55 Mo. App. 427 | Mo. Ct. App. | 1893
The defendant Dunn entered into a contract with his eo defendants, Meehan and Creagen, for the construction of some buildings to be erected on a lot owned by him. The houses were to be built according to written specifications and plans, and the building contract contained the further stipulation that, if they were not completed at a given time, then Meehan and Creagen should forfeit and pay to Dunn $5 for each day thereafter until their final conipletion. To secure Dunn in the performance of this contract, Meehan and Creagen gave an indemnifying bond, in which the plaintiff was surety.
The present action is one for work done and materials furnished by the plaintiff as a subcontractor under Meehan and Creagan in the construction of the houses, and. for the enforcement of a mechanics’ íien against the lot and houses. Dunn alleged in his answer, by way of counterclaim against the plaintiff as surety in the bond, that Meehan and Creagen had failed to complete the houses within the prescribed time, and that, by reason thereof, he- (Dunn) was
On the trial the jury returned a verdict in plaintiff’s favor for $507.90, and the jury also found that the plaintiff was entitled to the enforcement of his mechanics’ lien. Judgment was entered accordingly. The jury also returned a verdict in favor of Dunn on the counterclaim for $500, and the court entered a judgment thereon. It is of this last matter that the plaintiff complains.
The building contract contains this clause: “The superintendent shall be at liberty to make any deviation from, or alteration in the plan, form, construction, detail and execution described by the drawings and specifications without invalidating or rendering void
It was developed by the plaintiff on the cross-examination of W. B. Ittner, one of the architects in charge of the buildings, that the cellar was dug six inches deeper than the plans called for, thereby entailing the additional cost of $32. Concerning this change the witness said: • “As I remember, I think'that (the change in the depth of the cellar) was more of a necessity than anything else. When we went to lay out the house, we found the ground low; if we had built our house as the plans showed, we would have nothing to rest it on but six inches of air, so that we just dropped our bottom six inches; it was not a change made on Mr. Dunn’s request, but it had to be made.” The witness also testified that, at the request of Dunn, extra work was done in the bath room, amounting to $8; shelves in the closets, $3; and a partition fence, $7; that there was no written agreement between Meehan and Creagen and the superintendents, providing for any change in the plans or for extra work or the cost thereof; that the plaintiff was not notified of the change or extra work, and that he did not assent to the same.
The court refused the following instruction, asked by the plaintiff:
"The court instructs the jury that, under the terms of the contract read in evidence, neither the owner nor the superintendents, Poster and Ittner, had any right to make any changes, alterations or additions in the work required to be done, which would increase the cost thereof, without first agreeing in writing as to the value of such additional cost, and said agreement being signed by said superintendents and Meehan and Creagen; and, if the jury believe from the evidence that there was any additional work done by said Meehan and Creagen at the instance and request of the superintendents, which increased the cost of the flats in question, and that there was no agreement entered into in writing between said superintendents on the one side and Meehan and Creagen on the other before said extra work was done, then this would release the plaintiff from any liability on. his bond, and the jury should find for the plaintiff and against defendant Dunn upon his counterclaim.”
But we are all agreed that the court committed error by giving the defendants’ fifth instruction, which reads: “The court instructs the jury that by the terms of the contract and bond read in evidence the fact that alterations or extra work was done by Meehan and Creagen, the contractors on the buildings and improvements, did not impair or render void said bond, nor release or discharge the plaintiff from the obligations of said bond.” As all the evidence tended to show that the alterations were made, and that the extra work was performed without any agreement in writing providing therefor, and fixing the price thereof, this instruction was clearly wrong under the recent decision of the supreme court in the case of Beers v. Strimple, reported in 22 S. W. Rep. 620. The court was there called upon to construe a similar contract, and the conclusion arrived at was that, before the owner or superintendent of the building was authorized under the
The other assignments are not well taken. But, in view of a retrial, we deem it proper to suggest that to relieve the plaintiff from his liability on the bond the changes and extra work must have been authorized either by the superintendents or Dunn, and the extra work must have been performed under the original contract. Therefore, if, as a matter of fact, the change
As the rights of the respective parties must be settled and adjudicated at one and the same time, the error of the court in reference to the trial of the counterclaim must result in vacating the judgment altogether. Therefore, it will be set aside, and the cause remanded.