JOHN P. KING et al., Respondents, v. THE CITY OF SEATTLE, Appellant.
No. 42920
En Banc.
August 15, 1974.
239
Lee Olwell (of Olwell, Boyle & Hattrup), for respondents.
UTTER, J.—The City of Seattle appeals from a ruling by the trial court awarding damages to John P. King and his wife. The damages were for the City‘s alleged intentional and wrongful refusal to issue street use and building permits to the Kings.
The City contends that its acts are immune from liability because they involve the erroneous exercise of discretion and, even if no immunity exists, that its acts were not the
The Kings were contract purchasers of lots submerged in Lake Union in Seattle. The lots abut Fairview Avenue East which is itself partially submerged along the edge of the lake where it adjoins the lot boundaries. The Kings first applied for a building permit in January 1969 to construct an apartment building on the lots. They were unable to obtain a lease from the State of Washington for adjoining state land which would have been necessary to meet the zoning requirements for construction of an apartment building. Their failure to obtain the leased land resulted in denial of the building permit.
In March of 1970 the Kings applied for a building permit to enable them to construct an office building on the same lots. This building did not require the use of additional land. A condition precedent to the granting of the building permit, however, was the issuance of a street use permit by the Board of Public Works, an agency of the City. The Board of Public Works denied the application for the street use permit at that time, based upon their judgment that a street use permit might conflict with a pending local improvement district plan, not yet enacted by ordinance. The building department denied the building permit at that time because no street use permit was granted.
The Kings then brought a mandamus action on May 15, 1970, to require the issuance of street use and building permits by the City. On June 11, 1970, a judgment was entered directing issuance of the building permit and street use permit either in the form requested or upon reasonable terms and without unreasonable delay. The court also found that the prior action of the City in refusing the same was arbitrary and capricious and without justification in law. The building permit was issued on June 16, 1970, and a street use permit authorizing construction of two ramps
On May 26, 1970, however, the United States Corps of Engineers had changed its regulations to require permits over water areas inside the harbor or pierhead lines. For 70 years prior to this the Corps had required permits only in navigable waters beyond the established harbor or pierhead lines. After the issuance of the street use permit pursuant to court order, the Kings did not make application to the Corps for an overwater building permit for their office building but, apparently, abandoned the project. They ceased making payments on the property in the summer of 1970 and in November 1970, quitclaimed their interest in the property to the vendor following service of a notice of forfeiture. No attempt was made to sell their interest in the property nor was it listed with a real estate broker.
The Kings, in this action, seek from the City damages and expenses for their loss of profit on the office building which they were unable to construct. The trial court found that “[f]ollowing the revision of the Army Corps regulations, it became impossible for Plaintiffs to construct the proposed office building . . .” (Finding of fact No. 8.), “the said actions of the Defendant City of Seattle were a proximate cause of the losses and damage sustained by Plaintiffs, and the nature of said damage was reasonably foreseeable” (Finding of fact No. 9.), and “the actions of the Defendant City of Seattle in refusing to issue a permit to Plaintiffs for an office building, from and after May 7, 1970, and in denying Plaintiffs any access to their own property involved no exercise of discretion, and in no manner were legislative or part of the planning process” (Finding of fact No. 10.).
The trial court awarded damages for costs and expenses of $54,524.36 and for lost profits on the proposed office building of $311,018.02.
The City appears to attempt to relitigate the characterization of the nature of its acts of April 22 in denying the street use permit and refusing to grant a building per-
The City urges, however, that its acts were purely of a governmental, policy-implementing character and the abrogation of governmental immunity in Washington did not expose the City to tort liability when performing such functions. Laws of 1963, ch. 159, § 2 (
Immunity of governmental officials for discretionary acts historically has been independent of that advanced to justify the immunity of the state from liability for torts for which
These fears are not founded upon fact, however, if it is the municipality and not the employee who faces liability. The most promising way to correct the abuses, if a community has the political will to correct them, is to provide incentives to the highest officials by imposing liability on the governmental unit. The ranking officials, motivated by threats to their budget, would issue the order that would be necessary to check the abuses in order to avoid having to pay damages. K. Davis, Administrative Law Treatise, § 25.17 (Supp. 1970) at 864-65. The idea that public entities and not officers or employees should ultimately bear liability springs from United States v. Gilman, 347 U.S. 507 (1954).
