57 Ind. 480 | Ind. | 1877
Suit by the appellee, against the appellants, ■who are the trustees of St. Bernard’s Catholic Church of Rockport, Spencer county, Indiana, upon a special contract for erecting the walls of a church building.
A copy of the contract is made a part of the complaint.
. The complaint consists of a single paragraph, and alleges completion of the contract on the part of the appellee, and a breach on the part of the appellants, by failing to pay, according to the contract, for the erection of the church.
Appended to this complaint on the special contract is this hill of particulars:
“ St. Bernard’s Catholic Church,
To Philip Eigenmann, Dr.
“ To furnishing and laying in the wall six hundred and thirty-three thousand six hundred and sixteen brick, at nine dollars and fifty cents per thousand, . . . . ■ $6,020 35
*482 “ Extra work on said church, as ordered by tbe trustees,.......$180 00
“ Interest,........ 54 00
“ Bal. due plaintiff, '.....$6,204 35
“Philip Eigenmann.”
The complaint avers, that notice of intention to hold a lien on the property had been duly given and recorded, and prayed a decree for enforcement thereof.
A copy of the notice was filed with the complaint.
The contract upon which the suit was brought is in words following:
“This agreement, made this nineteenth day of January, 1875, by and between John Kerstein, Albert Killian, J ohn Eischer and Ignatz Quick, trustees of the St. Bernard’s Catholic Church of Eockport, Spencer county, Indiana, of the first part, and Philip Eigenmann, of the second part, witnesseth: That the party of the first part have employed the party of the second part to build a church house in Eockport, Spencer county, Indiana, corner of Elm and Sixth streets, where the foundation of said .church is now laid; the said Eigenmann to do the brickwork ■ on said church; the said church to be built in all respects according to the ■ specifications and plans drawn up and "furnished said Eigenmann this day, being the same as the specifications and plans of the Cedar G-rove, Indiana, Catholic Church, except that an addition of one sanctuary and two sacristies are [is] to be built in the rear end of the main building, specifications of which are to be furnished hereafter. The said Eigenmann is to furnish all the materials except rock, and to do all the work, including the laying of stone and brick, and is to receive, for his compensation, nine dollars and fifty cents per thousand brick, after building masons’ measurement. The said Eigenmann is to commence his work on said building not later than. April 1st, 1875, and to complete the main building of said church by August 1st, 1875, and the steeple**483 and entire job by September 1st, 1875. The said Eigenmann is to receive five hundred dollars of his pay, on or before April 1st, 1875, and afterward he is to receive fifty per cent, of his pay as the work progresses, inclusive of the five hundred dollars to be paid April 1st, until the completion, when he shall receive the balance. The said Eigenmann is to furnish good material, and'do the work on said building in a good workmanlike manner.
“ Witness our hands, this 19th of January, 1875, at Rockport, Spencer county, Indiana.
(Signed,) “ John Kerstein,
“ Albert Killian,
“Ignátz Quick,
“John Fischer, ■
“ Trustees of St. Bernard’s Catholic Church, Rockport, Spencer county, Indiana,
“Philip Eigenmann.”
A notice of a mechanic’s lien, addressed to said trustees by name, but as trustees of said, church, and to their successors in office, and to the Bishop of Vincennes, follows;
“ Take notice, that I intend to hold a lien on the real estate described as follows: Commencing at the southwest corner of Out-lot No. 6, in Wm. R. Hynes’ Donation to .the town of Rockport, Spencer county, Indiana; running thence west one hundred and seventy-one feet, to the State road; thence north two hundred and twelve feet, along said State road; thence east one hundred and seventy-one feet, to the beginning; together with the church building situated thereon, for the sum,” etc.
Dated December 14th, 1875, and signed Philip Eigenmann.
Endorsed:
“ Filed 8 a. m., 15 December, 1875, and recorded in Lien Record No. 1, page 142. L. E. Riggs, R. S. C.”
The appellants answered in three paragraphs:
1. The general denial;
2. Payment; and,
Reply:
1. A genéral denial; and,
2. Alleging that the failure to complete the building, averred in the third paragraph of answer, was caused by the fault of appellants.
The issues in the cause were tried by a jury, who returned a general verdict of over two thousand dollars in favor of the plaintiff, and that he have a mechanic’s lien, etc., and also returned with their verdict the following answers to interrogatories:'
“ 1. How many thousand brick did the plaintiff lay in the building, according to building masons’ measurement?
“Answer. We, the jury, find that the plaintiff laid five hundred and seventy-one thousand one hundred and fifty-five brick.
“ 2. ■ What amount of damages, if any, have the defendants sustained on account of non-performance by the plaintiff in laying said brick according to contract?
“Answer. Not any.
“ 3. What amount, if any thing, is due the plaintiff for extra work ?
“Answer. Nothing.
“ We, the jury, find that there is due plaintiff fifty-four dollars and eight cents, as interest due on said judgment.
“Absalom Hackleman, Foreman.”
