Cross the certificate, but refused to give it to him for the reason that he had not earned it and was not entitled to it under the terms of his contract.
The trial court ruled that the production of the manager’s certificate, called for by the contract, was essential to' plaintiff’s right to recover and instructed the jury to find the issues for the defendant.
On this ruling plaintiff took a nonsuit, with leave to set the same aside. His motion to set aside the nonsuit was overruled, whereupon he appealed.
It would be a paradoxical condition of the law, if, when the parties to a contract agreed to abide by the decision or-opinion of an outside party in regard to the correspondence of the word “done” or “services performed” with the contract, if the party to the contract who had done the work of per-
In the same case, on the second appeal (153 Mo. 499), the Supreme Court said:
“We held then that where parties agree to abide by the decision or opinion of an architect, engineer or commission of any kind, in regard to the correspondence of the work done with the contract, in an action on such contract, the approval of the person selected by both parties to determine this must be averred and proved, but that if the engineer or arbitrator so chosen made no measurement or estimate, or fraudulently neglected and refused to do so, then plaintiff would not be debarred of redress upon proper and appropriate charges of such fraudulent and collusive refusal, or failure, to make such estimate.”
The refusal of the manager of the defendant to give the certificate if Cross was entitled to it, does not deprive Cross of the right to recover his earnings under the contract. Nee
The judgment is reversed and the cause remanded.