KEYES HELIUM COMPANY, LLC, CERTAIN UNDERWRITERS AND CERTAIN INSURANCE COMPANIES, SUBSCRIBING TO POLICY NO. B1740200667000, Plaintiffs-Appellants v. UNITED STATES, Defendant-Appellee
2024-1132
United States Court of Appeals for the Federal Circuit
June 23, 2025
NOTE: This disposition is nonprecedential.
Decided: June 23, 2025
BRET SUMNER, Beatty & Wozniak, P.C., Denver, CO, argued for plaintiff-appellant Keyes Helium Company, LLC.
SAMUEL J. DOLAN, Hall Maines Lugrin, PC, Houston, TX, argued for plaintiff-appellant Certain Underwriters and Certain Insurance Companies. Also represented by CAROLINE E. BOSSIER, MAURICIO RONDON.
JOSHUA DAVID TULLY, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by BRIAN M. BOYNTON, TARA K. HOGAN, PATRICIA M. MCCARTHY.
Before LOURIE, DYK, and REYNA, Circuit Judges.
LOURIE, Circuit Judge.
Keyes Helium Company, LLC and its subrogated insurers (collectively, “Keyes“) appeal from a final judgment of the United States Court of Federal Claims (“the Claims Court“) dismissing various claims arising from a contract for the storage and delivery of helium with the United States (“the government“). See Keyes Helium Co., LLC v. United States, 167 Fed. Cl. 283 (2023), J.A. 1-15. For the following reasons, we affirm-in-part, reverse-in-part, vacate-in-part, and remand.
BACKGROUND
The government, acting through the Bureau of Land Management (“BLM“), a division of the United States Department of the Interior, administers the federal helium program. See Helium Stewardship Act,
The Contract, which was renewed in August 2020, provided that BLM would store Keyes’ crude helium within the federal helium system subject to certain pre-conditions. For instance, the Contract required that for Keyes’ crude helium-gas volumes to be stored at BLM‘s facility, the gas
(a) The helium will be delivered to Person1 at Person‘s Delivery/Acceptance Point where the Federal Helium Pipeline is connected with a line that goes to Person‘s facilities, and in a helium-gas mixture containing not less than 50 percent helium by volume, and at a pressure existing in the system at the time and at the point of delivery, and will be delivered under conditions that permit suitable measurement and analysis specified by Article VI.
(b) Person agrees to compensate the United States, pursuant to Article VI, for any costs that the United States incurs to deliver a helium-gas mixture containing not less than 50 percent helium by volume.
Id. (emphasis added). Moreover, the contract contains no limitations on damages except for instances of force majeure, which is not at issue here. J.A. 57, § 9.1.
In opposition to the government‘s motion to dismiss, Keyes also asserted that its complaint sufficiently pleaded a claim for breach of an implied duty of good faith and fair dealing because it alleged facts sufficient to establish that BLM‘s delivery of “damaging levels of contaminants with the crude helium completely destroyed its ability to achieve the benefit of the bargain with the United States (i.e., transporting crude helium for refining and resale).”2 J.A. 148.
As an alternative to its breach of contract claims, Keyes alleged that the government would also have liability for damages sounding in tort in the District Court of the Northern District of Texas as a result of the government‘s off-spec deliveries. J.A. 37-38. It alleged that BLM failed to exercise its duty of reasonable care in “performing services relating to the delivery of helium” and “obtaining and/or disclosing information regarding the unacceptable and damaging levels of methane in the helium.” J.A. 37.
Finally, in addition to its claim for breach of contract and alternative tort claims, Keyes alleged a takings claim under the Fifth Amendment of the United States Constitution actionable under the Tucker Act,
The Claims Court dismissed all of Keyes’ claims, including its alternative tort claims, under Rule 12(b)(6) of the Rules of the United States Court of Federal Claims on August 31, 2023. Keyes timely appealed, and we have jurisdiction under
DISCUSSION
Keyes contends on appeal that the Claims Court erred in dismissing its breach of contract claims, alternative claim in tort, and takings claim. After consideration of all
The Claims Court may dismiss a complaint if it fails “to state a claim upon which relief can be granted.” RCFC, Rule 12(b)(6). “We review the Claims Court‘s dismissal for failure to state a claim de novo.” Oliva v. United States, 961 F.3d 1359, 1362 (Fed. Cir. 2020). To survive a motion to dismiss, the claimant must provide sufficient factual matter in its complaint to state a plausible claim for relief. Id. “We take all plausible factual allegations in the complaint as true and construe the facts in the light most favorable to the non-moving party.” Id.