A motion for a new trial was made by the defendants, for the following reasons:
1. Excessive damages in the amount of fifty-four dollars, being the interest found due by the jury;
2. Verdict contrary to the law, and not sustained by the evidence;
4. Permitting the plaintiff, Eigenmann, to testify, over the defendants’ objections, to extra work claimed to have been done on the building, and refusing to permit George Procaskey, a defendant, to testify whether he, as one of the building committee, knew, at the time of making the contract, what the plaintiff’s rule of measuring brick work was; also, in allowing the plaintiff, after both parties had-introduced their evidence and rested, to recall J. K. Erick, and allow him to testify, over the defendants’ objections, to his mode of measurement, and that it was the only correct one; and in permitting, in like manner, over like objections, J. D. Armstrong to be recalled, and to testify as to what was building masons’ measurement, and that Erick’s was correct; and that William Reynolds had told him that Erick’s rule was the correct one; and,
5. Giving instructions from one to fourteen inclusive.
The motion for a new trial was overruled, and exception taken.
The only alleged error, assigned in this court, is the overruling of the motion for a new trial. This requires, the court to consider and decide upon the validity of the causes assigned for a new trial.
We will notice them in the order of their assignment:
1. Interest may be allowed by the court upon trying a cause, in a case where money is due, and its payment unreasonably delayed. 1 R. S. 1876, p. 600, sec. 4.
2. The evidence is in the record, and tends to sustain the verdict, except as to the mechanic’s lien. By the contract, the work was to be completed by September 1st, 1875. It was not finished by that time, owing to the fault of the defendants; but it appears to have been finished by the 1st of October, at least; and the burden was upon the plaintiff to show when it was completed,
■Whether the verdict is shown to be illegal, will appear from what will be said hereafter.
3. The court may refuse to submit interrogatories to the jury, which are asked to be answered by them absolutely, and not in the event that they return a general verdict. Hopkins v. Stanley, 43 Ind. 553. The court may direct a jury to answer interrogatories propounded of its own motion. See Weatherly v. Higgins, 6 Ind. 73. But abuse of this power might be error.
4. The plaintiff:' had incorporated in his bill of particulars filed an item for extra work. The defendants did not, as they should have done, move to have it struck out. As the complaint was upon the special contract alone, the claim for extra work should have b.een set forth in an additional paragraph for work and labor done, etc. This suit was not commenced before a justice of the peace. But as the jury disallowed this item of his claim, it does not appear that the defendants suffered any harm by the error, if error it was, in permitting the testimony of the plaintiff' touching this item.
The defendants asked witness Procaskey this question, “Are you acquainted with the rule for measuring brick work, followed by the plaintiff, on buildings he put up here, in Rockport, about the time of making this contract, and if so, state what his custom is ?”
On objection, the court refused to permit the question to be answered, and the defendants excepted. The contract sued on provided that the quantity of brick for which plaintiff was to be paid should be determined by masons’ measurement; and the testimony on the trial tended to show that there was not • uniformity in the manner of measuring, by' what was termed masons’ measurement; and we suppose the excluded question was asked with
The court did err in permitting J. D. Armstrong to testify to the statements of William Reynolds, as to the character of Erick’s rule of masons’ measurement. It was hearsay testimony, and upon an important and controverted point. The jury found specially that the defend-' ants were not entitled to recover on their answer, by way of counter-claim, for damages. This finding was upon the two issues made by the reply to this paragraph of answer:
1. A general denial;
2. That the damages were occasioned by the fault of ‘ the defendants.
We say nothing as to the form of pleading in the case.’ We look to the substance alone. We think, if the delay and damage complained of were caused by the fault of the defendants, the finding of the jury on these issues may be upheld.
We turn now to the instructions of the court.
“ Mr. Erick states that he is an architect, and that he measured the brick work, and it contains 634,706. Mr. Bellamy states that he is an architect, and that he measured the same brick work, and that it only contained 478,768, making a difference between these two measurements of 145,938. It is for you to say, after carefully considering the evidence of Mr. Erick and Mr. Bellamy, the architects, and all the other evidence of the other witnesses, as to the number of brick laid in building said church, and, from the evidence, say what number of brick was laid by plaintiff in building said church.
“ Given and excepted to.
“ "Wedding & Evans,
“ Reinhard & Swan,
“ Eor defendants.”
This instruction is erroneous. It states positively to' the jury what the testimony of witnesses was upon a material point. It was not for the court, but for the jury,, to say what the testimony of the witnesses was. And the latter part of the instruction does not cure the error-in the former; for, while it says to the jury that they are-to determine the particular fact in dispute, of which he-was speaking, from the testimony of all the witnesses, touching it, the court had assumed to tell them positively what the testimony of two of the witnesses was, and upon which they might have felt bound to act, as being the testimony of those witnesses.
There are other alleged errors insisted upon, but they will not probably be repeated on another trial.
The judgment is reversed, with costs, and the cause is remanded for further proceedings, in accordance with, this opinion.