210 S.W. 832 | Tex. App. | 1919
On August 28, 1915, J. G. Lea-veil Company, brokers, negotiated a contract between 'the parties to this suit, whereby appellant sold appellee—
“200 bales of cotton linters, mill run, free from trash, being seller’s make, at 3⅛ cents per pound, f. o. b. cars Kingsville, Texas.”
“Shipment. Beginning October, and shipped in car lots as fast as made.”
Only 25 bales were delivered under the contract, and appellee sued appellant for damages on account of the breach, alleging, in substance, that by the terms of the contract appellant was obligated to begin shipping cotton linters in October, 1915, and continue to ship in carload lots as fast as made until the contract was fulfilled; that the average bale of cotton linters was 500 pounds, and that it was so intended by the parties to said contract; that appellant had delivered to plaintiff under said contract 25 bales, but failed and refused to deliver any more; that after due notice, on January 25, 1916, appellee bought 175 bales of linters at 5¾ cents per pound, f. o. b. Texas common points, which was the lowest price at which said linters could be bought; that at said price the difference between the contract price and the market price of said'linters was $2,296.87; that appellant had had a reasonable time and more in which to perform the contract before January 27, 1916, but had failed and refused to do so; that, if it should be held that appellant was entitled to have until the end of the cotton season in which to fulfill the contract, then in such event plaintiff’s damages amounted to $4,000, for the reason that at the end of the season the difference between the contract price and the market price was 2% cents per pound.
Appellant demurred-generally and specially, pleaded the general issue, and specially, in substance, that the contract sued upon was a contract of manufacture and sale; that it was contemplated by both parties that the linters should be manufactured by appellant and shipped to appellee, beginning with the month of October, 1915, and thereafter as fast as made; that in compliance with said contract apjjlllant shipped to appellee, in the month of October, 25 bales, and was prevented from further shipments by circumstances ever which it had no control, to wit, that the electrical power company, which at that time, and for a long time prior thereto, had furnished the power to operate appellant’s mill, and which had been a dependable source of power, broke down suddenly and without
The first assignment is that the court erred in not sustaining appellant’s general demurrer to the plaintiff’s first amended original petition. Appellant’s general demurrer was not urged until after the first supplemental petition was filed. If the original and supplemental petitions, considered together, state a cause of action, the court did not err in its ruling on the demurrer. We think the plaintiff’s pleadings, taken together, show its right to recover. The contention under this assignment is that because the plaintiff’s original petition shows that by the terms of the contract the linters were to be delivered as soon as they were made, and does not by further allegation show that appellant ever made any more than the 25 bales delivered in October, the petition is insufficient; that appellant’s obligation to deliver the remaining 175 bales rested upon the condition that it thereafter made that number.
“The general doctrine that, when a party voluntarily undertakes to do a thing without qualification, performance is not excused by unavoidable accident or other contingency not foreseen, it becomes impossible for him to do the act or thing he agreed to do, is well settled. As*834 a man consents to bind himself so shall he be bound. Where no express or implied provision as to the event of impossibility can be found in the terms or circumstances of the agreement it is a general rule of construction, founded on the absolute and unqualified term of the promise, that the promisor remains responsible for damages notwithstanding the supervening impossibility or hardship.”
Even i£ the words, “as fast as made,” should he construed to be a condition, the same authority (section 1897) declares:
“It is no excuse for the nonperformance of a condition that it is impossible for the obligor to fulfill it, if the performance be in its nature possible.”
6 R. C. L. p. 998, § 365, states the rule in this language, with reference to implied conditions ' excusing nonperformance:
“But when it is admitted that implied conditions in an absolute contract may excuse performance, when performance has become impossible, the question whether subsequent impossibility is an excuse for nonperformance seems to become one of construction. Viewing the subject in this way, the conclusion reached in some modern decisions seems to be at variance with the rule as stated in the early English decisions. It has been said that the words of a mere general covenant will not be construed as an undertaking to answer for the happening without the covenantor of a subsequent event which renders performance of the covenant itself not merely difficult, or relatively impossible, but absolutely impossible, owing to the act of God, thg act of the law, or the loss or destruction of the subject-matter of the contract. Where the performance is thus rendered impossible, the inquiry naturally arises whether there was a purpose to covenant against such an extraordinary, and therefore presumably un-apprehended, event, the happening of which it was not within the power of the covenantor to prevent.
[3] “In other words, there can be no doubt that a man may, by an absolute contract, bind himself to perform things which subsequently become impossible, or to pay damages for the nonperformance, and this construction is to be put upon an unqualified undertaking where the event which causes the impossibility was or might have been anticipated and guarded against in the contract, or where the impossibility arose from the act or default of the prom-isor.
[4] “But where the event is of such a character that it cannot reasonably be supposed to have been in the contemplation of the contracting parties when the contract was made, they will not be held bound by general words which, though large enough to conclude, were not used with reference to the possibility of the particular contingency which afterwards happens.”
We do not intend to convey the impression that we think the furnishing of power by the electric company was an implied condition, or that the failure to furnish such power by the electric company rendered performance of the contract by appellant impossible. Upon the failure of such power it became appellant’s duty to substitute other power or pay the damages incident to a breach, since there is nothing in the contract indicating that the power with which it operated its mill would likely fail. The reasonable inference from the language of the writing is, as alleged by appellee, that appellant had and would continue to have the power necessary to run its mill and the cotton seed available from which to obtain the lint, else some mention of it would have been made in the instrument. This case is distinguishable from the case of Wright v. Farmers’ National Bank, 31 Tex. Civ. App. 406, 72 S. W. 103, and the Texas cases therein cited, in that here the intention of the appellant to fulfill the contract is manifest and may be inferred from its sale of and agreement to make and ship 200 bales of linters. The absolute promise is inferable from the failure to mention the contingency which actually prevented performance. In the Wright Case and the cases cited therein, the inability to perform until the happening of the conditions upon which the promises to pay are predicated are expressed in the contracts themselves. In the instant case doubt is expressed as to the appellant’s ability to fulfill the contract. The rule with reference to excuses for noh-performance of similar contracts is thus stated in 13 C. J. § 706:
“The general rule is that where a person, by his contract, charges himself with an obligation possible to be performed, he must perform it unless its performance is rendered impossible by the act of God, by the law, or by the other party ; it being the rule that in case the party desires to be excused from performance in the event of contingencies arising it is his duty to provide therefor in Ms contract. Hence performance is not excused by subsequent inability to perform, by unforeseen difficulties, * * * by inevitable accident, or by the breaking of machinery. * * * ”
What has been said also disposes of the fifth and sixth assignments.
cgnwFor other oases see same topic and KEY-NUMBER in all Key-Numbered Digests and Indexes