As noted in K. Davis, Administrative Law Treatise, § 25.18 (Supp. 1970), at 870:
A discretionary function exception is essential to a good system of law on governmental tort liability, but the exception should not be pushed beyond the reasons behind it.
. . . Fears that a system of liability for deliberate torts may cause unwanted results are satisfactorily answered by the experience in New York and California, where governmental units are often liable for deliberate torts of their agents.
In further refining what process must be entered into by the court in determining whether an act is discretionary or not, the court in Johnson v. State, 69 Cal. 2d 782, 788, 790, 793, 794, 447 P.2d 352, 73 Cal. Rptr. 240 (1968), rejected as semantic inquiry into the meaning of “discretion-
Immunity for “discretionary” activities serves no purpose except to assure that courts refuse to pass judgment on policy decisions in the province of coordinate branches of government. Accordingly, to be entitled to immunity the state must make a showing that such a policy decision, consciously balancing risks and advantages, took place. The fact that an employee normally engages in “discretionary activity” is irrelevant if, in a given case, the employee did not render a considered decision.
In Weiss v. Fote, 7 N.Y.2d 579, 586, 200 N.Y.S.2d 409, 167 N.E.2d 63 (1960), the Buffalo Board of Safety, exercising its discretion, chose a time interval between red and green in traffic lights which a trial jury found to be negligent. The appellate court reversed, reasoning that “absent some indication that due care was not exercised in the preparation of the design or that no reasonable official could have adopted it — and there is no indication of either here — we perceive no basis for preferring the jury verdict, as to the reasonableness of the ‘clearance interval‘, to that of the
Whatever policy reasons may exist for discretionary immunity, we do not find them present in this case. The finding of fact that the City, through its Board of Public Works, acted arbitrarily and capriciously and without foundation in law and that it “intended to harass and discriminate against Plaintiffs and to prevent Plaintiffs from constructing a commercial building on their property”1 brings it within the language in the Johnson and Weiss cases. Their holding that it is improper to extend the discretionary activity analysis to those cases where employees do not render a considered decision or render decisions that no reasonable official would have adopted applies here. The question whether the City‘s acts complained of here were of a kind usually nominated “ministerial” or “discretionary” is not material to our determination because earlier they had been determined conclusively to have been arbitrary and capricious.
Though not characterized by the parties, the tort complained of here is interference with prospective economic advantage. There are three elements to the tort. The plaintiff must prove that he had a relationship with others contemplating a contract, with at least a reasonable expectancy of fruition, that this relationship was known, or reasonably apparent, to the interferor, and that the interference which caused the termination of the relationship or expectancy was intentional. Scymanski v. Dufault, 80 Wn.2d 77, 491 P.2d 1050 (1971).
There is a reasonable basis from which to support the trial court‘s findings that the City intentionally acted to interfere with the plaintiffs’ known or reasonably foreseeable business expectancy. The City was under a duty to act
We have earlier held that foreseeability of the risk of harm to the plaintiff is an element of the duty question. If the risk of harm which befell the plaintiff as a result of the defendant‘s act was not reasonably foreseeable, our cases have held, then, as to that plaintiff, no duty respecting that act was owed. Thus, no duty was breached, and no legal liability attached to the defendant for that plaintiff‘s loss. Rikstad v. Holmberg, 76 Wn.2d 265, 456 P.2d 355 (1969); Wells v. Vancouver, 77 Wn.2d 800, 467 P.2d 292 (1970). A more complete discussion of the problem is found in Palsgraf v. Long Island R.R., 248 N.Y. 339, 162 N.E. 99, 59 A.L.R. 1253 (1928), dissenting opinion per Andrews, J.; Gregory, Proximate Cause in Negligence — A Retreat from “Rationalization”, 6 U. Chi. L. Rev. 36, 50 (1938); Prosser, Proximate Cause in California, 38 Cal. L. Rev. 369, 396 (1950).
Liability extends to foreseeable results from unforeseeable causes. It was foreseeable that arbitrary and capricious delay of the plaintiffs’ building project could cause them damages, increase in the price of materials, the cost of labor, the interest rate on borrowed money, and many other specific areas of harm. Liability is not predicated upon the ability to foresee the exact manner in which the injury may be sustained. Berglund v. Spokane County, 4 Wn.2d 309, 103 P.2d 355 (1940).
