Plaintiff sued for damages for breach of a construction subcontract; judgment was entered in favor of the defendant. Thereafter plaintiff moved for a new trial; the motion was granted upon grounds of the insufficiency of the evidence to justify the decision and that the judgment was “against law.” Defendant appeals from the resulting order.
The subcontract was for demolition, site clearance and other work connected with the construction of an elementarv school in Torrance for which project plaintiff had been awarded the general contract. Bids were invited, and the low bid was eventually telephoned to plaintiff by one Andy Thomas on behalf of “Anderson Grading.” When plaintiff’s project manager proceeded to secure Anderson’s license number for inclusion in a contract then being drafted, he was given a number by the licensing agency which it had assigned to defendant Gibson. Another contract, the one here in suit, was then prepared by plaintiff and forwarded to Thomas. It was returned in executed form and signed: “H. C. Gibson, by Andy Thomas, Partner.” Although the law so provided (Gov. Code, §4104), 1 the above change admittedly was not communicated to the awarding authority—in this ease, the Torrance Unified School District; nor was the district’s consent to such change ever sought. Thus, in answer to written interrogatories, plaintiff declared that the name of the only subcontractor submitted to the public authority was “Anderson Grading, Garden Grove.”
Thomas, it appears, was married to a cousin of the defendant. He knew Gibson was a contractor, had been in his office in Brawley and had taken some of Gibson's letterhead stationery. He and an associate having commenced work on the Torrance job, on October 18 of 1960, a progress demand payment was forwarded to plaintiff on one of Gibson’s letterheads; the demand ostensibly bore defendant’s signature. Plaintiff refused payment because, among other *43 things, no bond had been posted by Thomas, and material suppliers were also asking to be paid. When work on the subcontract stopped, plaintiff’s manager insisted that Gibson perform. The latter refused, stating that he had no contract. Subsequently, after being importuned by material-men, Gibson asked plaintiff by letter to pay these suppliers. In response to this request, checks were sent to Gibson in the total amount of $15,059.15 and payable jointly to him and the suppliers. Defendant endorsed each check and sent it on to the other payee. He testified that he received nothing from the proceeds thereof.
On December 28, 1960, Gibson for the first time visited the job site. He again advised plaintiff’s project manager that he had no contract with plaintiff but offered to do the rest of the job for the unexpended balance of the contract price if plaintiff would give him a contract in his own name. Plaintiff elected to rely on the contract signed by Thomas, its project manager having testified that he was told by defendant, upon receipt of the contract in suit, that Thomas had authority to sign for him. (This was denied by defendant.)
Thereafter plaintiff finished the job. The damages sought represent the difference between the cost thereof and the contract price.
The court made findings of fact favorable to defendant from which it drew the conclusion of law that “plaintiff having listed Anderson Grading as a demolition and site clearance subcontractor on the Victor Elementary School Job, and never having sought permission to change such subcontractor, plaintiff is estopped by reason thereof from claiming against defendant Gibson or anyone except the principals of Anderson Grading. ’ ’ It further concluded that at no time did any contract exist between plaintiff and Gibson. Implicit in the above conclusions is the determination that plaintiff’s failure to comply with the applicable provisions of the statute then governing (Gov. Code, § 4104,-
supra)
barred its right to recovery. Unless the evidence would warrant a judgment in favor of the moving party, it is error to grant a new trial.
(Ellis
v.
City of Los Angeles,
*44
“ [I]t has been repeatedly declared in this state that ‘a contract made contrary to the terms of a law designed for the protection of the public and prescribing a penalty for the violation thereof is illegal and void, and no action may be brought to enforce such contract.' [Citation.]”
(Loving & Evans
v.
Blick,
We must now determine whether the imposition of the above penalty was for the purpose of regulating such transactions for the protection of the public—and not simply as a means of raising revenue (Cf.
Wood
v.
Krepps,
On the other hand, plaintiff also relies upon the
Klose
decision. It emphasizes the statement above quoted that the basic public policy of the subject sections “is not to grant rights to subcontractors,” arguing that there is nothing in former section 4104 which renders this contract void as between the parties. Cited in this connection is
Wood
v.
Krepps, supra,
Plaintiff also invokes the principle that " [a] bargain collaterally and remotely connected with an illegal purpose or act is not rendered illegal thereby if proof of the bargain can be made without relying upon the illegal transaction.” (Rest., Contracts, § 597.) Although imposing a penalty, the governing statutes do not declare the transaction at bar to be illegal per se; but considerations of public policy discussed in the
Klose
and
Early
cases require us to treat it as such
(Harriman
v.
Tetik,
Still another consideration militates against plaintiff’s position on this appeal. Section 4107 (renumbered § 4112 and amended by Stats. 1963) provides that, “The failure on the part of a contractor to comply with any provision of this chapter does not constitute a defense to the contractor in any action brought against him by a subcontractor.” No such privilege, on the other hand, is extended to the general contractor; the omission of the Legislature to do so is significant. “Under the familiar maxim of
expressio unius est exelusio alterius
it is well settled that, when a statute expresses certain exceptions to a general rule, other exceptions are necessarily excluded.”
(Collins
v.
City & County of San Francisco,
Plaintiff criticizes the decision of the trial court, nullified in effect by the order appealed from, that there was an estoppel to assert the claims contained in the complaint; it is contended that defendant, rather than plaintiff, is estopped to urge the illegality of the subject agreement. Defendant’s estoppel is said to be
in pais,
proceeding upon the theory that by its conduct or declarations defendant misled plaintiff to its prejudice.
(American National Bank of San Francisco
v.
A. G. Somerville, Inc.,
We recognize that there is “a wide range of exceptions” to the general rule that parties to an illegal contract cannot seek the assistance of the courts upon a breach thereof
(Harriman
v.
Tetik, supra,
The order is reversed.
Wood, P. J., and Fourt, J., concurred.
Respondent’s petition for a hearing by the Supreme Court was denied January 27, 1965.
Notes
Renumbered § 4107 and amended by Stats. 1963, eh. 2125, § 8.
