In response to an invitation for bids by the Board of Trustees of the Village of Munde-lein (the “Board”) for the construction of a sanitary sewer line, the Kim Construction Co. (“Kim”) submitted a timely bid that met *1245 the Board’s specifications for the project. Because two lower bids submitted in response to that invitation contained irregularities, the Board decided to reject all bids and call for a rebidding on the project. Kim did not participate in the rebidding. The Board subsequently awarded the contract to the lowest responsible bidder after the second round of bids. Kim then filed suit, claiming that it had been deprived of a constitutionally protected property interest without due process of law. The district court granted the Board’s motion for summary judgment. We agree that Illinois law does not create the property interest that Kim seeks to vindicate, and therefore affirm.
I. Background
In March 1992, the Board ran an advertisement soliciting bids for a sanitary sewer project, which included the following provision: “The Board of Trustees reserves the right to reject any and all bids and to waive technicalities. Unless the bids are rejected for good cause, award of a contract shall be made to the lowest responsible and responsive bidder.” The advertisement also specified that the project was to be funded in part by a grant from the Illinois Environmental Protection Agency (IEPA), and that the contract award would be subject to the IEPA’s prior approval. Four bids, including Kim’s, were submitted in response to this advertisement. After examining the bids, the village engineer determined that the two lowest bids contained irregularities, and that Kim’s bid was the lowest bid which fully conformed to project specifications. Rather than waiving the irregularities and awarding the contract to the lowest bidder, the Board, with the IEPA’s concurrence, rejected all bids and advertised for a second round of bidding on the project. No substantive changes were made in project specifications between the first and second round of bidding; thus both rounds were on the same project. In response to this decision, Kim asserted that the Board’s action was unauthorized, and requested that it be awarded the contract as the lowest responsible and responsive bidder. Approximately two weeks later, the Board adopted a resolution confirming its rejection of all first round bids and its authorization of a rebidding on the project. Kim refused to participate in the rebidding.
At the close of the second round of bidding in September 1992, the Board awarded the contract to the lowest responsible bidder, whose bid was substantially lower than that submitted by Kim in the first round. Kim then filed an action pursuant to 42 U.S.C. § 1983, seeking to prevent the Board from rejecting all first round bids and from awarding the contract to any party which submitted a second round bid. The district court denied Kim’s request for injunctive relief on the basis of its failure to show that it had a reasonable chance of prevailing on the merits. Kim then filed an amended complaint seeking money damages in compensation for the losses it had incurred due to the Board’s rejection of its first round bid. The district court granted summary judgment in favor of the Board. Kim appeals.
II. Analysis
Kim’s claim that it was deprived of a property interest in violation of the Fourteenth Amendment requires two separate inquiries: first, whether Kim possessed a constitutionally protected property interest in the contract award, and second, whether Kim was deprived of that interest without due process.
See Cleveland Bd. of Educ. v. Loudermill,
To have a constitutionally protected property interest in the award of a municipal contract, an individual must have a “legitimate claim of entitlement to it.”
Board of Regents v. Roth,
In the absence of an underlying property interest, the Due Process Clause does not require states to obey their own procedural rules in awarding municipal contracts.
See Szabo,
Whether Kim has a property interest in being awarded the municipal contract on the basis of its first round bid is determined by Illinois law.
See Bishop v. Wood,
To counter this result, Kim advances two arguments. First, Kim contends that Ill. Rev.Stat. ch. 24, para. 8-9-1 (1990) 2 contains mandatory language requiring a municipality to award a contract “to the lowest responsible bidder after advertising for bids.” In relevant part, para. 8-9-1 provides that
any work or public improvement ... shall be constructed ... by a contract let to the lowest responsible bidder after advertising for bids, in the manner prescribed by ordinance, except that any such contract may be entered into ... without advertising for bids, if authorized by a vote of two-thirds of all the aldermen or trustees then holding office;
Ill.Rev.Stat. ch. 24, para. 8-9-1 (1990). Kim maintains that because it was the lowest responsible bidder after the first round of bidding, it was entitled by statute to the contract award.
In
Kentucky Dep’t of Corrections v. Thompson,
Under para. 8-9-1, the Board was permitted to establish by ordinance the procedures that would govern the solicitation of bids. As the district court observed in its order denying injunctive relief, a statute which grants a municipality the power to specify the manner of bidding, or to dispense with competitive bidding by a two-thirds vote and choose an entirely different method of awarding public contracts, cannot reasonably be read as imposing a binding obligation on the municipality to award a public contract to the lowest responsible bidder after the first round of bids.
See Olim,
This conclusion is further supported by the state administrative regulations which govern the award of public contracts for sewage treatment facilities that receive IEPA funding. Section 360 of Title 35 of the Illinois Administrative Code sets forth the general conditions of IEPA grants for sewage treatment works under the Anti-Pollution Bond Act of 1970. 3 Section 360.302(d)(8)(B) of the Code provides: “The grantee may reserve the right to reject all bids. Unless all bids are rejected, award shall be made to the low, responsive, responsible bidder after the bid evaluation has been submitted to the Agency *1248 and written notice of Agency approval has been received by the grantee.” Ul.Ad-min.Code tit. 35, § 360.302(d)(8)(B). Under this regulation, the Board, as a grantee of an IEPA-funded project, was expressly authorized to reserve the right to reject all bids. Since the Board did reject all bids in the first round, it was not required to accept the bid of the lowest responsible bidder. Moreover, because the Board’s invitation to bid advised all prospective bidders that the bidding process was governed by this regulation, Kim’s claim of entitlement on the basis of “rules or mutually explicit understandings” creating a property right in the contract award proves untenable. See Perry, 408 U.S. at 601, 92 S.Ct. at 2699.
Second, Kim argues that Illinois courts have recognized the “very limited due process right for unsuccessful bidders as established under the rationale of
Three Rivers,’’ Northwest Disposal Co., 75
Ill.Dec. at 12,
To the extent that the decision in
Three Rivers
rested on a proposition of Pennsylvania law, it is, of course, inapplicable to this case. Kim’s reliance on
Pataula Elec. Membership Corp. v. Whitworth,
Kim also draws a distinction between the federal constitutional aspect of
Northwest Disposal,
which has not survived the Supreme Court’s decision in
Olim,
The other cases upon which Kim relies to show that Illinois recognizes the right of disappointed bidders to claim the protection of state competitive bidding statutes are in-apposite. In
Stanley Magic-Door, Inc. v. City of Chicago,
The Board has maintained that the underlying purpose of the Illinois responsible bidder statute was served by its action in this case.
See Beaver Glass & Mirror v. Board of Edue.,
the district court’s summary judgment in favor of the Board is
Affirmed.
Notes
. See
also McCammon v. Indiana Dep’t of Financial Institutions,
. Recodified as 65 ILCS 5/8-9-1 (1992).
. See Ill.Rev.Stat. ch. 127, para. 451 et seq. (1990), recodified as 30 ILCS 405/1 et seq. (1993).
. In
Court Street Steak House,
the court noted that "the award of a contract to a bidder involves the exercise of discretion on the part of the Board, which discretion will not normally be interfered with by the courts,”
. This is precisely the sort of policy argument that may be made in state court in support of a state law claim,
see, e.g., Court Street Steak House,
189 Ul.Dec. at 58,