The City‘s actions here were a cause in fact of the plaintiffs’ damages, and the amount of damages is not disputed. But for the City‘s acts which delayed plaintiffs’ ability to begin construction, the plaintiffs would have been able to build the structure over water before the changed Corps rule required a federal permit.
This is the sense in which the term “proximate cause” is often discussed. See WPI 15.01.2 Cause in fact is not, however, the sole determinate of proximate cause, and in a broader sense the question of law as to whether legal liability should attach, given cause in fact, is the question still before us in this case. The plaintiffs here do not present a good cause of action against the City for interference with prospective economic advantage.
As a matter of policy we cannot say on these facts that
The trial court in finding of fact No. 9 determined that the City‘s acts were “a proximate cause” of the plaintiffs’ damages. We treat this finding as a conclusion of law, its proper designation, subject to the review of this court as a question of law. See L. Green, Rationale of Proximate Cause, ch. 1, §§ 3-4 (1927); 1 T. Street, Foundations of Legal Liability, 110 (1906); Terry, Proximate Consequences in the Law of Torts, 28 Harv. L. Rev. 10, 24 (1914).
The standards which a court must apply to a tort action in determining whether legal liability should attach to the defendant if the factual elements of the tort are proven, are not susceptible of a conclusive and fixed set of rules, readily formulated. “[Legal liability] is always to be determined on the facts of each case upon mixed considerations of logic, common sense, justice, policy, and precedent. . . . The best use that can be made of the authorities on proximate cause is merely to furnish illustrations of situations which judicious men upon careful consideration have adjudged to be on one side of the line or the other.” 1 T. Street, Foundations of Legal Liability, 110 (1906).
There are two reasons why we cannot say, as a policy of law, that the City should be subject to legal liability for the plaintiffs’ damages in this case. The plaintiffs made no effort to exhaust their federal administrative remedies nor did they attempt to avoid their damages, even
The plaintiffs maintain that they elected not to apply for the federal permit and not to attempt a sale of their property because they no longer had the economic resources which in their judgment would have been necessary to adequately pursue these avenues. This was a voluntary business judgment.
Municipal liability for tortious interference with prospective economic advantage should not be premised on the independent unsubstantiated decision of a plaintiff that it would be unavailing to seek a possible administrative remedy accorded him under the law. If this were not so, the plaintiff would be able to create liability in another by his own independent judgment. We therefore find no legal liability (proximate cause) in the City for the plaintiffs’ damages here.
The approach taken by the dissent begs the question. The question presented by this case is whether, given that the defendant City‘s acts were a cause in fact of the plaintiffs’ harm, the City should be held legally liable for all of the plaintiffs’ ultimate damages. The plaintiffs urge this liability should exist even though they had available to them but intentionally refused to exercise a known legal remedy which, if pursued, could have prevented all of their damages.
The doctrine of mitigation of damages which the dissent discusses is inapplicable to this case because the question of whether the plaintiffs had a duty to mitigate presupposes that the City is legally liable for the plaintiffs’ damages in the first instance. We may not presuppose that issue here precisely because that is the issue presented for decision.
There was no finding of fact here that the plaintiffs, because of the City‘s bad faith tactics, could not have afforded financially either (1) to further pursue the federal
A neighboring developer, faced with the same legal question, received a judgment in the Federal District Court for the Western District of Washington which held that no application for a federal Corps of Engineers building permit was required under the May 27, 1970, change in the Corps requirements. The reasoning of the court was that the project had been “commenced,” in the language of the new Corps rule, prior to the effective date of that Corps regulation change. “Commencement” was held to be mere preparation of plans for building, requiring no physical act such as driving piles, etc. United States v. E.T. Hinrichs & Associates, No. 9353 (W.D. Wash., Dec. 28, 1970). If plaintiffs here had not gratuitously quitclaimed their property back to their contract vendor on November 13, 1970, the reasoning of the Hinrichs case, entered 1 month later, would have required that the plaintiffs here be permitted to proceed without regard to the change in the Army Corps regulations.
We do not believe it would be wise judicial policy to allow one party to create legal liability in another by a voluntary exercise of the complaining party‘s own personal business judgment not to seek to protect his rights in the legal forums provided him. This is especially so where, if the complaining party had exercised his legal rights in the first place, there may well have been no damage to his interests at all.
