136 Minn. 401 | Minn. | 1917
July 24, 1914, plaintiff and defendants P. C. Giguere & Son entered into a written contract, by the terms of which defendants were to erect a warehouse for plaintiff on land owned by it in consideration of the sum of $58,500. To secure the faithful performance of this contract defendants Giguere & Son, as principal, and defendant American Surety Company, as surety, on August 4, 1914, executed and delivered to plaintiff a bond in the penal sum of $29,250. This action is on this bond, the breach alleged being the failure of the contractors to pay certain claims for material and labor, with the result that mechanics’ liens were filed against the property, which plaintiff was compelled to pay. The case was tried by the court without a jury, and a decision rendered in favor of plaintiff and against both principal and surety for the amount which plaintiff was thus compelled to pay with interest. Defendant
It is not disputed that the contractors failed to pay claims for material and labor, that the liens filed therefor were valid and enforceable, or that plaintiff was compelled to and did pay these claims to obtain releases of the liens. It is admitted that the contractors have not refunded to plaintiff any part of the sums so paid, as the contract required, and that the appellant has not indemnified plaintiff for this failure of the contractors to faithfully perform their contract. In brief, a breach of the bond and appellant’s liability therefor is clear, unless one or more of the defenses here urged is sustained. We will state and dispose of the contentions of appellant in their order.
There is one element in the present case that did not exist in any of the cases referred to, or at least received no attention from the court. This may be called the element of prejudice to the surety by the failure to apprise it of the contractors’ default. In the Lakeside Land Company case, referring to the case of U. S. Fidelity & Guaranty Co. v. Rice, 148 Fed. 206, 78 C. C. A. 164, the court -called attention to the provision in the bond in that case to the effect that, in the event of default on the part of the contractor, the surety should have the right, if it so desired, to assume or complete the contract, and be subrogated to all the rights and properties of the principal arising out of the contract. Mr. Justice Lewis noted that there was no such condition either in the bond or the contract in the ease then before the court, and distinguished the Bice case because of this provision. In the case at bar the bond does contain the provision that the party shall have the right, within 30 days after the receipt of such notice of the contractor’s default,- to proceed, or procure others to proceed, with the performance of such contract; shall be subrogated to all of the rights of the principal, and that any and all moneys or property that may, at the time of such default, be due or that thereafter may become due to the principal under said contract, shall be credited upon any claim which the obligee may then or thereafter have against the surety, and the surplus, if any, applied as the surety may' direct. It is argued that a notice of the failure to complete the building on time would have enabled the surety to exercise its option to take over the work, and that it would have thus saved the loss arising from the lien claims which the contractors failed to pay. But the evidence is conclusive that the failure to complete the building by the time specified was not regarded as a default of the contractors or a breach of their contract. The delay was partly caused by instructions
Appellant contends that the contractors were delayed in the prosecution and completion of the work by the act of the owner in directing them to go slow, and by the failure of the excavators, who were contractors employed by the owner, to diligently prosecute their work. It is claimed that this delay caused a serious loss to the contractors. But they made no claim for an extension of time, nor was there any submission of the amount of the loss to arbitration, as provided. The contractors do not appeal, and we need not consider the ease as between them and the plaintiff. The surety company seems to claim that it suffered damage by these delays, presumably for the reason that but for the delays the contractors could have done the work at less expense, and would have been able to pay at least some part of the claims for which liens were filed. Granting that the owner was responsible for the delay, and that the contractors had a just claim against it for the loss they sustained, they failed to take advantage of the remedy provided by the contract. We find no provision of the bond that releases the surety from liability or lessens its liability under such circumstances.
Order affirmed.