Regarding the breach of contract claim, “[w]hether a contract creates a duty is a legal question of contract interpretation and thus freely reviewable by this court.” San Carlos Irr. & Drainage Dist. v. United States, 877 F.2d 957, 959-60 (Fed. Cir. 1989). The Claims Court determined that Keyes had failed to establish a breach because there was no “contractually explicit basis for its claim,” i.e., there was no relevant obligation under the Contract. Keyes, 167 Fed. Cl. at 292. We disagree.
The Claims Court correctly recited that “[t]o recover for breach of contract, a party must allege and establish: (1) a valid contract between the parties, (2) an obligation or duty arising out of the contract, (3) a breach of that duty, and (4) damages caused by the breach.” Id. at 290 (citing San Carlos, 877 F.2d at 959) (emphasis added). The court, however, overlooked its own recitation of the law, which explains that a breach of contract analysis necessarily flows from the alleged obligation identified in the contract. That is, once a duty is established under the contract at issue, we ask whether there was a breach of “that duty,” and, if so, then we ask whether there were any “damages
The Claims Court‘s analysis was therefore incorrect because it reverses the breach of contract analysis. Instead of identifying BLM‘s alleged obligations under the Contract and considering whether any had been breached, it started with the alleged harm and attempted to identify a “contractually explicit basis,” or obligation, that flowed from that harm. Keyes, 167 Fed. Cl. at 292. Specifically, the Claims Court began its analysis by stating that “[h]ere, the harm detailed at length by plaintiff centers on measured methane levels in defendant‘s deliveries to plaintiff.” Id. It then concludes that because there is no obligation that corresponds to that harm, there can be no breach. See id. (“neither the contract nor plaintiff indicates how the detection of elevated methane levels is related to any contractual obligation.“). That was error. The question is not whether “produced methane levels trigger any duty owed by defendant under the contract,” id., as the Claims Court states; it is whether the Contract prescribes an obligation of BLM that Keyes has plausibly shown to have been breached by BLM. And only after that is established, can one undertake a proper causation analysis to determine whether there are any “damages that stem from the breach.” Id. (citing San Carlos, 877 F.2d at 959).
Here, Keyes’ complaint plausibly establishes that (1) the Contract imposes an obligation on BLM‘s delivery, and (2) BLM subsequently breached that obligation. The Contract clearly obligated BLM to deliver “a helium-gas mixture containing not less than 50 percent helium by volume.” J.A. 47-48, § 2.3(a) (emphasis added). And Keyes identifies at least two alleged instances where BLM delivered off-spec helium gas mixtures, including on December 15, 2020, and February 27, 2021. See J.A. 29-31 (December 2020
BLM relies on the Claim Court‘s interpretation “that [Section 2.3(b) of] the Contract ‘anticipates that a delivery may contain less than 50 percent helium, and allows that in such an instance, defendant is not obligated to pay for the nonconforming delivery.‘” Appellee Br. 15 (citing Keyes, 167 Fed. Cl. at 292; J.A. 48 § 2.3(b)). It argues that because Section 2.3(b) anticipates off-spec deliveries and that “in those circumstances, Keyes Helium is not obligated to pay,” Appellee Br. 28, Section 2.3(b) of the Contract therefore operates to negate BLM‘s liability for off-spec deliveries, id. at 30. But Section 2.3(b) merely provides that Keyes agreed to compensate BLM for costs that it incurred for on-spec deliveries under Section 2.3(a), i.e., deliveries that contains “not less than 50 percent helium by volume.” J.A. 47-48, § 2.3(a). It does not absolve BLM of its liability for an express breach of Section 2.3(a).