We are mindful, nonetheless, of the potential for abuse which legal process may serve in the hands of public
Reversed.
HALE, C.J., and FINLEY, ROSELLINI, STAFFORD, and WRIGHT, JJ., concur.
BRACHTENBACH, J. (dissenting) — I agree with all of the majority opinion except its conclusion that the defendant‘s actions were not a proximate cause of plaintiffs’ damages. To be precise we should emphasize, as the majority correctly does, that we are not here speaking of proximate cause as cause in fact. The majority acknowledges that cause in fact did exist, linking the defendant‘s actions to the plaintiffs’ damages.
Cause in fact does not lead automatically to legal responsibility. Again the majority is right in stating that there remains the question of whether the defendant should be legally responsible for the damages caused in fact. Proximate cause, in this sense, is an imprecise term. It really is a matter of policy of determining the extent of a defendant‘s liability for its wrongdoing. W. Prosser, Torts § 42, at 244 (4th ed. 1971).
Surely we must have some recognized legal theory upon which to base a conclusion that there is no legal responsibility here. What are the policy considerations which free
What the majority in fact and in reality is holding, in my view, is that, as a matter of policy, we will deny damages because these plaintiffs did not mitigate their damages. I find no other legal theory in the majority opinion to justify its conclusion.
There are several reasons why the principle of mitigation should not be the foundation for such a policy determination that no damages are recoverable. First, it is the wrongdoer to which we are affording this protection and we should proceed with caution in creating such freedom from liability. That is the philosophy of this court. Hogland v. Klein, 49 Wn.2d 216, 221, 298 P.2d 1099 (1956).
Second, the defendant was guilty of an intentional tort against plaintiffs. That is, interference with prospective economic advantage. The majority correctly characterizes the defendant‘s actions as an intentional tort. An intentional wrongdoer cannot place upon its victim the duty to mitigate. We have long so held. Desimone v. Mutual Materials Co., 23 Wn.2d 876, 884, 162 P.2d 808 (1945); Champa v. Washington Compressed Gas Co., 146 Wash. 190, 200, 262 P. 228 (1927). To apply mitigation principles in this case under the guise of a policy consideration in the context of determining proximate cause is unwarranted.
The majority rejects the plaintiffs’ explanation that they could not — for economic reasons — pursue their federal administrative procedures for a permit or keep up the contract payments while trying to sell the property. The majority contends that the trial court made no finding that plaintiffs were without economic resources to continue their efforts. In fact, the trial court did enter a finding that the plaintiffs were forced to abandon the property. Implicit in that find-
I fail to understand why an intentional tort-feasor can or should escape liability because it happened to choose a plaintiff who did not have the financial resources to overcome the damages caused by the intentional tort.
In any event, contrary to the majority‘s rejection of this economic decision by plaintiffs, it is entirely fitting to evaluate plaintiffs’ actions in light of their own financial condition. We have so held in Hoff v. Lester, 25 Wn.2d 86, 168 P.2d 409, 164 A.L.R. 751 (1946), and Adams v. Thibault, 49 Wn.2d 24, 297 P.2d 954, 57 A.L.R.2d 1372 (1956).
Returning to the two reasons assigned by the majority to its policy conclusion that no liability attaches, we find that these are tenuous grounds factually. The project could not go forward without a permit from the Corps of Engineers. The majority speculates that the plaintiffs could well have obtained such a permit. Yet the person in charge of issuance of such permits testified that in very similar circumstances it took almost 2 years to process such a permit. The defendant City chose to introduce no other evidence as to the likelihood of success or of the time which might be involved in securing the permit. Likewise, with regard to a possible sale of the property to recover the plaintiffs’ equity, the City did not present any evidence as to the market demand for this property or the time it might take to find a buyer; indeed it proved nothing more than the gross equity. Recovery of the equity would not have offset the $311,018.02 which the trial court found to be plaintiffs’ loss of profit on the contemplated building.
Under these circumstances I believe that justice requires
HUNTER and HAMILTON, JJ., concur with BRACHTENBACH, J.
Petition for rehearing denied December 17, 1974.
Notes
“PROXIMATE CAUSE — DEFINITION.
“The term ‘proximate cause’ means a cause which in a direct sequence, unbroken by any new independent cause, produces the [injury] [event] complained of and without which such [injury] [event] would not have happened.
“[There may be one or more proximate causes of an [injury] [event].]”