In addition to alleging that the government breached its obligation to deliver a helium-gas mixture composed of not less than 50% helium under Section 2.3, the complaint also alleged that the government breached its agreement with Keyes by “[f]ailing to follow industry standard by delivering crude helium with methane levels more than double the amount generally accepted in the industry.” J.A. 36. Helium industry standards allegedly set the maximum limit for methane in helium-gas mixtures at around
The Claims Court‘s dismissal of Keyes’ breach of contract claim must therefore be reversed. This claim survives the 12(b)(6) stage and is remanded for further proceedings. On the merits, the court should consider whether Keyes’ plausibly alleged breach of BLM‘s delivery obligation under Section 2.3(a) is causally connected to the resultant harm, i.e., whether it was reasonably foreseeable that an off-spec helium gas mixture could contain elevated methane levels sufficient to cause damage to Keyes’ facility and operations. Damages for breach of contract are recoverable where: “(1) the damages were reasonably foreseeable by the breaching party at the time of contracting; (2) the breach is a substantial causal factor in the damages; and (3) the damages are shown with reasonable certainty.” Kansas Gas & Elec. Co. v. United States, 685 F.3d 1361, 1369 (Fed. Cir. 2012) (quotations and citation omitted).
Turning to the next issue, the Claims Court, while acknowledging that Keyes “did not enumerate a separate claim for breach of the implied duty of good faith and fair dealing,” nonetheless held that such claim “must fail for the same reason that its breach of contract claim does.” See
On remand, the Claims Court should heed its own words, which explained that “[i]mplied in every contract is a duty of good faith and fair dealing.” Keyes, 167 Fed. Cl. at 292 (citing Precision Pine & Timber, Inc. v. United States, 596 F.3d 817, 828 (Fed. Cir. 2010). And while, as the court states, “[t]he implied duty of good faith and fair dealing ... ‘cannot expand a party‘s contractual duties beyond those in the express contract,” Keyes, 167 Fed. Cl. at 292 (citing Precision, 596 F.3d at 831), “all that the quoted language means is that the implied duty of good faith and fair dealing depends on the parties’ bargain in the particular contract at issue,” Metcalf Const. Co. v. United States, 742 F.3d 984, 994 (Fed. Cir. 2014).
The question therefore is not whether “[t]he contract imposes [a] duty on defendant to monitor the methane levels in its deliveries,” Keyes, 167 Fed. Cl. at 292, because “[t]hat goes too far: a breach of the implied duty of good faith and fair dealing does not require a violation of an express provision in the contract.” See Metcalf, 742 F.3d at 994 (rejecting the government‘s “constrain[ed] view ... that there was no breach of the implied duty because ‘Metcalf cannot identify a contract provision that the Navy‘s inspection process violated‘“). Instead, the question is whether Keyes’ complaint plausibly establishes that BLM‘s alleged breach of an implied duty frustrated Keyes’ bargained-for benefit under the Contract, i.e., receiving volumes of crude helium gas that it could refine and sell to its customers. See id. 994-95 (explaining that “[t]he implied duty of good faith and fair dealing ... prevents a party‘s
The Claims Court also dismissed Keyes’ alternative tort claim because it determined that it too rose and fell with its contract claim. See Keyes, 167 Fed. Cl. at 293 (holding that because “[Keyes‘] breach of contract claim cannot stand ... neither can [Keyes‘] allegedly related tort claim“). Again, because the court‘s breach of contract analysis is flawed and because it relied on that analysis to dismiss the tort claim, we must vacate and remand its dismissal of that claim. On remand, the court should determine whether Keyes’ “action sounds in contract,” or whether Keyes “has stated an independent action in tort.”3 Awad v. United States, 301 F.3d 1367, 1372 (Fed. Cir. 2002). If Keyes’ “action sounds in contract,” it “is properly within the jurisdiction of the Court of Federal Claims.” Id. If not, the court should either dismiss or transfer the independent tort claims accordingly.
Finally, we turn to Keyes’ takings claim under the Fifth Amendment. As the Claims Court explained, “[Keyes] claims that its lost helium is the property interest at issue.” Keyes, 167 Fed. Cl. at 293. On appeal, Keyes claims that it actually has two independent property rights at issue here: its “property interest in its facilities” and its property interest in “lost helium volumes.” Appellant Br. 42. Regardless, Keyes’ complaint regarding its takings claim, with respect to either property interest, was appropriately dismissed for failure to state a claim.
CONCLUSION
We have considered Keyes remaining arguments and find them unpersuasive. For the foregoing reasons, we reverse the Claims Court‘s decision with respect to the breach of contract claim, vacate with respect to the implied duty of good faith and fair dealing and alternative tort claims, affirm with respect to the takings claim, and remand for consideration consistent with this opinion.
AFFIRMED-IN-PART, REVERSED-IN-PART, VACATED-IN-PART, AND REMANDED
COSTS
No costs.